Sounding Research Report No. 20260724-105810

Study-Area Permit & Infrastructure Report

Lake Mary Boulevard Corridor

Seminole County, Florida

150.0Study area · ac
23Permits governing
18Superseded records
544Documents retrieved
7,421Pages indexed

Incomplete: extraction pending for 2 of 23 governing permits (191235-3, 48694-7) — see Part 07. A production report does not finalise in this state.

Prepared 10 August 2026 · Source SJRWMD public ERP records, queried 2026-07-24

This report compiles and summarises public regulatory records. It is not engineering design, not a regulatory determination, and not sealed work. The permit file of record governs.

Part 01

Study area searched

The geometry this report was swept from — 150.0 acres, geodesic, as submitted. Same coordinates, same index: same sweep.

21945-1922463-248694-749830-369432-171294-176767-376781-385947-186365-1087951-198061-198533-198636-1103055-1108660-2110309-1114454-14123954-1141317-1191235-3214983-1237414-1 N 2,000 ft NW · -81.32800, 28.76000 SE · -81.32000, 28.75300

Teal: the boundary as queried. Grey: the 23 governing permits’ recorded footprints, clipped at the frame — one running off it is a permit far larger than this study area.

Geodesic area150.0 ac
Vertices5
Bounding box-81.32800, 28.75300 → -81.32000, 28.76000
Geometry fingerprintSHA-256 ef7112e961c7b315…
Index layerlayer 2
Queried2026-07-24

Boundary coordinates (WGS84 lon, lat)

-81.328000, 28.753000
-81.320000, 28.753000
-81.320000, 28.760000
-81.328000, 28.760000
-81.328000, 28.753000

GeoJSON delivered in the source set; the fingerprint is the SHA-256 of its coordinates array.

Part 02

Executive summary

The study area contains 23 governing Environmental Resource Permits, carrying 544 documents across 7,421 pages. A further 18 permit records were returned and resolved as superseded — earlier sequences of permits that remain in the District index but no longer govern.

Extraction is complete for 21 of 23 governing permits: 525 regulatory criteria and 222 stormwater structures, each counted once. (68 duplicate extractions consolidated) 827 of 833 citations passed page-location verification — the quoted support was found on the cited page. 6 failed and are quarantined in Part 09. Location is not interpretation; see Method.

Pending: extraction has not run for 191235-3, 48694-7 — inventory and index rows complete, registers and summaries not. Each card says so.

For 9 of the 23 governing permits, every retrieved document is from an earlier sequence of the file — labelled per entry, and read as file history (Method — Sequence lineage).

164 citations were read from deeper than any permit letter or staff report in this record runs — Part 04 sets out where.

Document mix

25Permit
22Technical Staff Report
34Drainage calculations
46Construction plans
54Request for additional information
4As-built
1Certification of completion
26Application
250Correspondence
82Other

Part 03

Permit inventory & supersession

Every ERP record the SJRWMD index returned for this boundary (layer 2, queried 2026-07-24). Governing permits are listed first; superseded sequences follow, indented under the permit number they belong to. Completeness here means the index’s completeness as of that date — see Method for what the index does and does not cover.

PermitProjectApplicantRule typeDecidedStatus
103055-1 CNBS - Lake Mary CNBS Properties LLC ERP Stormwater Standard General (40C) 2006-03-23 Governing
108660-2 Washington Estates Washington Estates Property Owners Association, Inc. ERP Stormwater Standard General (40C) 2014-03-28 Governing
110309-1 CR 15 from Ranoul Lane to CR 46A Department of Public Works Engineering Division ERP Stormwater Standard General (40C) 2007-08-07 Governing
114454-14 Central Florida Commuter Rail - Lake Mary Station Florida Department of Transportation - District 5 ERP Standard General (40C) 2013-12-17 Governing
114454-6 Central Florida Commuter Rail - Lake Mary Station Florida Department of Transportation - District 5 ERP Standard General (40C) 2009-05-21 Superseded
114454-1 Central Florida Commuter Rail Transit - Phase 1 Florida Department of Transportation - District 5 ERP Individual w/ SSL (40C) 2008-10-14 Superseded
123954-1 Carli Professional Office Building D & B Carli LLC ERP Stormwater Standard General (40C) 2010-06-15 Governing
141317-1 Lake Mary Pediatric Medical Office Urgent Care Developers of West Lake Mary, LLC ERP Individual (<40 ac no WL <12 IMP) 2015-04-10 Governing
191235-3 City of Lake Mary Downtown Redevelopment Stormwater Park City of Lake Mary ERP Individual 2023-03-03 Governing
214983-1 South Country Club Drainage Improvements Seminole County - Chief Design Engineers ERP General 2024-03-07 Governing
21945-19 Lake Mary Boulevard , Phase II: pedestrian overpass (Ltr Mod) Seminole County Board of County Commissioners MSSW Individual 2005-12-30 Governing
21945-17 City of Lake Mary-City Hall City of Lake Mary ERP Standard General (40C) 2004-05-28 Superseded
21945-11 Lake Mary Boulevard widening: County Club Rd to US 17-92 ( Phase II) Seminole County Board of County Commissioners MSSW Individual 1993-10-12 Superseded
21945-3 Lake Mary Boulevard widening: County Club Rd to US 17-92 Seminole County Engineering MSSW Individual 1988-06-07 Superseded
21945-2 Lake Mary Boulevard expansion: Markham Woods Rd to Country Club Dr Jerry McCollum MSSW Individual 1988-05-09 Superseded
22463-2 Woodbridge Lk Phase 2C Olympia Homes Inc ERP Individual (40C) 1999-09-07 Governing
237414-1 Crystal Lake Condos ACC Trust ERP Individual 2025-12-29 Governing
48694-7 Lake Mary Elementary School Seminole County Public Schools ERP Individual 2026-03-05 Governing
48694-6 Lake Mary Elementary School Seminole County Public Schools ERP Individual 2026-01-09 Superseded
48694-2 SEMINOLE COUNTY SCHOOL BOARD Seminole County School Board ERP Stormwater Standard General (40C) 1991-06-27 Superseded
48694-1 LAKE MARY ELEMENTARY SCHOOL ERP Stormwater Standard General (40C) 1987-11-10 Superseded
49830-3 Rainbow Child Care Center EIG14T RCCC 200 FL - Lake Mary LLC ERP Individual (<40 ac no WL <12 IMP) 2018-04-13 Governing
49830-2 Rainbow Child Care Center EIG14T RCCC 200 FL - Lake Mary LLC ERP Individual (<40 ac no WL <12 IMP) 2017-11-21 Superseded
49830-1 ZANCA OFFICE SITE Starcraft Homes ERP Stormwater Standard General (40C) 1998-04-13 Superseded
69432-1 JR Academy of Lake Mary JR Academy of Lake Mary ERP Stormwater Standard General (40C) 2001-01-26 Governing
71294-1 Regency Pointe Commercial/Professional Center Delro Properties, Inc. ERP Stormwater Standard General (40C) 2001-09-17 Governing
76767-3 Cold Mix Paving of City's dirt streets - all phases City of Lake Mary ERP Stormwater Standard General (40C) 2006-07-24 Governing
76781-3 City of Lake Mary Police Station Retention Pond City of Lake Mary ERP Stormwater Standard General (40C) 2013-05-22 Governing
76781-1 NEW POLICE STATION City of Lake Mary ERP Stormwater Standard General (40C) 1999-05-18 Superseded
85947-1 Medlin Professional Office EEMJ/SM Family Trust ERP Stormwater Standard General (40C) 2002-10-29 Governing
86365-10 Seminole Ave Pond Expansion City of Lake Mary ERP Individual 2020-09-17 Governing
86365-8 Shaw Office Complex (Transfer) City of Lake Mary ERP Standard General (40C) 2019-10-31 Superseded
86365-7 4th Street Complex Shaw Construction and Management Services Inc ERP Standard General (40C) 2017-09-01 Superseded
86365-6 Shaw Office Complex Shaw Construction and Management Services Inc ERP Standard General (40C) 2013-12-06 Superseded
86365-4 Shaw Office Complex Shaw Construction & Management Svcs Inc ERP Standard General (40C) 2009-10-02 Superseded
86365-3 Shaw Office Complex Shaw Construction And Management Inc. ERP Standard General (40C) 2008-07-18 Superseded
86365-2 Shaw Office Buildings Shaw Construction Inc ERP Stormwater Standard General (40C) 2007-08-27 Superseded
87951-1 GTE Federal Credit Union-Lake Mary GTE Federal Credit Union ERP Stormwater Standard General (40C) 2003-05-19 Governing
98061-1 Cambridge Prep School - Lake Mary Blvd. Lake Mary Cambridge LLC ERP Stormwater Standard General (40C) 2005-06-03 Governing
98533-1 Watson Center at Lake Mary Watson Realty Corp ERP Stormwater Standard General (40C) 2006-07-03 Governing
98636-1 Ruskin St, Johnson Ave, & S 4th St Paving & Drainage Improvements City of Lake Mary ERP Stormwater Standard General (40C) 2005-05-19 Governing

Part 04

Constraints found at depth

No permit letter or technical staff report in this study area runs past page 20. Those are the documents a file search reads. 164 of the 833 citations in this report were read from a page deeper than that — inside calculation books, bound submittals and as-built sets running to 450 pages — and 91 of those carry binding regulatory criteria.

164Citations past page 20
66Past page 50
91Binding criteria among them
15 of 21Permits with findings at depth

Deepest finding in each permit’s file

PermitFindingSource documentIn filePage
22463-2 structureUnderdrain systemRetention Tract A2 underdrain system: 6-in drains, treatment volume 37,026 cf, 3-day recovery design (Universal… Drainage calculations20 Mar 2007 219/450
71294-1 criterionTreatment volume recovery time0.1610 days total recovery time; 100% of 21,519 cf runoff volume recovered Drainage calculations22 Sep 2006 158/313
86365-10 criterionTreatment volume recovery 72hrFull treatment volume (10,480 cf) infiltrated, pond stage down to 50.55 ft at 72 hours after slug load Drainage calculations7 Jan 2008 103/104
21945-19 structureSide drain filterSide-drain filter (underdrain) analyzed for drawdown using Darcy's law on a handwritten Mizo, Hill & Glass… As-built set17 Sep 2007 88/89
49830-3 structureStorm collection systemOn-site collection per site plan: Type C inlets (grate EL 52.00 and 53.00) and Type P7 storm manholes (inv EL… Drainage calculations30 Jan 2006 72/72
141317-1 criterionRequired treatment volume0.10 ac-ft Drainage calculations18 Mar 2015 56/65
98636-1 criterionHydrologic soil groupsRuskin Street and South 4th Street soils are NRCS Hydrologic Group A; Johnson Avenue soils are Group B Drainage calculations25 Apr 2005 52/53
98533-1 criterionPond B 36-hour recoveryFull 4,108 ft3 treatment volume infiltrated by 36 hours; stage down to 50.36 ft datum Drainage calculations31 May 2006 49/51
110309-1 criterionSeasonal high groundwater3.5 to 6 feet below existing ground in vicinity of proposed culvert (per SCS Soil Survey) ft below grade Drainage calculations15 Mar 2007 45/59
69432-1 structureControl structure orificeSingle circular weir/gate/orifice control structure (reach OUT) from pond to outfall, invert elevation 59.610 ft… Drainage calculations22 Sep 2006 42/44
85947-1 criterionGeotechnical stormwater design parametersUniversal Engineering Sciences Table 3: depth of confining layer 3 ft, horizontal saturated hydraulic conductivity… Drainage calculations9 Feb 2007 42/63
123954-1 criterionSeasonal high groundwater elevation ft48.75 ft Drainage calculations17 Mar 2010 35/77

Depth is not importance. A long document is not automatically a significant one, and a number on page 3 of a permit can bind a site harder than anything in an appendix. What this measures is where in the file the governing numbers sit — here, spread across 17 documents, past the page a reader of the permit and the staff report stops turning. A further 3 permits carry findings below the summary layer as well. Every finding counted here appears in the registers that follow, with its citation.

Part 05

Special regulatory criteria register

Binding conditions carried by permits in the study area — the constraints a new design here has to answer to. Each entry cites the document and page it was read from.

CNBS - Lake Mary 103055-129 governing-sequence
Water-quality treatment
greater of 1 inch of runoff from the entire drainage basin, or 1.25 inches over the impervious areas plus 0.5 inch of runoff from the drainage basinDrainage calculations·5 Sep 2008·p.5
“The first inch (1") of runoff from the entire drainage basin or one and a quarter inches (1.25")”
Treatment volume required
0.087 ac-ftDrainage calculations·5 Sep 2008·p.9
“0.087 ac. Ft”
Design storm attenuation sjrwmd
post-development discharge rate and volume must be less than or equal to pre-development for the Mean Annual/24-hour storm eventDrainage calculations·5 Sep 2008·p.5
“Development Condition based on a Mean Annual/24-Hr. storm event.”
Design storm attenuation city
post-development discharge rate and volume must be less than or equal to pre-development for the 25-year/24-hour storm event (City of Lake Mary)Drainage calculations·5 Sep 2008·p.5
“Development Condition based on a 25Yr./24Hr. storm event.”
Treatment volume recovery
72 hours with 50% factor of safetyDrainage calculations·5 Sep 2008·p.5
“Recovery of the treatment volume within 72 Hours with 50% factor of safety.”
Wet season water table elevation
51.02 ftDrainage calculations·5 Sep 2008·p.4
“wet season water table (WSWT) at elevation 51.02.”
Design storm rainfall 25yr 24hr
8.6 inchesDrainage calculations·5 Sep 2008·p.16
“Rainfall Amount (in): 8.600”
Design storm rainfall mean annual 24hr
4.4 inchesDrainage calculations·5 Sep 2008·p.16
“Rainfall Amount (in): 4.400”
Pre development peak discharge 25yr 24hr
1.907 cfsDrainage calculations·5 Sep 2008·p.16
“1.907”
Receiving water body
Crystal Lake (via small retention area east of site)Drainage calculations·5 Sep 2008·p.4
“which then flows into Crystal Lake located north of the site.”
Treatment volume
3790 ft3Drainage calculations·28 Dec 2005·p.10
“3790”
Allowable discharge cfs
1.907 (pre-development peak discharge, 25-yr/24-hr storm; post-development discharge must not exceed pre-development) cfsDrainage calculations·28 Dec 2005·p.12
“Flow Max (cfs): 1.907”
Pre development peak discharge mean annual
0.817 cfsDrainage calculations·28 Dec 2005·p.12
“Flow Max (ef s): 0.817”
Permit number
42-117-103055-1Permit·23 Mar 2006·p.1
“PERMIT NO. 42-117-103055-1”
Permit issue date
March 23, 2006Permit·23 Mar 2006·p.1
“DATE ISSUED: March 23, 2006”
Regulatory authority
Chapter 40C-42, F.A.C. (SJRWMD regulation of stormwater management systems)Permit·23 Mar 2006·p.1
“CHAPTER 40C-42, F.A.C.”
Construction permit expiration
5 years from date of issuancePermit·23 Mar 2006·p.3
“This permit for construction will expire five years from the date of issuance unless otherwise”
As built certification
As-built certification form must be completed within 30 days of completion of construction of the permitted system, including all site workPermit·23 Mar 2006·p.1
“Complete this form within 30 days of completion of construction of the permitted system,”
Pre discharge excavation condition
retention and detention storage must be excavated to rough grade prior to building construction or placement of impervious surface, before any offsite discharge occursPermit·23 Mar 2006·p.3
“Before any offsite discharge from the stormwater management system occurs, the retention”
Soils analysis condition
as-built report must include a soils analysis of the retention pond verifying that the design permeability rates are provided; otherwise a permit modification is requiredPermit·23 Mar 2006·p.5
“Contained within the as-built report, the permittee must submit a soils analysis of the”
Inspection requirement
O&M entity must inspect the system once within two years after completion of construction and every two years thereafterPermit·23 Mar 2006·p.5
“management system once within two years after the completion of construction and every”
Exceptions report
if the system is not functioning as designed and permitted, an Exceptions Report (form 40C-42.900(6)) must be submitted to the Altamonte Springs Service Center within 14 daysPermit·23 Mar 2006·p.5
“If at any time the system is not functioning as designed and permitted, then within 14 days”
Receiving water body
Crystal Lake, Lake JesupTechnical Staff Report·23 Mar 2006·p.1
“Crystal Lake,Lake Jesup”
Receiving water class
Class III FreshTechnical Staff Report·23 Mar 2006·p.1
“III Fresh.”
Special basin criteria
N/A (no special basin criteria apply; value listed as N/A on the line following this label)Technical Staff Report·23 Mar 2006·p.1
“Special Basin Criteria:”
Water quality treatment recovery
system designed to recover its required treatment volume within 72 hoursTechnical Staff Report·23 Mar 2006·p.2
“within 72 hours, and also attenuate the pre versus post discharge for the mean annual”
Design storm
pre versus post discharge attenuated for the mean annual stormTechnical Staff Report·23 Mar 2006·p.2
“attenuate the pre versus post discharge for the mean annual”
Pond recovery dependency
pond recovery depends upon the new fill material proposed for the siteTechnical Staff Report·23 Mar 2006·p.2
“It should be noted that the pond recovery depends upon the new fill material that”
Soils analysis condition
as-built report must include a soils analysis of the retention pond verifying design permeability rates; otherwise a permit modification is requiredTechnical Staff Report·23 Mar 2006·p.2
“the permittee must submit a soils analysis of”
Washington Estates 108660-20 governing-sequence · 19 file history
Lineage: every attributable document here is from seq 1 (documents dated 2006–2008) — none from governing seq 2 (“Washington Estates”, 2014). Entries below are file history, not the governing record.
Water-quality treatment
Treatment volume retained in the proposed pond; percolates (perks) within 36 hoursseq 1Drainage calculations·21 Feb 2007·p.1
“the proposed pond and perks within thirty-six (36) hours.”
Retention system rule criteria
Retention system meets Subsection 40C-42.026(2) F.A.C.seq 1Drainage calculations·21 Feb 2007·p.1
“The retention system meets the criteria at Subsection 40C-42.026(2) F.A.C.”
Wekiva river basin
Project is not in the Wekiva River Basin; it is in the Soldier Creek Basinseq 1Drainage calculations·21 Feb 2007·p.1
“The project is not in the Wekiva River Basin.”
Water-quality treatment
11,416 ft3 retained (0.5 in plus an additional 0.5 in for dry retention); recovers within 36 hoursseq 1Drainage calculations·21 Feb 2007·p.3
“be 11,416 ft3. This volume recovers within thirty-six (36) hours”
Allowable discharge cfs
Pre-development discharge 8.11 cfs (rational method) / 7.409 cfs (ICPR); post-development discharge must be lessseq 1Drainage calculations·21 Feb 2007·p.3
“= CIA + (0.3) (8.6) (3.145) = 8.11 per the rational method and1 7.409 per ICPR”
Peak discharge cfs
4.7177 cfs maximum system discharge, 25-yr/24-hr storm (less than pre-development)seq 1Drainage calculations·21 Feb 2007·p.3
“storm event is 4.7 177 CFS, which is less than the pre-development discharge of Q”
Peak stage
52.80 ft maximum stage, 25-yr/24-hr storm (top of pond 53.80 ft)seq 1Drainage calculations·21 Feb 2007·p.4
“(52.80') feet and the top of pond fifty-three point eighty (53.80') feetJ which gives”
Peak stage 100yr ft
52.96 ft maximum stage, 100-yr/24-hr storm (below top of pond 53.80 ft)seq 1Drainage calculations·21 Feb 2007·p.4
“fifty-two point ninety-six (52.96') feet, which is less than the top of pond”
Freeboard ft
1.0 ft of freeboard at the 25-yr/24-hr maximum stageseq 1Drainage calculations·21 Feb 2007·p.4
“one (1') foot of freeboard.”
Design storm
25-yr/24-hour (discharge control) and 100-yr/24-hour (stage check)seq 1Drainage calculations·21 Feb 2007·p.3
“of Calculations. The maximum discharge for the system for thF 25-yr/24-hour”
Floodplain
Flood Zone C; site not affected by the 100-year flood (no floodplain compensation involved)seq 1Drainage calculations·21 Feb 2007·p.4
“The site is in flood zone C and is not affected by the 100-year flood.”
Permit expiration
Construction permit expires five years from the date of issuanceseq 1Permit·27 Mar 2007·p.3
“This permit for construction will expire five years from the date of issuance unless otherwise”
Construction sequencing
Retention and detention storage must be excavated to rough grade prior to building construction or placement of impervious surface, before any offsite discharge occursseq 1Permit·27 Mar 2007·p.3
“Before any offsite discharge from the stormwater management system occurs, the retention”
As built certification
As-built certification by a registered professional due within 30 days after completion of the stormwater systemseq 1Permit·27 Mar 2007·p.3
“If the permitted system was designed by a registered professional, within 30 days after”
Om inspection
O&M entity must inspect the system once within two years after completion of construction and every two years thereafterseq 1Permit·27 Mar 2007·p.5
“management system once within two years after the completion of construction and every”
Receiving water body
Soldier Creek, Class III Freshseq 1Technical Staff Report·27 Mar 2007·p.1
“Soldier Creek”
Special basin criteria
N/A (no special basin criteria apply)seq 1Technical Staff Report·27 Mar 2007·p.1
“Special Basin Criteria:”
Water-quality treatment
Retention of one inch of runoff so post-development phosphorus loading does not exceed pre-development loading inchesseq 1Technical Staff Report·27 Mar 2007·p.2
“will not exceed the pre-development loading of phosphorous by retaining one inch of”
Treatment type
Retentionseq 1Technical Staff Report·27 Mar 2007·p.1
“Retention”
CR 15 from Ranoul Lane to CR 46A 110309-120 governing-sequence
Design storm
25-year/24-hourDrainage calculations·15 Mar 2007·p.24
“25 yr/24 hr Runoff”
Design storm rainfall depth
8.6 inDrainage calculations·15 Mar 2007·p.24
“8.6”
Water-quality treatment
Treatment volume criterion of 2.50 inches over new impervious areaDrainage calculations·15 Mar 2007·p.23
“New imp Area * 2.50”
Water quality treatment volume
0.20 ac-ftDrainage calculations·15 Mar 2007·p.23
“0.20”
Receiving wetland nhw elevation
47.5 ftDrainage calculations·15 Mar 2007·p.4
“has a NHW elevation of 47.5”
Floodplain compensation
None required; project outside 100-year floodplainDrainage calculations·15 Mar 2007·p.6
“The project is outside of the 100-year floodplain.”
Wetland mitigation
None required; no wetland impacts proposedDrainage calculations·15 Mar 2007·p.34
“No mitigation is required as no wetland impacts are proposed.”
Seasonal high groundwater
3.5 to 6 feet below existing ground in vicinity of proposed culvert (per SCS Soil Survey) ft below gradeDrainage calculations·15 Mar 2007·p.45
“estimated seasonal high groundwater table ranging between 3.5 and 6 feet below existing”
Permit construction expiration
5 years from date of issuance (issued August 7, 2007)Permit·7 Aug 2007·p.3
“This permit for construction will expire five years from the date of issuance”
Water-quality treatment
Stormwater treatment by best management practicesPermit·7 Aug 2007·p.1
“Stormwater Management System with stormwater treatment by best”
As built certification
As-built certification form due within 30 days of completion of constructionPermit·7 Aug 2007·p.1
“Complete this form within 30 days of completion of construction of the permitted system,”
Pre discharge condition
Retention and detention storage must be excavated to rough grade before any offsite discharge occursPermit·7 Aug 2007·p.3
“Before any offsite discharge from the stormwater management system occurs, the retention”
Operation inspection frequency
Inspect system within two years after completion of construction and every two years thereafterPermit·7 Aug 2007·p.5
“once within two years after the completion of construction and every”
Dewatering consumptive use threshold
Consumptive Use Permit (40C-2) required if dewatering facilities can withdraw 1,000,000 gpd or more, or average 100,000 gpd over a year, with off-site dischargePermit·7 Aug 2007·p.2
“capable of withdrawing one million gallons of water per”
Receiving water body
Crystal LakeTechnical Staff Report·7 Aug 2007·p.1
“Crystal Lake”
Receiving water class
Class III FreshTechnical Staff Report·7 Aug 2007·p.1
“III Fresh.”
Water-quality treatment
Best Management PracticesTechnical Staff Report·7 Aug 2007·p.1
“Best Management Practices”
Special basin criteria
N/A (no special basin criteria apply)Technical Staff Report·7 Aug 2007·p.1
“Special Basin Criteria:”
Roadway pavement exemption
New roadway pavement meets exemption under 40C-42.0225(5)(c), F.A.C., for road widening that will not create additional traffic lanesTechnical Staff Report·7 Aug 2007·p.2
“roadway pavement meets the exemption under 40C-42.0225(5)(c), F.A.C., for road”
Operation inspection frequency
System inspection within two years of construction completion and every two years thereafter; Exceptions Report within 14 days if not functioning as designedTechnical Staff Report·7 Aug 2007·p.2
“construction and every two years thereafter to determine if the system is”
Central Florida Commuter Rail - Lake Mary Station 114454-140 governing-sequence · 57 file history
Lineage: every attributable document here is from seq 1 (“Central Florida Commuter Rail Transit - Phase 1”, 2008) — none from governing seq 14 (“Central Florida Commuter Rail - Lake Mary Station”, 2013). Entries below are file history, not the governing record.
Water-quality treatment
Swales and swales with blocks must retain and infiltrate the treatment volume of 1 inch of runoff from the project area (Chapter 40C-42, F.A.C.); compensating treatment of existing-track runoff where right-of-way is lackingseq 1Technical Staff Report·14 Oct 2008·p.9
“swales and swales with blocks to retain and infiltrate the treatment volume of 1 inch of”
Attenuation requirement
Surface water management systems must provide attenuation of the required storm events pursuant to Chapter 40C-4, F.A.C.seq 1Technical Staff Report·14 Oct 2008·p.9
“required storm events pursuant to Chapter 40C-4, F.A.C.”
Wetland impacts authorized
Work in, on, or over 7.44 acres of wetlands or other surface waters (rail-side ditches) authorized; total construction work in 9.46 acres of wetlands and other surface watersseq 1Technical Staff Report·14 Oct 2008·p.7
“over 7.44 acres of wetlands or other surface waters (rail-side ditches).”
Wetland impacts requiring mitigation
7.920 acresseq 1Technical Staff Report·14 Oct 2008·p.12
“7.920”
Wetland mitigation
6.173 acres of impacts (Wekiva River Nested basin 15 + St Johns River basin 18) mitigated via Section 373.4137, F.S.; Lake Jesup basin (23) impacts of 1.747 acres offset by 8.3 acres of the ~20-acre Joanne Logue Parcel donated to the Districtseq 1Technical Staff Report·14 Oct 2008·p.14
“Mitigation to offset the 6.173 acres of impacts to wetlands and other surface waters”
Wetland mitigation funding
$50,000 to fund restoration and enhancement of the mitigation parcel plus $500/acre for long term management USDseq 1Technical Staff Report·14 Oct 2008·p.15
“the District receives title to the property, the amount of $50,000 to fund restoration”
Turbidity monitoring
During St. Johns River bridge construction, downstream turbidity must not exceed State Water Quality Standards; twice-daily sampling and weekly reporting requiredseq 1Technical Staff Report·14 Oct 2008·p.14
“If at any time the downstream turbidity level exceeds the State Water Quality”
Sovereign lands easement
Public easement pre-empting 1.195 acres of sovereign submerged lands of the St. Johns River, within the Wekiva River Aquatic Preserveseq 1Technical Staff Report·14 Oct 2008·p.17
“empting 1.195 acres as shown on the surveyors' certification for SSL Easement Parcel”
Safe upland line elevation ft
2.80 ft NGVD29seq 1Technical Staff Report·14 Oct 2008·p.17
“bound by the Safe Upland Line provided by FDEP of elevation 2.80 feet (NGVD29).”
Project area
203.66 acresseq 1Drainage calculations·12 Dec 2007·p.6
“Total Area 203.66”
Design storm
25-year 24-hour storm event, 8.4 inches (Central Florida); used to compare pre- vs post-development flows per SJRWMD criteriaseq 1Drainage calculations·12 Dec 2007·p.9
“The 25-year 24-hour storm event used for Central Florida was 8.4 inches.”
Total floodplain encroachment
1.94 acre-feetseq 1Drainage calculations·12 Dec 2007·p.10
“The total encroachment for the area of double tracking for the project is 1.94 ac-ft.”
Cross drain allowable headwater
11 culverts extended; post-development headwater elevations below allowable headwater at every crossing; max headwater difference 1.55 ft at 98"x63" RCP (Sta 40925+36, allowable 43.10 ft)seq 1Drainage calculations·12 Dec 2007·p.12
“98"x63" RCP 38.20 39.75 43.10 1.55”
Culvert extension base flood elevation
84" RCP (Sta 40884+73): 100-yr pre 41.55 / post 41.62; 98"x63" RCP (Sta 40925+36): 100-yr pre 43.87 / post 44.05 ftseq 1Drainage calculations·12 Dec 2007·p.10
“98"x63" RCP 42.60 42.70 43.87 44.05”
Bridge water surface increase
Proposed HEC-RAS model estimates water surface elevation will increase by one hundredth for the 500-year flood event upstream; no increase for 10- and 50-year eventsseq 1Drainage calculations·12 Dec 2007·p.13
“increase by one hundredth for the five hundred year flood event upstream of the two”
Design storm
25 year storm runoff (ac-ft) computed per basin for pre- and post-development conditionsseq 1Drainage calculations·12 Dec 2007·p.2
“25 year storm”
Post development curve numbers
St Johns River Monroe CN 81; Ravenna Park Ditches 81; Lake Mary 73; Deforest Lake Outlet 70; Soldier Creek Reach 68; Gee Creek 63; Cranes Roost Outlet 77; Prairie Lake 69; Lake Seminary 84; Howell Creek 70; Boggy Creek 77seq 1Drainage calculations·12 Dec 2007·p.2
“Post- Development Curve Numbers”
Required swale volume
Swale volume provided per basin: max 1.65 ac-ft (Ravenna Park Ditches); Soldier Creek Reach 1.56; Boggy Creek 1.26; Lake Seminary 0.69; St Johns River Monroe 0.33 acre-feetseq 1Drainage calculations·12 Dec 2007·p.2
“Swale”
Floodplain elevations by location
St. Johns River Monroe basin FIRM elev 9 ft (Volusia/Seminole); Soldier Creek basin 45/39/42/64/66 ft; Cranes Roost Outlet 81 ft; Lake Seminary 88 ftseq 1Drainage calculations·12 Dec 2007·p.2
“Areas of Floodplain Encroachment and Compensation”
Firm panels
FIRM panels: 12127C0730G (Volusia), 12117C0030E, 12117C0040E, 12117C0130E, 12117C0140E (Seminole)seq 1Drainage calculations·12 Dec 2007·p.2
“12127C0730G”
Cross drain headwater difference
Post-development headwater difference ranges 0.00-1.55 ft across the 11 extended culverts, all commented No Impact; max 1.55 ft at Sta 40925+36 (98"x63" RCP)seq 1Drainage calculations·12 Dec 2007·p.2
“98"x63" RCP 38.20 39.75 1.55 No Impact”
Max allowable headwater example
Sta 40241+20 (36" RCP, MP 762.14): maximum allowable headwater elevation 21.30 ft; post-development HW 19.26 ftseq 1Drainage calculations·12 Dec 2007·p.3
“Headwater Elevation 21.30 ft”
Design discharge example
Sta 40241+20 (36" RCP): design discharge 42.39 cfs, HW elev 19.05 ft, velocity 6.00 ft/sseq 1Drainage calculations·12 Dec 2007·p.3
“Design Discharge 42.39 cfs”
Tailwater example
Constant tailwater elevation 18.20 ft at Sta 40241+20 crossingseq 1Drainage calculations·12 Dec 2007·p.3
“Tailwater Elevation 18.20 ft”
Conveyance ditch slope range
Ditch profile flowline elevations and longitudinal slopes tabulated by station; typical/special ditch segments daylighting to cross drains and existing outfalls %seq 1Drainage calculations·12 Dec 2007·p.2
“Ditch Profile Left Side”
Design flood discharges
Q Total: 10-year 13,000 cfs; 50-year 21,800 cfs; 100-year 26,500 cfs; 500-year 40,700 cfs (St. Johns River at the rail bridge crossing)seq 1Drainage calculations·12 Dec 2007·p.7
“500 YR 40700”
Bridge water surface elevation 500yr
At RS 81 (upstream of rail bridge): proposed HEC-RAS 500-yr WSE 11.12 ft vs existing HEC-RAS 11.11 ft (0.01 ft increase); 100-yr 9.51 ft bothseq 1Drainage calculations·12 Dec 2007·p.7
“500 YR 40700 11.12 11.11 10.97”
Peak stage downstream
At RS 5 (downstream): 500-yr WSE 10.50 ft, 100-yr 9.25 ft, 50-yr 8.75 ft, 10-yr 7.20 ft (proposed = existing HEC-RAS)seq 1Drainage calculations·12 Dec 2007·p.8
“500 YR 40700 10.50 10.50 10.50”
Permit scope
Apply for an Individual Permit for the Right-of-Way (ROW) only; project area may be submitted as the proposed double-track areas only or the entire CFCRT Phase 1 corridor from Ft. Florida Rd. to Sand Lake Roadseq 1Drainage calculations·12 Dec 2007·p.4
“Apply for an Individual Permit for the Right-of-Way (ROW) only.”
Forested wetland temporary impact area
4.928 acresseq 1Drainage calculations·12 Dec 2007·p.1
“4.928 acres”
Forested wetland functional loss
FL = delta x acres = 0.7 x 4.928 = 3.45 functional unitsseq 1Drainage calculations·12 Dec 2007·p.2
“FL = delta x acres = 0.7 x. 4.928 = 3.45”
Forested wetland mitigation rfg
RFG = [0.7 / (2.18 x 3)] = 0.11 x 4.928 = 0.54; time lag t-factor 2.18, risk factor 3.0 functional unitsseq 1Drainage calculations·12 Dec 2007·p.4
“[0.7 / (2.18 x 3) ] = 0.11 x 4.928 = 0.54”
Herbaceous wetland temporary impact area
0.05 acresseq 1Drainage calculations·12 Dec 2007·p.5
“0.05 acres”
Osw ditch temporary impact area
1.369 acresseq 1Drainage calculations·12 Dec 2007·p.9
“1.369 acres”
Osw ditch mitigation rfg
RFG = [0.7 / (1 x 1)] = 0.7 x 1.369 ac. = 0.96 functional unitsseq 1Drainage calculations·12 Dec 2007·p.12
“[0.7 / (1 x 1) ] = 0.7 x 1.369 ac. = 0.96”
Affected waterbody classification
Class III; St. Johns River - Wekiva River Aquatic Preserve (OFW)seq 1Drainage calculations·12 Dec 2007·p.1
“St. Johns River - Wekiva River Aquatic Preserve”
Manatee protection shutdown
All in-water operations, including vessels, must be shut down if a manatee comes within 50 feet of the operation; activities resume only after the manatee moves beyond 50 feet or 30 minutes elapseseq 1Permit·12 Dec 2007·p.1
“be shutdown if a manatee(s) comes within 50 feet of the operation.”
Vessel speed restriction
All vessels shall operate at Idle Speed/No Wake while in the immediate area and where vessel draft provides less than four-foot clearance from the bottomseq 1Permit·12 Dec 2007·p.1
“Speed/No Wake” at all times while in the immediate area and while in water”
Turbidity barrier requirement
Siltation or turbidity barriers shall be made of material in which manatees cannot become entangled, properly secured, and regularly monitored; must not impede manatee movementseq 1Permit·12 Dec 2007·p.1
“Siltation or turbidity barriers shall be made of material in which manatees cannot become entangled”
Water quality standards
Activities shall be conducted in a manner which does not cause violations of state water quality standardsseq 1Permit·20 Oct 2008·p.4
“violations of state water quality standards.”
Wetland impacts authorized
Work in, on, or over 7.44 acres of wetlands or other surface waters (rail-side ditches)seq 1Permit·20 Oct 2008·p.3
“acres of wetlands or other surface waters (rail-side ditches).”
Wetland mitigation
6.173 acres of impacts within Wekiva River Nested basin (15) and St Johns River (Canaveral Marshes to Wekiva River) basin (18) mitigated through Section 373.4137, F.S.seq 1Permit·20 Oct 2008·p.8
“Mitigation to offset the 6.173 acres of impacts to wetlands and other surface waters within”
Wetland mitigation lake jesup
1.747 acres within the Lake Jesup basin (23) offset by acquisition, enhancement/restoration/preservation and donation of 8.3 acres of the ~20-acre Joanne W. Logue parcel in the Black Hammock area of Seminole Countyseq 1Permit·20 Oct 2008·p.8
“Mitigation to offset the 1.747 acres of wetlands and other surface waters within the Lake Jesup basin (23)”
Mitigation funding
$50,000 to fund restoration and enhancement of the property plus $500/acre for long term management USDseq 1Permit·20 Oct 2008·p.8
“the amount of $50,000 to fund restoration and enhancement of the property, and the amount of $500/acre for long term”
Turbidity monitoring
During bridge construction, downstream turbidity may not exceed State Water Quality Standards; twice-daily sampling and weekly reporting to the District's Altamonte Springs Service Centerseq 1Permit·20 Oct 2008·p.7
“If at any time the downstream turbidity level exceeds the State Water Quality Standards,”
Manatee protection shutdown
Operation of moving equipment no closer than 50 feet of a manatee; equipment closer than 50 feet necessitates immediate shutdownseq 1Permit·20 Oct 2008·p.9
“equipment no closer than 50 feet of a manatee. Operation of any equipment closer than 50”
Permit expiration
This permit for construction will expire five years from the date of issuanceseq 1Permit·20 Oct 2008·p.6
“This permit for construction will expire five years from the date of issuance.”
Om inspection frequency
O&M entity shall inspect the stormwater/surface water management system once within two years after completion of construction and every two years thereafterseq 1Permit·20 Oct 2008·p.7
“management system once within two years after the completion of construction and every two years thereafter”
Water-quality treatment
Swales and swales with blocks to retain and infiltrate the treatment volume of 1 inch of runoff from the project area, pursuant to Chapter 40C-42, F.A.C.seq 1Technical Staff Report·20 Oct 2008·p.4
“swales and swales with blocks to retain and infiltrate the treatment volume of 1 inch of runoff from the project area.”
Total wetland surface water impact
Construction requires work in a total of 9.46 acres of wetlands and other surface waters (1.94 ac ditches through wetlands, 1.54 ac ditches in uplands, 5.98 ac wetlands)seq 1Technical Staff Report·20 Oct 2008·p.4
“Construction of the proposed track improvements requires work in a total of 9.46 acres of wetlands and other surface waters.”
Impacts requiring mitigation
7.920 acresseq 1Technical Staff Report·20 Oct 2008·p.7
“Impacts that Require Mitigation 7.920”
Total mitigation
8.300 acresseq 1Technical Staff Report·20 Oct 2008·p.7
“Mitigation 8.300”
Wetland mitigation 373 4137
6.173 acres of impacts within Wekiva River Nested basin (15) + St Johns River basin (18) mitigated via Section 373.4137, F.S. (5.147 ac SJ53; 1.026 ac SJ41)seq 1Technical Staff Report·20 Oct 2008·p.9
“Mitigation to offset the 6.173 acres of impacts to wetlands and other surface waters within the Wekiva river Nested basin (15) and St Johns River”
Wetland mitigation lake jesup
1.747 acres within Lake Jesup basin (23) offset by donation of 8.3 acres of the ~20-acre Joanne W. Logue parcel in the Black Hammock area of Seminole Countyseq 1Technical Staff Report·20 Oct 2008·p.9
“Mitigation to offset the 1.747 acres of wetlands and other surface waters within the Lake Jesup basin (23)”
Mitigation funding
$50,000 to fund restoration and enhancement plus $500/acre for long term management of the mitigation property USDseq 1Technical Staff Report·20 Oct 2008·p.10
“the amount of $50,000 to fund restoration and enhancement of the property, and the amount of $500/acre for long term”
Sovereign lands preemption
Bridge crossing pre-empts approximately 1.195 acres of sovereign submerged lands (SSL Easement Parcel 855) within the Wekiva River Aquatic Preserveseq 1Technical Staff Report·20 Oct 2008·p.12
“empting 1.195 acres as shown on the surveyors’ certification for SSL Easement Parcel 855”
Safe upland line elevation
2.80 ft NGVD29seq 1Technical Staff Report·20 Oct 2008·p.12
“bound by the Safe Upland Line provided by FDEP of elevation 2.80 feet (NGVD29).”
Carli Professional Office Building 123954-119 governing-sequence
Water quality treatment volume required
0.042 ac-ftDrainage calculations·17 Mar 2010·p.5
“Total Volume = 0.042 Ac-ft”
Retention volume provided
0.043 (at weir crest elevation 50.50) ac-ftDrainage calculations·17 Mar 2010·p.12
“Retention Provided = 0.043 Ac-ft”
Recovery drawdown time
55.57 hrs provided vs 72 hrs maximum (SJRWMD requirement), with factor of safety 2.0 hoursDrainage calculations·17 Mar 2010·p.12
“Drawdown Time = 55.57 hrs < 72 hrs Required”
Design storm
SJRWMD mean annual, 25-yr, and 100-yr 24-hr storm eventsDrainage calculations·17 Mar 2010·p.12
“For 25-yr 24-hr Storm Event: (SJRWMD)”
Allowable discharge mean annual cfs
post-development peak 0.372 cfs does not exceed pre-development peak 0.503 cfsDrainage calculations·17 Mar 2010·p.12
“Pre-Dev. Peak Flow = 0.503 cfs> 0.372 cfs = Post-Dev. Peak Flow”
Allowable discharge 25yr cfs
post-development peak 1.49 cfs does not exceed pre-development peak 1.547 cfsDrainage calculations·17 Mar 2010·p.12
“Pre-Dev. Peak Flow = 1.547 cfs> 1.49 cfs = Post-Dev. Peak Flow”
Allowable discharge 100yr cfs
post-development peak 1.994 cfs does not exceed pre-development peak 2.132 cfsDrainage calculations·17 Mar 2010·p.12
“Pre-Dev. Peak Flow = 2.132 cfs> 1.994 cfs = Post-Dev. Peak Flow”
Peak stage mean annual ft
50.74 ftDrainage calculations·17 Mar 2010·p.12
“Peak Stage = Elev. 50.74”
Peak stage 25yr ft
51.10 ftDrainage calculations·17 Mar 2010·p.12
“Peak Stage = Elev. 51.10”
Peak stage 100yr ft
51.23 ftDrainage calculations·17 Mar 2010·p.12
“Peak Stage = Elev. 51.23”
Seasonal high groundwater elevation ft
48.75 ftDrainage calculations·17 Mar 2010·p.35
“Elevation of Seasonal High Groundwater Table 48.75 ft”
Tailwater elevation ft
50.00 (right-of-way piping system assumed flowing full) ftDrainage calculations·17 Mar 2010·p.2
“the tailwater was at elevation 50.00”
Water-quality treatment
stormwater treatment by retentionPermit·15 Jun 2010·p.1
“Construction of a Stormwater Management System with stormwater treatment by retention”
Construction permit expiration
five years from date of issuancePermit·15 Jun 2010·p.3
“will expire five years from the date of issuance”
Om inspection frequency
inspect system within two years after completion of construction and every two years thereafterPermit·15 Jun 2010·p.5
“once within two years after the completion of construction”
Receiving waterbody class
Crystal Lake, Class III freshTechnical Staff Report·9 Jun 2010·p.1
“Crystal Lake III Fresh”
Water-quality treatment
treatment and recovery of the required treatment volume per Chapter 40C-42, F.A.C. for systems discharging to a Class III waterbodyTechnical Staff Report·9 Jun 2010·p.2
“provide treatment and recovery of the required treatment”
Peak rate attenuation
N/ATechnical Staff Report·9 Jun 2010·p.1
“Peak Rate Attenuation: N/A”
Impaired basin
project lies within the impaired Lake Jesup drainage basin, but site runoff discharges to Crystal Lake, which is not impairedTechnical Staff Report·9 Jun 2010·p.2
“located within the Lake Jesup drainage basin, which is an impaired”
Lake Mary Pediatric Medical Office 141317-125 governing-sequence
Design storm
25-yr/24-hr (City of Lake Mary pre vs. post-development rate attenuation)Drainage calculations·18 Mar 2015·p.5
“City of Lake Mary: Pre vs. post-development rate attenuation is required for the 25-yr/24-hr storm”
Water-quality treatment
On-line dry retention: greater of 1.25 in of runoff from impervious area or 0.5 in over basin, plus additional 0.5 in over basinDrainage calculations·18 Mar 2015·p.5
“treatment requirement is retention of the greater of 1.25” of runoff from the impervious area or 0.5””
Required treatment volume
0.10 ac-ftDrainage calculations·18 Mar 2015·p.56
“1 0.5 1.04 0.05 0.04 0.04 0.10”
Recovery time
72 hours required; 24 hours providedDrainage calculations·18 Mar 2015·p.6
“72 HRS 24 HRS”
Allowable discharge cfs
pre-development 0.85 cfs vs post-development 0.78 cfs (25-yr/24-hr)Drainage calculations·18 Mar 2015·p.7
“1 0.85 0.78”
Sjrwmd attenuation
not required (project area less than 50% impervious)Drainage calculations·18 Mar 2015·p.5
“50% impervious, no attenuation is required”
Seasonal high water elevation
48.25 (used in modeling) ftDrainage calculations·18 Mar 2015·p.7
“however, a SHWE of 48.25 is used in the modeling to provide the necessary separation between the”
Design permeability
vertical 8 ft/day, horizontal 15 ft/day (includes factor of safety of 2)Drainage calculations·18 Mar 2015·p.6
“vertical permeability of 8-ft/day and design coefficient of horizontal permeability of 15 ft/day (refer”
Floodplain compensation
none required - no construction within 100-year floodplain (FIRM 12117C0065F)Drainage calculations·18 Mar 2015·p.7
“This project does not propose construction within the 100 year flood plain as determined from the”
Wetland mitigation
none - no wetlands in or adjacent to project areaDrainage calculations·18 Mar 2015·p.7
“There are no wetlands in or adjacent to the project area.”
Receiving water flood zone
Lake Mary Zone AE elevation 43 ft NAVD 88Drainage calculations·18 Mar 2015·p.7
“Mary, which has a Zone AE elevation of 43’ (NAVD 88) according to the FEMA Map.”
Water-quality treatment
treatment volume of 0.10 ac-ft required; retention pond attenuates 0.21 ac-ftTechnical Staff Report·10 Apr 2015·p.2
“for a treatment volume of 0.10 ac-ft and the retention pond is able to attenuate 0.21 ac-”
Design storm
25-year/24-hour per City of Lake Mary requirementsTechnical Staff Report·10 Apr 2015·p.2
“which is the 25-year/24-hour design storm, per the City of Lake Mary requirements”
Recovery time
pond recovery within 72 hours after a storm eventTechnical Staff Report·10 Apr 2015·p.2
“pond will have adequate recovery within the 72 hours after a storm event.”
Receiving water class
Lake Mary, Class III FreshTechnical Staff Report·10 Apr 2015·p.1
“Lake Mary III Fresh”
Water quality impairment
Lake Mary not listed for water quality impairmentsTechnical Staff Report·10 Apr 2015·p.2
“Lake Mary is the recieving waterbody and is not listed for water”
Floodplain
site not within 100-year floodplain per FIRM 12117C0065F dated September 28, 2007Technical Staff Report·10 Apr 2015·p.2
“Flood Insurance Rate Map #: 12117C0065F, dated September 28, 2007.”
Special basin criteria
noneTechnical Staff Report·10 Apr 2015·p.2
“There are no special basin criteria.”
Wetland mitigation
none - no wetlands or other surface waters within or adjacent to project boundariesTechnical Staff Report·10 Apr 2015·p.3
“other surface waters occur within the project boundaries or adjacent to the site, and no”
Conservation easement
N/ATechnical Staff Report·10 Apr 2015·p.1
“Easements/Restrictions: N/A”
Construction permit expiration
five years from date of issuanceTechnical Staff Report·10 Apr 2015·p.7
“22.This permit for construction will expire five years from the date of issuance.”
Om inspection frequency
inspect within two years after completion of construction and every two years thereafterTechnical Staff Report·10 Apr 2015·p.7
“construction and every two years thereafter to determine if the system is”
Permit issue date
April 10, 2015Permit·10 Apr 2015·p.3
“PERMIT NO: 141317-1 DATE ISSUED: April 10, 2015”
Plans of record
system must be constructed and operated per plans received by the District on March 18, 2015Permit·10 Apr 2015·p.6
“accordance with the plans received by the District on March 18, 2015.”
Retention area excavation
retention/detention storage areas must be excavated to rough grade prior to building construction or impervious placementPermit·10 Apr 2015·p.6
“19.At a minimum, all retention and detention storage areas must be excavated to rough grade”
South Country Club Drainage Improvements 214983-18 governing-sequence
Authorizing rule
General ERP issued under subsection 62-330.451, F.A.C. (General Permit to Counties, Municipalities, and other Agencies to Conduct Stormwater Retrofit Activities)Technical Staff Report·7 Mar 2024·p.1
“62-330.451”
Receiving water classification
Lake Mary, Class III FreshTechnical Staff Report·7 Mar 2024·p.1
“III Fresh”
Plans of record
Construction must be as per plans received by the District on February 8, 2024Technical Staff Report·7 Mar 2024·p.1
“District on February 8, 2024”
Permit duration
5 yearsTechnical Staff Report·7 Mar 2024·p.3
“authorized for a duration of five years”
Construction certification deadline
30 daysTechnical Staff Report·7 Mar 2024·p.5
“Within 30 days after completion of construction”
Governing rules
Activities are subject to the general and special conditions in rules 62-330.405 and 62-330.451, F.A.C.Permit·7 Mar 2024·p.3
“specified in rules 62-330.405 and 62-330.451, F.A.C.”
Permit expiration
Permit expires 5 years from the date the notice of intent to use the General ERP was received by the DistrictPermit·7 Mar 2024·p.3
“General Environmental Resource Permit expires 5 years from the”
Federal authorization
Activity does not qualify for federal authorization under SPGP VI-R1; a separate permit or authorization may be required from the U.S. Army Corps of EngineersPermit·7 Mar 2024·p.3
“authorization pursuant to the State Programmatic General Permit VI-R1 (SPGP VI-R1)”
Lake Mary Boulevard , Phase II: pedestrian overpass (Ltr Mod) 21945-190 governing-sequence · 17 file history
Lineage: every attributable document here is from seq 1 (documents dated 2007–2008) — none from governing seq 19 (“Lake Mary Boulevard , Phase II: pedestrian overpass (Ltr Mod)”, 2005). Entries below are file history, not the governing record.
Wetland protection
No encroachment permitted in the adjacent off-site wetland; STA 35+00 to STA 50+00 construction limits must be staked and field-verified by District staff before road ROW constructionseq 1Permit·p.5
“no encroachment occurs in the adjacent off-site wetland”
Wetland impact
0.29 ac maximum wetland area that could potentially be impacted (six wetland areas identified; Palustrine Emergent and Palustrine Forested)seq 1Drainage calculations·17 Sep 2007·p.9
“wetland that could potentially be impacted is 0.29 acres”
Outstanding Florida Waters
No water bodies within the study area qualify as Outstanding Florida Waters (reviewed per Ch. 17-3.041 F.A.C.); nearest OFW is the Wekiva River / Wekiva Springs State Parkseq 1Drainage calculations·17 Sep 2007·p.11
“None of these fall within that classification”
Critical habitat / listed species
No USFWS-listed critical habitat on the project site; no federally- or state-listed threatened or endangered plant species sightedseq 1Drainage calculations·17 Sep 2007·p.11
“No "critical habitat", as listed by the USFWS, is found”
Design storm
25-year / 24-hour, SCS Type II Modified (runoff methods: SCS curve number, SBUH, ICPR)seq 1Technical Staff Report·p.2
“DESIGN STORM: 25 YEAR”
Post-development peak discharge
Post-development 25-yr/24-hr peak runoff held at or below pre-development levels by road reach; post-development peaks range ~7.19 to 30.13 cfs across the seven reaches (Sta 2+00 to 90+05)seq 1Technical Staff Report·p.2
“POST-DEVELOPMENT”
Wetland mitigation
0.0 ac - wetlands involved, preserved, disturbed, lost, and restored/created all reported as 0.0 (no wetland impact or mitigation required)seq 1Technical Staff Report·p.3
“TOTAL WETLANDS PRESERVED”
Water-quality treatment
Runoff treatment accomplished by retention and percolationseq 1Technical Staff Report·p.3
“RUNOFF TREATMENT”
Peak stage
100-year / 24-hour storm event stage at EL 50.0 (ponds provide storage to EL 51.0) ftseq 1Technical Staff Report·p.8
“100 YR STORM EVENT (24 HR) STAGE IS EL 50.0”
Post-development discharge (100-yr)
38.65 cfs post-development discharge (vs 76.5 cfs pre-development, including Lake Mary Blvd) after joint-use pond connection/expansionseq 1Technical Staff Report·p.8
“POST DEVELOPMENT DISCHARGE IS 38.65 CFS”
Design storm
25-year, 96-hour storm (Basin 5 ponds shown to have adequate storage capacity up to and including this event)seq 1As-built·17 Sep 2007·p.25
“up to and including the 25 yr. 96 hr. storm”
Water-quality treatment
pre-treatment of the runoff from the first inch of rainfall (Lake Mary City Hall Phase 1 submittal under permit 4-117-0151GM)seq 1As-built·17 Sep 2007·p.4
“pre-treatment of the runoff from the first inch of rainfall”
Allowable impervious area
1.3 acres allowable for the 8.6-acre tract bounded by Lake Mary Blvd, Country Club Rd, Lakeview Ave and Fourth St; Lake Mary City Hall Phase I work totals 1.2 acresseq 1As-built·17 Sep 2007·p.4
“showing the allowable 1.3 ac.”
Additional permit for buildout
any subsequent buildout in the 8.8-acre parcel beyond Lake Mary City Hall Phase I requires an additional permitseq 1As-built·17 Sep 2007·p.4
“in this 8.8 acre parcel would require an additional permit”
Master permit lot authorization
Condition 28 of the master permit authorizes construction on individual lots upon provision of plans showing the construction complies with the master system design parametersseq 1As-built·17 Sep 2007·p.2
“Condition 28 of the reference permit provides authorization for construction on this lot”
Pond design impervious assumption
Basin 3 pond sized for the TASHJIAH parcel at a post-developed condition of 75% impervious surface, so the parcel can be developed in the future with no additional retention requiredseq 1As-built·17 Sep 2007·p.25
“a post-developed condition of 75% impervious”
Baseline impervious assumption
the 8.6-acre tract was presented as "developed" with approximately 15% impervious surface area in the master permitseq 1As-built·17 Sep 2007·p.4
“presented as "developed" with approximately 15% impervious”
Woodbridge Lk Phase 2C 22463-20 governing-sequence · 38 file history
Lineage: every attributable document here is from seq 1 (documents dated 2007–2008) — none from governing seq 2 (“Woodbridge Lk Phase 2C”, 1999). Entries below are file history, not the governing record.
Discharge volume limit
SJRWMD: limit post-development peak 96-hour volume of discharge to pre-development for the 25-year design stormseq 1Drainage calculations·20 Mar 2007·p.106
“Limit the post-development peak 96-hour volume-of-”
Design storm retention
City of Lake Mary: basins without positive outfall shall retain the post-development runoff volume from the 100-year, 24-hour (10.6 inch) design stormseq 1Drainage calculations·20 Mar 2007·p.105
“100-year, 24-hour (10.6 inch) design storm event.”
Peak flow attenuation
City of Lake Mary: basins with positive outfall shall attenuate peak flow to the pre-development rate for the 25-year, 24-hour (8.6 inch) stormseq 1Drainage calculations·20 Mar 2007·p.105
“development rate from the 25-year, 24-hour (8.6 inch)”
Design storm
System dynamically modeled in its entirety for the 100-year/24-hour and 25-year/96-hour design storm eventsseq 1Drainage calculations·20 Mar 2007·p.107
“year, 24-hour and the 25-year, 96-hour design storm events to”
Water-quality treatment
SJRWMD off-line retention: greater of first 0.5 inch of runoff from developed project or 1.25 inches times impervious area (plus 0.5 inch additional for on-line); City of Lake Mary: first inch of runoffseq 1Drainage calculations·20 Mar 2007·p.108
“Retention of the first one-half (0.5) inch of runoff”
Treatment volume recovery
Treatment volume must be recovered within 72 hours following the design storm eventseq 1Drainage calculations·20 Mar 2007·p.108
“The volume shall be recovered within 72 hours following”
Fema floodplain elevation
FEMA identified elevation 46.0 for all of the 100-year floodplain within the property ftseq 1Drainage calculations·20 Mar 2007·p.105
“FEMA has identified elevation 46.0 for”
Peak stage ft lake1
Lake #1 post-development stage: 44.90 ft (100-yr/24-hr), 46.61 ft (25-yr/96-hr)seq 1Drainage calculations·20 Mar 2007·p.107
“44.90 46.61”
Peak stage ft lake2
Lake #2 post-development stage: 45.40 ft (100-yr/24-hr), 46.48 ft (25-yr/96-hr)seq 1Drainage calculations·20 Mar 2007·p.107
“45.40 46.48”
Peak stage ft lake3
Lake #3 post-development stage: 42.34 ft (100-yr/24-hr), 42.90 ft (25-yr/96-hr)seq 1Drainage calculations·20 Mar 2007·p.107
“42.34 42.90”
Floodplain fill
Lake Dawson floodplain fill of 0.24 ac-ftseq 1Drainage calculations·20 Mar 2007·p.110
“0.24 Ac-Ft”
Floodplain compensation
Compensating storage volume of 4.63 ac-ft providedseq 1Drainage calculations·20 Mar 2007·p.110
“4.63 Ac-Ft”
Wetland impact
Total wetland impact 0.74 acres (minimal disturbance to mostly man-made isolated depressional areas); no impact to Lake Dawson or its wetlandsseq 1Drainage calculations·20 Mar 2007·p.110
“The total impact is 0.74 acres.”
Wetland mitigation
Preservation of a 25-ft upland buffer around wetland perimeters, total upland buffer area 5.68 acresseq 1Drainage calculations·20 Mar 2007·p.110
“The total area of upland buffer = 5.68 acres.”
Treatment volume basin3
Rinehart Road Basin 3 treatment volume required 67,213 cf (retention of 1.25 in over impervious plus 0.5 in over total area), recovery 65 hours ft3seq 1Drainage calculations·20 Mar 2007·p.6
“67,213”
Recharge volume pond3
Recharge volume 54,450 cf stored in Pond 3 at pond stage 47.25 ft, recovery time 1.5 days ft3seq 1Drainage calculations·20 Mar 2007·p.5
“54,450”
Hgl criterion
Maintain hydraulic gradeline of the pipe collection system 6 inches below pavement elevation for the 10-year storm eventseq 1Drainage calculations·20 Mar 2007·p.109
“(6) inches below the pavement elevation for the 10-year storm”
Operation maintenance entity
Woodbridge Lakes Homeowners Association (c/o Sentry Management), requested transferee of Permit 4-117-0422 for long-term operation and maintenanceseq 1As-built·20 Mar 2007·p.10
“that the District permit be transferred to Woodbridge Lakes Homeowners Association.”
Conservation easement
Existing conservation easement executed by Olympia Lake Mary Associates dated April 3, 1998, recorded O.R. Book 3398, Pages 1972-1988, Seminole County; 1999 Grant and Partial Release swaps easement areas per Exhibits B and Cseq 1As-built·20 Mar 2007·p.23
“Associates, Ltd, a Florida Corporation dated April 3, 1998 and recorded in 0 R Book 3398,”
Peak stage
46.0 ft = control elevation of the proposed bypass inlet in Lake 1, which is the 100-year 24-hour design storm elevation of that facilityseq 1As-built·20 Mar 2007·p.101
“46.0, which is the 100-year 24-hour design storm elevation of this facility.”
Adjacent pad elevation
52.35 ft Stenstrom residence pad elevation, higher than the estimated flood elevations resulting from the revised (bypass) projectseq 1As-built·20 Mar 2007·p.101
“determine that the Stenstrom pad elevation (52.35) is higher than the estimated”
Drainage easement
Olympia Lake Mary Associates retains a drainage easement across the lake area, including the rear yard of the Stenstrom residence, to elevations that would maintain the expected flood elevationsseq 1As-built·20 Mar 2007·p.101
“Associates retains a drainage easement across the lake area, including the rear”
Conservation easement
Required prior to any construction or land clearing; must prohibit all construction, clearing, dredging or filling within the 21.89-acre wetland preservation area and the 3.65-acre upland preservation area (text layer OCR reads 3.b5); enforceable by the District and not amendable without District approval acresseq 1Permit·p.7
“CLEARING, DREDGING OR FILLING WITHIN THE 21.89 ACRES OF”
Upland preservation
3.65 acres of upland preservation within the conservation easement (text layer OCR reads 3.b5)seq 1Permit·p.7
“WETLAND PRESERVATION AREA AND THE 3.b5 ACRES OF UPLAND”
Natural vegetation buffer
Natural vegetation buffer area is part of the surface water treatment system; must not be disturbed and must remain intact throughout the life of the system (Condition 23)seq 1Permit·p.8
“THE NATURAL VEGETATION BUFFER AREA IS PART”
Receiving waterbody
Lake Dawsonseq 1Permit·p.10
“LAKE DAWSON.”
Erosion sediment control
BMPs per Section 6 of the Florida Land Development Manual required; stabilization of disturbed areas no more than 14 days after construction activity ceasesseq 1Permit·p.5
“NO CASE MORE THAN 14 DAYS AFTER THE CONSTRUCTION ACTIVITY”
Exfiltration system maintenance
Inlets to exfiltration systems must be inspected and cleaned quarterly (February, May, August, November)seq 1Permit·p.7
“OF DEBRIS AND SEDIMENT ON A QUARTERLY BASIS IN FEBRUARY”
Receiving waterbody
Lake Dawson, Class IIIseq 1Technical Staff Report·p.4
“Lake Dawson (CLASS III)”
Design storm
System designed for the 100-year/24-hour and 25-year/96-hour storm eventsseq 1Technical Staff Report·p.5
“Also, the system was designed for the 100-year, 24-”
Land locked basin
Design meets the land-locked basin criteriaseq 1Technical Staff Report·p.5
“will meet the land-locked basin criteria.”
Water-quality treatment
Retention and detention facilities treat the pollution abatement volume per Chapter 40C-42 criteriaseq 1Technical Staff Report·p.5
“treat the pollution abatement volume in accordance with Chapter 40C-”
Floodplain compensation
Compensating storage provided on site with direct connection to the floodplain; no net reduction in flood storage within the 100-year floodplain of Lake Dawsonseq 1Technical Staff Report·p.5
“in flood storage within the 100-year floodplain of Lake Dawson.”
Wetland fill
0.46 acres of waters-of-the-state wetlands and 0.27 acres of isolated wetlands filled for portions of 5 residential lots and rear-lot stormwater treatmentseq 1Technical Staff Report·p.5
“The applicant proposes to fill 0.46 acres of waters of the state”
Wetland mitigation
Preserve 21.89 acres of on-site wetlands and 3.65 acres of on-site uplands to compensate for proposed wetland impacts (text layer OCR reads wet1ands)seq 1Technical Staff Report·p.6
“these proposed impacts preserve 21.89 acres of on-site wet1ands and”
Conservation easement
Easement must prohibit all construction, clearing, dredging or filling within the 21.89 acres of wetland preservation area and 3.65 acres of upland preservation, recorded before constructionseq 1Technical Staff Report·p.7
“dredging or filling within the 21.89 acres of wetland”
Upland preservation
3.65 acres upland preservation as other compensationseq 1Technical Staff Report·p.7
“3.65 acres (upland preservation)”
Natural vegetation buffer
Natural vegetation buffer area is part of the surface water treatment system; must not be disturbed and must remain intact for the life of the systemseq 1Technical Staff Report·p.8
“The natural vegetation buffer area is part of the surface water”
Crystal Lake Condos 237414-131 governing-sequence
Design storm
25-year/96-hour, 11.30 in rainfall (SJRWMD 96-hr distribution) - governing water quantity event because the project is in a closed basinDrainage calculations·12 Jun 2025·p.18
“Rainfall Amount(in): 11.30”
Design storm 25yr 24hr rainfall
8.40 (Flmod distribution, 25-yr/24-hr simulation) inDrainage calculations·12 Jun 2025·p.18
“Rainfall Amount(in): 8.40”
Water quality treatment required
0.210 (greater of 1/2 inch of basin runoff vs 1.25 inch of impervious runoff) Ac-FtDrainage calculations·12 Jun 2025·p.14
“0.210 Ac-Ft”
Water quality treatment provided
0.489 Ac-FtDrainage calculations·12 Jun 2025·p.14
“0.489 Ac-Ft”
Treatment volume recovery time
63.8 (against a 72-hour maximum) hoursDrainage calculations·12 Jun 2025·p.14
“63.8 HRS”
Allowable discharge volume 25yr96hr
0.343 (pre-development 25-yr/96-hr boundary volume, node PRE-E) Ac-FtDrainage calculations·12 Jun 2025·p.13
“0.343 Ac-Ft”
Post development discharge volume 25yr96hr
0.342 (post-development 25-yr/96-hr boundary volume, node POST-E; less than pre-development 0.343) Ac-FtDrainage calculations·12 Jun 2025·p.14
“0.342 Ac-Ft”
Allowable discharge cfs nw boundary
0.15 (pre-development 25-yr/24-hr peak flow, node PRE-NW) cfsDrainage calculations·12 Jun 2025·p.13
“0.15 CFS”
Allowable discharge cfs sw boundary
0.21 (pre-development 25-yr/24-hr peak flow, node PRE-SW) cfsDrainage calculations·12 Jun 2025·p.13
“0.21 CFS”
Peak stage
54.94 (max stage in stormwater chambers, 25-yr/96-hr routing; 25-yr/24-hr max stage 54.53) ftDrainage calculations·12 Jun 2025·p.20
“54.94”
Control elevation ft
54.400 (control structure weir CS) ftDrainage calculations·12 Jun 2025·p.17
“Control Elevation(ft): 54.400”
Fema flood zone
Zone X, outside the 0.2% annual chance floodplain (FIRM panel 12069C0450E dated 12-18-2012)Drainage calculations·12 Jun 2025·p.4
“12069C0450E”
Seasonal high groundwater depth
6 (average high wet season groundwater level below prevailing ground surface, for design) ftDrainage calculations·12 Jun 2025·p.7
“an average high wet season groundwater level at a depth of 6 feet below the prevailing”
Vertical permeability
26 (coefficient of vertical permeability kv of soil stratum #2, falling head test; kh may be assumed 1.5 x kv) ft/dayDrainage calculations·12 Jun 2025·p.7
“is equivalent to about 26 feet per day.”
Percolation safety factor
reduce percolation rates by 50% in stormwater recovery analyses (Design Factor of Safety = 2)Drainage calculations·12 Jun 2025·p.13
“provided above should be reduced by 50% in order to incorporate a Design Factor of Safety”
Soil porosity
25 (average porosity of soils underlying the pond bottom) %Drainage calculations·12 Jun 2025·p.13
“An average porosity of the soils underlying the pond bottom equivalent to 25%,”
Confining layer depth
7 (average depth of assumed confining layer / bottom of aquifer below prevailing ground surface in pond area) ftDrainage calculations·12 Jun 2025·p.13
“A confining layer (bottom of aquifer) assumed at an average depth of 7”
Certification action deadline
12/01/2026 (date by which the District agrees to act on the certification request)Certification of completion·29 Dec 2025·p.1
“reasonable period of time, and no later than 12/01/2026.”
Water-quality treatment
System designed to provide water quality treatment per Sections 4.1 and 7.0, A.H. Vol. II, for discharge to Class III waters; permit also constitutes a Section 401 Clean Water Act water quality certificationTechnical Staff Report·29 Dec 2025·p.2
“provide water quality treatment in accordance with Sections 4.1 and 7.0, A.H. Vol. II for”
Design storm
Post-development peak rate of discharge shall not exceed pre-development peak rate for the mean annual and 25-year 24-hour storm eventsTechnical Staff Report·29 Dec 2025·p.2
“mean annual and 25-year 24-hour storm event.”
Receiving water class
Crystal Lake, Class III FreshTechnical Staff Report·29 Dec 2025·p.1
“III Fresh”
Conservation easement
No (no ERP conservation easements/restrictions)Technical Staff Report·29 Dec 2025·p.1
“ERP Conservation”
Wetland mitigation
None required - upland site; no direct or secondary wetland or surface water impacts associated with this projectTechnical Staff Report·29 Dec 2025·p.3
“There are no direct or secondary wetland or surface water impacts associated”
Special basin criteria
N/A (not in a special regulatory basin)Technical Staff Report·29 Dec 2025·p.2
“Special Basin Criteria:”
Permit duration
Construction permit expires five years from date of issuance (Condition 19)Technical Staff Report·29 Dec 2025·p.7
“This permit for construction will expire five years from the date of issuance.”
Om inspection frequency
O&M entity must submit inspection reports one year after operation phase becomes effective and every two years thereafter on form 62-330.311(1), signed and sealed by a registered professional (Condition 21)Technical Staff Report·29 Dec 2025·p.7
“every two years thereafter on form 62-330.311(1)”
Permit issue date
December 29, 2025Permit·29 Dec 2025·p.3
“DATE ISSUED: December 29, 2025”
Permit expiration
Construction permit expires five years from date of issuance (Condition 19)Permit·29 Dec 2025·p.6
“This permit for construction will expire five years from the date of issuance.”
Wetland impacts
Permit does not authorize impacts to wetlands or other surface waters (Condition 24)Permit·29 Dec 2025·p.7
“This permit does not authorize impacts to wetlands or other surface waters.”
Om inspection certification
O&M inspection reports due one year after operation phase and every two years thereafter on form 62-330.311(1) (Condition 21)Permit·29 Dec 2025·p.7
“on form 62-330.311(1)”
Plans of record
Project must be constructed and operated per plans and calculations received by the District on November 19, 2025 (Condition 25)Permit·29 Dec 2025·p.7
“received by the District on November 19, 2025.”
Rainbow Child Care Center 49830-30 governing-sequence · 27 file history
Lineage: every attributable document here is from seq 1 (“ZANCA OFFICE SITE”, 1998) — none from governing seq 3 (“Rainbow Child Care Center”, 2018). Entries below are file history, not the governing record.
Design storm
Pollution abatement volume treatment, peak attenuation of the mean annual storm (SJRWMD/Lake Mary), and full storage of the 25-year/24-hour storm (Seminole County)seq 1Drainage calculations·30 Jan 2006·p.3
“attenuation of the mean annual storm, and full storage of the 25 year /24 hour”
Water quality treatment volume
0.19 ac-ftseq 1Drainage calculations·30 Jan 2006·p.14
“0.19 AC-FT”
Treatment recovery time
48 hrseq 1Drainage calculations·30 Jan 2006·p.14
“48 HR”
Bleed down flow rate
0.024 cfsseq 1Drainage calculations·30 Jan 2006·p.14
“0.024 CFS”
Allowable discharge cfs
0.043 (pre-development mean annual peak, 1.74 ac, CN 42.5) cfsseq 1Drainage calculations·30 Jan 2006·p.9
“0.043 CFS”
Post development discharge cfs
0.038 (post-development mean annual peak pond output, less than pre-development 0.043) cfsseq 1Drainage calculations·30 Jan 2006·p.19
“0.038 CFS”
Peak stage ft 25yr 24hr
52.007 (max pond stage, 25-yr/24-hr storm; top of pond 53.00) ftseq 1Drainage calculations·30 Jan 2006·p.26
“52.007 Feet”
Peak stage ft mean annual
50.480 (max pond stage, post-development mean annual storm) ftseq 1Drainage calculations·30 Jan 2006·p.19
“50.480 Feet”
Design rainfall mean annual
4.5 inseq 1Drainage calculations·30 Jan 2006·p.9
“4.500 In”
Design rainfall 25yr 24hr
8.6 inseq 1Drainage calculations·30 Jan 2006·p.25
“8.600 In”
Floodplain compensation
Not required - project site is not within the 100-year flood plainseq 1Drainage calculations·30 Jan 2006·p.3
“The project site is not within the 100 year flood plain”
Wetland mitigation
Not required - no wetlands exist on siteseq 1Drainage calculations·30 Jan 2006·p.3
“No wetlands exist on site.”
Seasonal high groundwater
5 feet below ground surface in the vicinity of the proposed pond (geotech report, Andreyev Engineering) ft bgsseq 1Drainage calculations·30 Jan 2006·p.32
“Estimated normal seasonal high groundwater table is 5 feet below”
Hydraulic conductivity
3.7 (average horizontal, surficial 14 ft of soil, field-measured) ft/dayseq 1Drainage calculations·30 Jan 2006·p.32
“3.7 feet per day”
Receiving waterbody
Lake Maryseq 1Technical Staff Report·p.2
“Receiving Water Body: Lake Mary”
Receiving water classification
Class IIIseq 1Technical Staff Report·p.2
“Class: III”
Project area
1.74 acresseq 1Technical Staff Report·p.2
“Project Area: 1.74 (acres)”
Water-quality treatment
Wet detention and swales (general permit category 40C-42.024(2)(b))seq 1Technical Staff Report·p.2
“40C-42.024(2)(b) Retention Underdrain, Exfiltration, Wet”
Plans of record
Plans received by the District on 4/6/98seq 1Technical Staff Report·p.2
“4/6/98.”
Permit number
42-117-1231N-ERPseq 1Permit·p.2
“42-117-1231N-ERP”
Date issued
April 13, 1998seq 1Permit·p.2
“DATE ISSUED APRIL 13, 1998”
Water-quality treatment
Wet detention and swalesseq 1Permit·p.2
“WET DETENTION AND SWALES TO SERVE THE ZANCA OFFICE”
As built certification
As-built certification form due within 30 days of completion of construction, including all site workseq 1Permit·p.2
“within 30 days of completion of construction of the permitted system,”
Wetland protection
All wetland areas or water bodies outside the permitted limits of construction must be protected from erosion, siltation, scouring, excess turbidity, and dewatering (Condition 1)seq 1Permit·p.5
“permit must be protected from erosion, siltation, scouring”
Limits of construction
Permittee must clearly designate the limits of construction on-site prior to construction (Condition 2)seq 1Permit·p.5
“Prior to construction, the permittee must clearly designate”
Inspection reports
O&M entity must submit inspection reports on District form EN-46 two years after the operation phase permit becomes effective and every two years thereafter, signed and sealed by a registered professional (Condition 3)seq 1Permit·p.5
“phase permit becomes effective and every two years theafter”
Dewatering consumptive use threshold
Consumptive Use Permit (40C-2) required before dewatering if withdrawing one million gallons per day or more, or an average of 100,000 gallons per day or more over a year, with off-site dischargeseq 1Permit·p.3
“facilities are capable of withdrawing one million gallons of water”
JR Academy of Lake Mary 69432-128 governing-sequence
Design storm
Mean annual storm event (pond designed to detain); ICPR run used 4.30 in over 24 hr, FLMOD distributionDrainage calculations·22 Sep 2006·p.38
“proposed pond has been designed to detain the mean annual storm event”
Design rainfall depth
4.30 in over 24 hrDrainage calculations·22 Sep 2006·p.39
“RAIN AMOUNT (in) 4.30 4.30”
Water quality treatment volume
0.09 ac-ft (pollution abatement volume, P.A.V.)Drainage calculations·22 Sep 2006·p.38
“Use 0.09 Ac.-Ft.”
Pollution abatement volume elevation
59.61 ft (datum not stated)Drainage calculations·22 Sep 2006·p.38
“(P.A.V. EL. 59.61)”
Mean annual stage elevation
60.05 ft (datum not stated)Drainage calculations·22 Sep 2006·p.38
“(MEAN ANNUAL STAGE EL. 60.05)”
Predevelopment discharge
0.14 cfs (peak, at 12.29 hr; runoff volume 0.39 in)Drainage calculations·22 Sep 2006·p.39
“PREDEV .14 12.29 .39 PREDEVELOPMENT DISCHARGE”
Postdevelopment runoff
1.55 cfs (peak inflow to pond, at 12.00 hr; runoff volume 2.38 in)Drainage calculations·22 Sep 2006·p.39
“POSTDEV 1.55 12.00 2.38 POST DEVELOPED”
Peak pond stage
60.05 ft at 13.25 hr (minimum/starting stage 58.00 ft)Drainage calculations·22 Sep 2006·p.41
“STAGE (ft): 58.00 1.75 60.05 13.25”
Peak pond outflow
0.13 cfs at 13.25 hrDrainage calculations·22 Sep 2006·p.41
“OUTFLOW (cfs): .00 12.00 .13 13.25”
Peak pond volume
0.12 ac-ft at 13.25 hrDrainage calculations·22 Sep 2006·p.41
“VOLUME (af): .00 1.75 .12 13.25”
Impervious area
0.49 acre of 0.88 acre basin (56 percent); DCIA 0.49 acreDrainage calculations·22 Sep 2006·p.38
“project area is 0.88 acre with a proposed impervious are of 0.49 acre”
Curve numbers
Predeveloped CN 49 (100 percent pervious, Tc 14 min, DCIA 0); postdeveloped CN 39 (Tc 10 min, DCIA 56 percent)Drainage calculations·22 Sep 2006·p.39
“CURVE NUMBER 49.00 39.00”
Seasonal high groundwater elevation
54.7 ft (estimated perched seasonal high groundwater table, at pond)Drainage calculations·22 Sep 2006·p.14
“Estimated "perched" Seasonal High Groundwater Table Elevation (ft) 54.7 feet”
Base of surficial aquifer elevation
53.2 ft (recommended)Drainage calculations·22 Sep 2006·p.14
“Recommended Elevation of Base of the Surficial Aquifer (ft) 53.2 feet”
Saturated permeability
22.2 feet/day (Khsat = Kvsat); unsaturated Kv 14.9 feet/dayDrainage calculations·22 Sep 2006·p.14
“Average Saturated Horizontal and Vertical Permeability Value (Khsat=Kvsat) 22.2 feet/day”
Surficial aquifer porosity
25 percentDrainage calculations·22 Sep 2006·p.14
“Porosity of Surficial Aquifer 25 percent”
Water quality treatment method
RetentionPermit·p.2
“A new stormwater system with stormwater treatment by retention”
Project area
0.88 acrePermit·p.2
“a .88 acre project to be constructed as per plans”
Construction sequencing
Retention and detention storage must be excavated to rough grade before any offsite discharge occurs and prior to building construction or placement of impervious surface within the area servedPermit·p.4
“Before any offsite discharge from the stormwater management system occurs”
Wetland protection
All wetland areas or water bodies outside the specific limits of construction authorized by the permit must be protected from erosion, siltation, scouring, excess turbidity and dewateringPermit·p.7
“All wetland areas or water bodies that are outside the specific limits”
Project acreage
0.880 acreTechnical Staff Report·26 Jan 2001·p.1
“a .88-acre project to be constructed as per plans received”
Receiving water body
Crystal Lake, Class III FreshTechnical Staff Report·26 Jan 2001·p.1
“Receiving Water Body: Crystal Lake”
Special basin criteria
N/A - no special basin criteria applyTechnical Staff Report·26 Jan 2001·p.1
“Special Basin Criteria: N/A”
Mean annual storm attenuation
Yes - providedTechnical Staff Report·26 Jan 2001·p.1
“Mean Annual Storm Attenuation Provided:”
Water quality volume recovery
Yes - recovery of water quality volume within required timeTechnical Staff Report·26 Jan 2001·p.1
“Recovery of Water Quality Vol. Within Req. Time:”
Peak attenuation volume recovery
Yes - recovery of peak attenuation volume within required timeTechnical Staff Report·26 Jan 2001·p.1
“Recovery of Peak Attenuation Vol. Within Req. Time:”
Wetland review approval
Yes - wetland review approval receivedTechnical Staff Report·26 Jan 2001·p.1
“Wetland Review Approval Received:”
Permitting authority
40C-42.022(1)(a), 40C-42.022(1)(b)Technical Staff Report·26 Jan 2001·p.1
“40C-42.022(1)(a), 40C-42.022(1)(b)”
Regency Pointe Commercial/Professional Center 71294-126 governing-sequence
Water-quality treatment
stormwater treatment by retentionPermit·p.2
“A new stormwater system with stormwater treatment by retention to serve Regency Pointe”
Permitted project area
3.90 acresPermit·p.2
“Commercial/Professional Center, a 3.90 acre project to be constructed as per plans received by”
Construction permit duration
expires five years from date of issuancePermit·p.4
“This permit for construction will expire five years from the date of issuance unless”
Offsite discharge precondition
retention and detention storage must be excavated to rough grade before any offsite discharge occursPermit·p.4
“Before any offsite discharge from the stormwater management system occurs, the retention”
Om inspection reporting
inspection reports due two years after operation phase becomes effective and every two years thereafter on District Form EN-46Permit·p.7
“years after the operation phase permit becomes effective and every two years thereafter”
Design storm attenuation
25yr/24hr storm eventDrainage calculations·22 Sep 2006·p.86
“provide water quality treatment, as well as provide peak attenuation for the 25yr/24hr storm”
Water quality treatment volume required
0.409 ac-ftDrainage calculations·22 Sep 2006·p.92
“use 0.409 ac.- ft. as the required treatment volume”
Treatment volume provided
0.811 ac-ft below weir elevation 52.75 ft-mslDrainage calculations·22 Sep 2006·p.92
“will be at elevation 52.75 ft-msl. @ 0.811 ac-ft.”
Mean annual storm analyzed
2.3 yr / 24 hr (SJRWMD mean annual storm)Drainage calculations·22 Sep 2006·p.94
“(SJRWMD - MEAN ANNUAL STORM)”
Pre development peak discharge 25yr
2.50 cfsDrainage calculations·22 Sep 2006·p.107
“2.50”
Post development peak discharge 25yr
1.41 cfsDrainage calculations·22 Sep 2006·p.138
“1.41”
Peak stage 25yr
53.69 ftDrainage calculations·22 Sep 2006·p.138
“53.69”
Pre development peak discharge 100yr
4.28 cfsDrainage calculations·22 Sep 2006·p.113
“4.28”
Peak stage 100yr
54.39 ftDrainage calculations·22 Sep 2006·p.147
“54.39”
Post development peak discharge 100yr
1.95 cfsDrainage calculations·22 Sep 2006·p.147
“1.95”
Peak stage 10yr
53.32 ftDrainage calculations·22 Sep 2006·p.129
“53.32”
Peak stage mean annual
52.49 (pond max outflow reported as 0.00 cfs for the 2.3yr/24hr storm) ftDrainage calculations·22 Sep 2006·p.120
“52.49”
Treatment volume recovery time
0.1610 days total recovery time; 100% of 21,519 cf runoff volume recoveredDrainage calculations·22 Sep 2006·p.158
“0.1610”
Om entity documents
Articles of Incorporation for Regency Pointe Association, Inc. and Declaration of Condominium submitted to District General Counsel to satisfy O&M entity requirementsAs-built·22 Sep 2006·p.12
“Enclosed are a blacklined set of Articles of Incorporation for Regency Pointe”
Water-quality treatment
RetentionTechnical Staff Report·17 Sep 2001·p.1
“Type of Treatment: Retention”
Receiving water body
Lake Jesup, Class III FreshTechnical Staff Report·17 Sep 2001·p.1
“Receiving Water Body: Lake Jesup”
Special basin criteria
N/ATechnical Staff Report·17 Sep 2001·p.1
“Special Basin Criteria: N/A”
Mean annual storm attenuation
Provided (Yes)Technical Staff Report·17 Sep 2001·p.1
“Mean Annual Storm Attenuation Provided: Yes”
Water quality volume recovery
Recovered within required time (Yes)Technical Staff Report·17 Sep 2001·p.1
“Recovery of Water Quality Vol. Within Req. Time: Yes”
Peak attenuation volume recovery
Recovered within required time (Yes)Technical Staff Report·17 Sep 2001·p.1
“Recovery of Peak Attenuation Vol. Within Req. Time: Yes”
Project area
3.900 acresTechnical Staff Report·17 Sep 2001·p.1
“Project Acreage: 3.900”
Cold Mix Paving of City's dirt streets - all phases 76767-30 governing-sequence · 10 file history
Lineage: every attributable document here is from seq 1 (documents dated 2006) — none from governing seq 3 (“Cold Mix Paving of City's dirt streets - all phases”, 2006). Entries below are file history, not the governing record.
Water-quality treatment
Best Management Practices including swales with ditch blocks (modification to an existing system)seq 1Permit·p.2
“MANAGEMENT PRACTICES, INCLUDING SWALES W/ DITCH”
Wetland protection
All wetland areas or water bodies outside the authorized limits of construction must be protected from erosion, siltation, scouring or excess turbidity, and dewateringseq 1Permit·p.5
“permit must be protected from erosion, siltation, scouring”
Construction limits designation
Permittee must clearly designate the limits of construction on-site prior to construction; work outside those limits, including clearing, may be a permit violationseq 1Permit·p.5
“Prior to construction, the permittee must clearly designate”
Scope exclusion 8th street
This permit does not authorize the paving of 8th Streetseq 1Permit·p.5
“This permit does not authorize the paving of 8th Street.”
As built certification
As-built certification form must be completed within 30 days of completion of construction of the permitted system, including all site workseq 1Permit·p.2
“within 30 days of completion of construction of the permitted system,”
Dewatering consumptive use threshold
A Consumptive Use Permit (40C-2) must be obtained before dewatering if pumps/wells can withdraw 1,000,000 gallons per day or more, or an average of 100,000 gallons per day or more over a year, with off-site dischargeseq 1Permit·p.3
“per day or more, or an average of 100,000 gallons per day or more”
Receiving water class
Class III receiving waters (Lake Mary, Crystal Lake, and unnamed wetlands to the south)seq 1Technical Staff Report·p.2
“Class: III”
Water-quality treatment
Swales with ditch blocks (treatment type 8) plus Other (12): BMPsseq 1Technical Staff Report·p.2
“Swales w/ditch blocks (8)”
Scope exclusion 8th street
Permit authorization does not include the paving of 8th Street; that paving was previously authorized by Permit No. 42-117-1340N-ERPseq 1Technical Staff Report·p.2
“prolect has been previously authorized by Permit No. 42-117-1340N-ERP.”
Special conditions applied
November 9, 1995 Special Conditions 10 and 13 apply, plus 1 other listed condition (paving of 8th Street not authorized)seq 1Technical Staff Report·p.2
“November 9, 1995 Special Conditions: 10, 13”
City of Lake Mary Police Station Retention Pond 76781-30 governing-sequence · 17 file history
Lineage: every attributable document here is from seq 1 (“NEW POLICE STATION”, 1999) — none from governing seq 3 (“City of Lake Mary Police Station Retention Pond”, 2013). Entries below are file history, not the governing record.
Design storm
SJRWMD mean annual storm event (modeled as SJRWMD96 96-hr rainfall file, 11.3 in) and City of Lake Mary 25-year 24-hour storm event (8.7 in)seq 1Drainage calculations·27 Dec 2007·p.4
“applied with total rainlalls of 11.3" and 8.7"”
Pre post discharge
Open basin; system designed to maintain pre/post discharge for the mean annual and 25-yr/24-hr storm eventsseq 1Drainage calculations·27 Dec 2007·p.5
“open basin and is designed to maintain the pre/post discharge for the mean annual and 25/24 storm”
Allowable discharge cfs
3.89 (pre-development peak outflow at outfall node DEP, 25-yr/24-hr storm; the pre-development rate the post condition must not exceed) cfsseq 1Drainage calculations·27 Dec 2007·p.13
“25YR24HR 12.28 54.34 54.00 0.0491 2078.11 12.25 4.00 12.28 3.89”
Post development peak discharge cfs
1.69 (Pond A maximum outflow, 25-yr/24-hr storm, at maximum stage 58.56 ft) cfsseq 1Drainage calculations·27 Dec 2007·p.23
“25YR24RR 12.85 58.56 59.00 0.0427 20435.66 12.00 12.87 12.85 1.69”
Peak stage
58.97 (maximum stage in Pond A from routing analysis, per executive summary) ftseq 1Drainage calculations·27 Dec 2007·p.5
“The routing analysis for Pond A indicates a maximum stage of 58.97 feet.”
Freeboard ft
at least 1 foot of freeboard maintained in Pond A during design storm events ftseq 1Drainage calculations·27 Dec 2007·p.5
“events while maintaining at least one foot of freeboard in Pond A.”
Water-quality treatment
Required dry retention water quality volume 7,623 cf, the greater of 0.5 in over the 3.969-ac site (7,204 cf) or 1.25 in over the 1.68-ac build-out impervious area (7,623 cf) ft3seq 1Drainage calculations·27 Dec 2007·p.28
“A 3.969 0.5 7,204 1.68* 1.25 7,623 7,623”
Water quality volume provided
34,173 (volume held between pond bottom and the control elevation) ft3seq 1Drainage calculations·27 Dec 2007·p.28
“designed to hold a volume of 34,173 ft between the bottom and the”
Pond recovery
Pond recovers within 14 days (PONDS Version 3.0.9 analysis)seq 1Drainage calculations·27 Dec 2007·p.30
“The proposed pond recovers within 14 days using the software program PONDS Version 3.0.9.”
Water-quality treatment
Stormwater treatment by retention (new stormwater system under Chapter 40C-42, F.A.C.)seq 1Permit·p.2
“AUTHORIZATION: A NEW STORMWATER SYSTEM WITH STORMWATER TREATMENT BY”
Wetland protection
Condition 1: all wetland areas or water bodies outside the authorized limits of construction must be protected from erosion, siltation, scouring or excess turbidity, and dewateringseq 1Permit·p.5
“permit must be protected from erosion, siltation, scouring”
Inspection reporting
Condition 2: O&M entity must submit inspection reports on District form EN-46 two years after the operation phase permit becomes effective and every two years thereafter, signed and sealed by a registered professionalseq 1Permit·p.5
“phase permit becomes effective and every two years thereafter”
As built certification
As-built certification form must be completed within 30 days of completion of construction of the permitted system, including all site workseq 1Permit·p.2
“within 30 days of completion of construction of the permitted system,”
Dewatering consumptive use
A Consumptive Use Permit (40C-2) is required before dewatering if pumps/wells can withdraw one million gallons per day or more, or an average of 100,000 gpd or more over a year, with off-site dischargeseq 1Permit·p.3
“per day or more, or an average of 100,000 gallons per day or more”
Receiving water body
Lake Mary, Class III (class shown as 'III' on the form; text layer is garbled at that spot)seq 1Technical Staff Report·p.2
“Receiving Water Body: Lake Mary Class: jfl”
General permit category
40C-42.024(2)(b) - Retention Underdrain, Exfiltration, Wet Detention, Swales, or Dry Detention (category checked; treatment type checked is Retention(1))seq 1Technical Staff Report·p.2
“40C-42.024(2)(b) Retention Underdrain, Exfiltration, Wet”
Special conditions
September 25, 1991 special conditions applied, handwritten as 2, 10, 28 (text layer garbled; page shows Special Conditions: 2,10,28)seq 1Technical Staff Report·p.2
“September 25, 1991 Special Conditions:t10,28”
Medlin Professional Office 85947-137 governing-sequence
Permit rule authority
Chapter 40C-42, F.A.C.; permit issued by SJRWMD staff on October 29, 2002Permit·p.2
“in accordance with Chapter 40C-42, F.A.C.”
Construction permit duration
5 years from date of issuancePermit·p.4
“This permit for construction will expire five years from the date of issuance”
Pre discharge excavation requirement
Retention and detention storage must be excavated to rough grade before any offsite discharge occurs and before building construction or placement of impervious surface in the area servedPermit·p.4
“the retention and detention storage must be excavated to rough grade”
Plans of record
System must be constructed and operated in accordance with the plans received by the District on October 1, 2002Permit·p.6
“must be constructed and operated in accordance with the plans received by the District on October 1, 2002”
Operation inspection frequency
Once within two years after completion of construction and every two years thereafter, with an Exceptions Report on form 40C-42.900(6) within 14 days if the system is not functioning as designedPermit·p.6
“inspect the Stormwater or surface water management system once within two years after the completion of construction”
Peak discharge post development 25yr 96hr
0.2928 cfsDrainage calculations·9 Feb 2007·p.26
“50.187 0.2928 None None 52.533 1209.9”
Peak stage post development 25yr 96hr
50.37 ft datumDrainage calculations·9 Feb 2007·p.26
“10.533 45.79 50.187 50.37”
Discharge volume post development 25yr 96hr
1209.9 cubic feetDrainage calculations·9 Feb 2007·p.26
“50.187 0.2928 None None 52.533 1209.9”
Peak discharge post development 100yr 24hr
0.4223 cfsDrainage calculations·9 Feb 2007·p.28
“13.253 0.4223 None None 17.893 4042.7”
Peak stage post development 100yr 24hr
50.56 ft datumDrainage calculations·9 Feb 2007·p.28
“4.693 46.21 13.253 50.56”
Peak discharge pre development 25yr 96hr
0.5715 cfsDrainage calculations·9 Feb 2007·p.9
“48.933 0.5715 None None 56.933 5959.3”
Peak stage pre development 25yr 96hr
51.04 ft datumDrainage calculations·9 Feb 2007·p.9
“35.511 48.58 48.933 51.04”
Peak discharge pre development 100yr 24hr
1.8367 cfsDrainage calculations·9 Feb 2007·p.11
“12.844 1.8367 None None 24.711 13934.0”
Peak stage pre development 100yr 24hr
51.20 ft datumDrainage calculations·9 Feb 2007·p.11
“9.111 49.24 12.844 51.20”
Design storm 25yr
25-year, 96-hour, 12.5 inches of rainfall, SCS Type II Florida Modified distributionDrainage calculations·9 Feb 2007·p.20
“Design Rainfall Depth (inches) 12.5 Design Rainfall Duration (hours) 96.0”
Design storm 100yr
100-year, 24-hour, 11.6 inches of rainfall, SCS Type II Florida Modified distributionDrainage calculations·9 Feb 2007·p.21
“Design Rainfall Depth (inches) 11.6 Design Rainfall Duration (hours) 24.0”
Mean annual storm
2.7 inches over 24 hours (Scenario 4); the model shows no discharge from the pond for this eventDrainage calculations·9 Feb 2007·p.20
“Design Rainfall Depth (inches) 2.7”
Water quality treatment volume
6256 cubic feetDrainage calculations·9 Feb 2007·p.20
“Treatment Volume (ft3) 6256”
Water quality treatment volume basis
Handwritten pollution abatement volume calculation: 2.5 inches over 17,399 sq ft impervious = 3,624 cf, plus 0.5 inches over 63,162 sq ft site and offsite = 2,632 cf, totaling 6,256 cfDrainage calculations·9 Feb 2007·p.20
“2.5" over 17,399 FT2 IMP. = 3624 FT3”
Treatment volume recovery
The 6,256 cf treatment volume infiltrates fully; 36-hour stage 46.51 ft with 6,256.0 cf infiltrated and 72-hour stage 46.84 ft with 6,256.0 cf infiltratedDrainage calculations·9 Feb 2007·p.22
“36.000 46.51 6256.0 72.000 46.84 6256.0”
Control elevation
50.61 ft datum (centerline of the 8-inch outfall)Drainage calculations·9 Feb 2007·p.19
“Description: 8" CLDIP Outfall (C/L at 50.61)”
Post development basin parameters
Basin area 1.450 acres, time of concentration 12.0 minutes, DCIA 28.0 percent, curve number 55Drainage calculations·9 Feb 2007·p.20
“Basin Area (acres) 1.450 Time Of Concentration (minutes) 12.0 DCIA (%) 28.0 Curve Number 55”
Design water table elevation
45.00 ft datum (post-development model initial groundwater level)Drainage calculations·9 Feb 2007·p.18
“Water Table Elevation, [Wi] (ft datum): 45.00”
Design hydraulic conductivity
14.00 ft/day (horizontal saturated hydraulic conductivity, Kh)Drainage calculations·9 Feb 2007·p.18
“Horizontal Saturated Hydraulic Conductivity, [Kh] (ft/day): 14.00”
Fillable porosity
25.00 percentDrainage calculations·9 Feb 2007·p.18
“Fillable Porosity, En] (%): 25.00”
Geotechnical stormwater design parameters
Universal Engineering Sciences Table 3: depth of confining layer 3 ft, horizontal saturated hydraulic conductivity 14 ft/day, vertical unsaturated infiltration 9 ft/day, fillable porosity 25 percent, perched seasonal high groundwater table 2 ft at borings P-3 and P-4Drainage calculations·9 Feb 2007·p.42
“Horizontal Saturated Hydraulic Conductivity for Surficial Sand Layer [SP] (feet per day) 14”
Design storm
25-year, 96-hour; the system stores the difference in direct runoff volume between the pre-development and post-development conditionsTechnical Staff Report·29 Oct 2002·p.2
“designed to store the difference of the direct runoff volume for the 25-year, 96-hour storm events”
Water quality treatment method
RetentionTechnical Staff Report·29 Oct 2002·p.1
“Type of Treatment: Retention”
Mean annual storm attenuation
ProvidedTechnical Staff Report·29 Oct 2002·p.1
“Mean Annual Storm Attenuation Provided: Yes”
Water quality volume recovery
Recovery of water quality volume within required time: YesTechnical Staff Report·29 Oct 2002·p.1
“Recovery of Water Quality Vol. Within Req. Time: Yes”
Peak attenuation volume recovery
Recovery of peak attenuation volume within required time: YesTechnical Staff Report·29 Oct 2002·p.1
“Recovery of Peak Attenuation Vol. Within Req. Time: Yes”
Project acreage
1.010 acresTechnical Staff Report·29 Oct 2002·p.1
“Project Name: Medlin Professional Office Project Acreage: 1.010”
Receiving water body
Crystal Lake, Class III Fresh; Lake Monroe Unit (4D) planning unitTechnical Staff Report·29 Oct 2002·p.1
“Receiving Water Body: Crystal Lake Class: III Fresh.”
Special basin criteria
N/A - no special basin criteria applyTechnical Staff Report·29 Oct 2002·p.1
“Special Basin Criteria: N/A”
Wetland review
Wetland review approval received: Yes. No wetland mitigation or conservation easement is described in this report.Technical Staff Report·29 Oct 2002·p.1
“Wetland Review Approval Received: Yes”
Permit rule authority
40C-42.022(1)(a), 40C-42.022(1)(b); project found consistent with Chapter 40C-42, F.A.C.Technical Staff Report·29 Oct 2002·p.1
“Authority: 40C-42.022(1)(a), 40C-42.022(1)(b)”
Operation maintenance entity
Applicant (EEMJ/SM Family Trust)Technical Staff Report·29 Oct 2002·p.1
“Final O&M Entity: Applicant (EEMJ/SM Family Trust)”
Seminole Ave Pond Expansion 86365-100 governing-sequence · 22 file history
Lineage: every attributable document here is from seq 1 (documents dated 2002–2008) — none from governing seq 10 (“Seminole Ave Pond Expansion”, 2020). Entries below are file history, not the governing record.
Regulatory authority
Chapter 40C-42, F.A.C. (Regulation of Stormwater Management Systems)seq 1Permit·p.2
“CHAPTER 40C-42, F.A.C.”
Construction permit expiration
5 yearsseq 1Permit·p.4
“will expire five years from the date of issuance”
As built certification deadline
30 daysseq 1Permit·p.2
“within 30 days of completion of construction of the permitted system”
Retention excavation before offsite discharge
Retention and detention storage must be excavated to rough grade prior to building construction or placement of impervious surface, before any offsite discharge occursseq 1Permit·p.4
“Before any offsite discharge from the stormwater management system occurs”
Om inspection frequency
Inspection once within two years after completion of construction and every two years thereafterseq 1Permit·p.6
“once within two years after the completion of construction”
Design storm 100yr 24hr
10.6 inchesseq 1Drainage calculations·7 Jan 2008·p.6
“lOOyr/24hr 10.6 Storm Event”
Design storm 25yr 96hr
11.0 inchesseq 1Drainage calculations·7 Jan 2008·p.30
“25yr/96hr 11.0" Storm Event”
Peak stage 100yr 24hr
55.79 ft datumseq 1Drainage calculations·7 Jan 2008·p.27
“55.79”
Peak stage 25yr 96hr
54.983 ft datumseq 1Drainage calculations·7 Jan 2008·p.34
“54.983”
Allowable discharge cfs
0 - full retention; all three modeled discharge structures inactive and cumulative discharge 0.0 cf at end of simulation for both design stormsseq 1Drainage calculations·7 Jan 2008·p.27
“Discharge Structure 1 - inactive”
Water quality treatment volume
10480 ft3seq 1Drainage calculations·7 Jan 2008·p.101
“10480”
Treatment volume recovery 72hr
Full treatment volume (10,480 cf) infiltrated, pond stage down to 50.55 ft at 72 hours after slug loadseq 1Drainage calculations·7 Jan 2008·p.103
“50.55”
Receiving water body
Dawson Lakeseq 1Technical Staff Report·26 Nov 2002·p.1
“Dawson Lake”
Receiving water class
Class III Freshseq 1Technical Staff Report·26 Nov 2002·p.1
“III Fresh.”
Special basin criteria
N/Aseq 1Technical Staff Report·26 Nov 2002·p.1
“Special Basin Criteria:”
Water-quality treatment
Retentionseq 1Technical Staff Report·26 Nov 2002·p.1
“Retention”
Design storm
Pond retains the entire post-development stormwater runoff volume from the 100-year, 24-hour storm eventseq 1Technical Staff Report·26 Nov 2002·p.2
“100-year, 24-hour storm event.”
Water quality recovery
Yes - water quality volume recovers within required timeseq 1Technical Staff Report·26 Nov 2002·p.1
“Recovery of Water Quality Vol. Within Req. Time:”
Regulatory authority
Chapter 40C-42, F.A.C.seq 1Technical Staff Report·26 Nov 2002·p.2
“as set forth in Chapter 40C-42, F.A.C.”
Erp general conditions
ERP Stormwater General Conditions by Rule (October 03, 1995): 1 through 19seq 1Technical Staff Report·26 Nov 2002·p.2
“1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19”
Erp special conditions
ERP/MSSW/Stormwater Special Conditions (November 09, 1995): 10 and 13seq 1Technical Staff Report·26 Nov 2002·p.2
“10, 13”
Wetland review
N/A - no wetland review approval requiredseq 1Technical Staff Report·26 Nov 2002·p.1
“Wetland Review Approval Received:”
GTE Federal Credit Union-Lake Mary 87951-19 governing-sequence
Water-quality treatment
Stormwater treatment by retentionPermit·p.2
“Construction of a Stormwater Management System with stormwater treatment by retention for”
Construction permit expiration
5 years from date of issuancePermit·p.4
“This permit for construction will expire five years from the date of issuance”
Pre discharge excavation requirement
Retention and detention storage must be excavated to rough grade before any off-site discharge occurs and prior to building construction or placement of impervious surfacePermit·p.4
“Before any off site discharge from the stormwater management system occurs, the retention”
Om inspection frequency
Inspect once within 2 years after completion of construction and every 2 years thereafterPermit·p.6
“management system once within two years after the completion of construction and every”
Water-quality treatment
RetentionTechnical Staff Report·16 May 2003·p.1
“Type of Treatment: Retention”
Receiving water classification
Lake Mary, Class III FreshTechnical Staff Report·16 May 2003·p.1
“Receiving Water Body: Lake Mary Class: III Fresh.”
Mean annual storm attenuation
Provided (Yes)Technical Staff Report·16 May 2003·p.1
“Mean Annual Storm Attenuation Provided: Yes”
Water quality volume recovery
Recovered within required time (Yes)Technical Staff Report·16 May 2003·p.1
“Recovery of Water Quality Vol. Within Req. Time: Yes”
Discharge condition
System discharges, as in the pre-development condition, to the existing roadway drainage systemTechnical Staff Report·16 May 2003·p.2
“development condition, to the existing roadway drainage system.”
Cambridge Prep School - Lake Mary Blvd. 98061-126 governing-sequence
Seasonal high groundwater depth
on the order of 3 feet below existing grade at the boring locations ft below gradeDrainage calculations·6 May 2005·p.8
“the seasonal high groundwater levels could be on the order of 3 feet below the existing grade at”
Observed groundwater depth
about 4 feet below the existing ground surface ft below gradeDrainage calculations·6 May 2005·p.8
“groundwater level was about 4 feet below the existing ground surface for this project.”
Design infiltration rate
Darcy's K of 2 feet per day recommended for the gray clayey sand ft/dayDrainage calculations·6 May 2005·p.8
“we recommend using Darcy's K of 2 feet per day for”
Confining unit depth
gray clayey sand at approximately 6 feet below existing grade, to be considered a confining unit for analysis ft below gradeDrainage calculations·6 May 2005·p.8
“approximately 6 feet below existing grade”
Pre development peak discharge 25yr 24hr
2.27 cfsDrainage calculations·21 Mar 2005·p.4
“2.27 CFS”
Post development peak discharge 25yr 24hr
2.12 cfsDrainage calculations·21 Mar 2005·p.4
“2.12 CFS”
Pre development peak discharge mean annual
1.02 cfsDrainage calculations·21 Mar 2005·p.4
“1.02 CFS”
Post development peak discharge mean annual
0.48 cfsDrainage calculations·21 Mar 2005·p.4
“0.48 CFS”
Drawdown time
less than 72 hours for pre/post volumeDrainage calculations·21 Mar 2005·p.4
“<72 HOURS”
Design storm
25-year/24-hour (SCS II MOD)Drainage calculations·21 Mar 2005·p.13
“CAMBRIDGE PREP LK MARY - PRE DEVELOPMENT - 25 YR/24 HR”
Design storm rainfall
8.60 inDrainage calculations·21 Mar 2005·p.13
“8.60”
Water-quality treatment
dry retention of first 1.0 inch of runoff from drainage area, or 1.25 inch x impervious area plus first 0.5 inch of runoff from drainage areaDrainage calculations·21 Mar 2005·p.20
“FIRST 1.0" OF RUNOFF FROM DRAINAGE AREA OR”
Water quality volume
0.095 ac-ftDrainage calculations·21 Mar 2005·p.20
“0.095 AC-FT”
Required retention volume
0.110 (25 yr/24 hr pre vs. post differential volume; retention volume provided = 0.110 ac-ft)Drainage calculations·21 Mar 2005·p.20
“0.110 AC-FT”
Peak stage
53.71 (design high water level; also max 25-yr/24-hr stage at pond Node 11) ftDrainage calculations·21 Mar 2005·p.30
“53.71 ft”
Seasonal high groundwater elevation
49.00 ftDrainage calculations·21 Mar 2005·p.29
“49.00 ft”
Regulatory authority
Chapter 40C-42, F.A.C. (Regulation of Stormwater Management Systems)Permit·3 Jun 2005·p.1
“CHAPTER 40C-42, F.A.C.”
Construction permit expiration
five years from the date of issuancePermit·3 Jun 2005·p.3
“This permit for construction will expire five years from the date of issuance unless otherwise”
Pre discharge excavation requirement
retention and detention storage must be excavated to rough grade prior to building construction or placement of impervious surface, before any offsite discharge occursPermit·3 Jun 2005·p.3
“Before any offsite discharge from the stormwater management system occurs, the retention”
As built certification deadline
as-built certification form due within 30 days of completion of construction of the permitted systemPermit·3 Jun 2005·p.1
“Complete this form within 30 days of completion of construction of the permitted system,”
Om inspection interval
inspect the system once within two years after completion of construction and every two years thereafterPermit·3 Jun 2005·p.5
“management system once within two years after the completion of construction and every”
Stabilization timeframe
stabilization measures for erosion and sediment control initiated on disturbed areas in no case more than seven (7) days after construction activity has temporarily or permanently ceasedPermit·3 Jun 2005·p.4
“but in no case more than seven (7) days before the construction”
Receiving waterbody
Crystal LakeTechnical Staff Report·3 Jun 2005·p.1
“Crystal Lake”
Receiving water classification
Class III FreshTechnical Staff Report·3 Jun 2005·p.1
“III Fresh.”
Water-quality treatment
Exfiltration Trench, RetentionTechnical Staff Report·3 Jun 2005·p.1
“Exfiltration Trench, Retention”
Mean annual storm attenuation
Provided (Yes)Technical Staff Report·3 Jun 2005·p.1
“Mean Annual Storm Attenuation Provided:”
Watson Center at Lake Mary 98533-143 governing-sequence
Project area
5.0784 acresDrainage calculations·31 May 2006·p.2
“The proposed development consists of 5.0784 acres”
Pre development discharge basin 1b
3.014 cfsDrainage calculations·31 May 2006·p.2
“maximum discharge rate for basin lB is 3.014 cfs and the post-development”
Post development discharge basin 1b
2.53 cfsDrainage calculations·31 May 2006·p.2
“maximum discharge rate is 2.53 cfs”
Pre development discharge basin 2b
2.078 cfsDrainage calculations·31 May 2006·p.2
“maximum discharge from Basin 2B is 2.078 cfs”
Retention recovery time
Basin 2B discharge is held in Pond A-16 and percolates in less than 36 hoursDrainage calculations·31 May 2006·p.2
“A- 16 and percolates in less than thirty-six (36) hours”
Design storm
100-year 24-hourDrainage calculations·31 May 2006·p.16
“100-year 24-hour Simulation”
Design storm
25-year 24-hourDrainage calculations·31 May 2006·p.16
“025-year 24-hour Simulation”
Rainfall depth 100yr 24hr
10.50 inchesDrainage calculations·31 May 2006·p.16
“Rainfall Axount(in) : 10.50”
Rainfall depth 25yr 24hr
8.60 inchesDrainage calculations·31 May 2006·p.39
“Rainfall Amount (in): 8.60”
Treatment volume Pond A
13186 ft3Drainage calculations·31 May 2006·p.43
“Treatment Volume (if3) 13186”
Treatment volume Pond B
4108 ft3Drainage calculations·31 May 2006·p.48
“Treatment Volume (ft3) 4108”
Pond A 36-hour recovery
Full 13,186 ft3 treatment volume infiltrated by 36 hours; stage down to 51.15 ft datumDrainage calculations·31 May 2006·p.44
“36 Hour Stage and Infiltration Volume 36.000 51.15 13186.0”
Pond B 36-hour recovery
Full 4,108 ft3 treatment volume infiltrated by 36 hours; stage down to 50.36 ft datumDrainage calculations·31 May 2006·p.49
“36 Hour Stage and Infiltration Volume 36.000 50.36 4108.0”
Pond A max stage 25yr
55.037 ftDrainage calculations·31 May 2006·p.9
“POND-A BASE 025Y-24M 18.43 55.037”
Pond A max stage 100yr
56.160 ftDrainage calculations·31 May 2006·p.9
“POND-A BASE l0OY-24H 18.06 56.160”
Pond A max outflow 25yr
2.815 cfsDrainage calculations·31 May 2006·p.9
“18.43 55.037 55.000 0.0050 24297 13.25 11.410 18.43 2.815”
Pond A max outflow 100yr
3.924 cfsDrainage calculations·31 May 2006·p.9
“18.06 56.160 55.000 0.0050 27351 13.25 15.017 18.06 3.924”
Water table elevation
48.50 ft datumDrainage calculations·31 May 2006·p.42
“Water Table Elevation, [Wi] (ft datum): 48.50”
Base of aquifer elevation
45.50 ft datumDrainage calculations·31 May 2006·p.42
“Base Of Aquifer Elevation, [B] (ft datum): 45.50”
Hydraulic conductivity Pond A
34.50 ft/dayDrainage calculations·31 May 2006·p.42
“Horizontal Saturated Hydraulic Conductivity, [Kh] (ft/day): 34.50”
Hydraulic conductivity Pond B
25.90 ft/dayDrainage calculations·31 May 2006·p.47
“Horizontal Saturated Hydraulic Conductivity, [Kb] (ft/day): 25.90”
Onsite basin curve number
62.90 over 5.074 acres (ICPR basin BSN-A)Drainage calculations·31 May 2006·p.13
“AreaCac) 5.074 Curve Number: 62.90”
Water quality treatment method
Off-line retention pondPermit·3 Jul 2006·p.1
“retention pond for Watson Center at Lake Mary, a 5.08-acre project”
Project area
5.08 acresPermit·3 Jul 2006·p.1
“a 5.08-acre project to be constructed as per”
Impervious limits
No numeric cap stated; any impervious surface exceeding the imperviousness shown on the permitted plans requires a permit modificationPermit·3 Jul 2006·p.5
“Placement of additional impervious surfaces, exceeding the imperviousness shown on the permitted plans”
Construction permit duration
5 years from date of issuancePermit·3 Jul 2006·p.3
“This permit for construction will expire five years from the date of issuance”
Wetland protection
Wetland areas and water bodies outside the authorized limits of construction must be protected from erosion, siltation, scouring, excess turbidity and dewateringPermit·3 Jul 2006·p.5
“All wetland areas or water bodies that are outside the specific limits of construction”
Inspection frequency
Once within two years after completion of construction and every two years thereafter, by the operation and maintenance entityPermit·3 Jul 2006·p.5
“shall inspect the stormwater or surface water management system once within two years”
Pre discharge grading requirement
Retention and detention storage must be excavated to rough grade before any offsite discharge occurs and before building construction or placement of impervious surfacePermit·3 Jul 2006·p.3
“and detention storage must be excavated to rough grade”
Water quality treatment method
RetentionTechnical Staff Report·3 Jul 2006·p.1
“Type of Treatment: Retention”
Project acreage
5.078 acresTechnical Staff Report·3 Jul 2006·p.1
“Project Acreage: 5.078”
Receiving water body
Crystal Lake, Class III FreshTechnical Staff Report·3 Jul 2006·p.1
“Receiving Water Body: Crystal Lake”
Permitting authority
40C-42.022(1)(a), 40C-42.022(1)(b)Technical Staff Report·3 Jul 2006·p.1
“Authority: 40C-42.022(1)(a), 40C-42.022(1)(b)”
Special basin criteria
N/ATechnical Staff Report·3 Jul 2006·p.1
“Special Basin Criteria: N/A”
Mean annual storm attenuation
N/A (not provided)Technical Staff Report·3 Jul 2006·p.1
“Mean Annual Storm Attenuation Provided: N/A”
Water quality volume recovery
Yes - water quality volume recovers within required timeTechnical Staff Report·3 Jul 2006·p.1
“Recovery of Water Quality Vol. Within Req. Time: Yes”
Peak attenuation volume recovery
N/ATechnical Staff Report·3 Jul 2006·p.1
“Recovery of Peak Attenuation Vol. Within Req. Time: N/A”
Wetland review approval
Yes - wetland review approval receivedTechnical Staff Report·3 Jul 2006·p.1
“Wetland Review Approval Received: Yes”
Impervious percentage on plans
33 percentTechnical Staff Report·3 Jul 2006·p.2
“The proposed imperviousness shown on the plans is 33%, the calculations assume an”
Impervious percentage in calculations
49 percentTechnical Staff Report·3 Jul 2006·p.2
“imperviousness of 49%”
Impervious limits
Impervious surface exceeding the imperviousness shown on the permitted plans requires a permit modificationTechnical Staff Report·3 Jul 2006·p.2
“Placement of additional impervious surfaces, exceeding the imperviousness”
Operation and maintenance entity
Watson Realty CorporationTechnical Staff Report·3 Jul 2006·p.1
“Final O&M Entity: Watson Realty Corporation”
Inspection frequency
Once within two years after completion of construction and every two years thereafter; Exceptions Report within 14 days if the system is not functioning as permittedTechnical Staff Report·3 Jul 2006·p.2
“water management system once within two years after the completion of”
Ruskin St, Johnson Ave, & S 4th St Paving & Drainage Improvements 98636-117 governing-sequence
Qualifying rule
Project qualifies for the Stormwater (40C-42) permit pursuant to Chapter 40C-42.024(2)(d), F.A.C. (SJRWMD pre-application determination)Drainage calculations·25 Apr 2005·p.51
“42024(2)(d), F,A.C. your proposed project qualifies for the Stormwater (40C-42) permit.”
Pavement type
Pervious open-graded cold-mix pavement processDrainage calculations·25 Apr 2005·p.51
“a pervious open-graded cold-mix process”
Hydrologic soil groups
Ruskin Street and South 4th Street soils are NRCS Hydrologic Group A; Johnson Avenue soils are Group BDrainage calculations·25 Apr 2005·p.52
“Street both have soils classified as by the NRCS as Hydrologic Group A. Soils along”
Wetland floodplain impacts
No wetland or floodplain impacts associated with the proposed improvementsDrainage calculations·25 Apr 2005·p.52
“There are no wetland or floodplain impacts associated with the proposed improvements.”
Project area
1.64 acresPermit·19 May 2005·p.1
“Improvements, a 1.64-acre project to be constructed as per information received by the District”
Construction permit expiration
Construction permit expires five years from date of issuance unless otherwise specified by special conditionPermit·19 May 2005·p.3
“This permit for construction will expire five years from the date of issuance unless otherwise”
As built certification deadline
As-built certification form must be completed within 30 days of completion of construction of the permitted system, including all site workPermit·19 May 2005·p.1
“Complete this form within 30 days of completion of construction of the permitted system,”
Dewatering consumptive use threshold
Consumptive Use Permit (40C-2) required before dewatering if facilities can withdraw one million gallons per day or more, or an average of 100,000 gallons per day or more over a year, with off-site dischargePermit·19 May 2005·p.2
“day or more, or an average of 100000 gallons per day or more over a year, and any discharge”
Retention detention rough grade
Retention and detention storage must be excavated to rough grade prior to building construction or placement of impervious surface within the area served, before any offsite discharge occursPermit·19 May 2005·p.3
“and detention storage must be excavated to rough grade prior to building construction or”
Erosion sediment control
Erosion and sediment control best management practices per chapter 6 of the Florida Land Development Manual (FDER 1988) required to retain sediment on-site and prevent water quality violationsPermit·19 May 2005·p.3
“accordance with the guidelines and specifications in chapter 6 of the Florida Land”
Stabilization deadline
Stabilization measures for disturbed areas initiated as soon as practicable, in no case more than seven (7) days after construction activity has temporarily or permanently ceasedPermit·19 May 2005·p.4
“or permanently ceased, but in no case more than seven (7) days before the construction”
Om inspection interval
O&M entity must inspect the stormwater management system once within two years after completion of construction and every two years thereafter; Exceptions Report (form 40C-42.900(6)) due within 14 days if the system is not functioning as designedPermit·19 May 2005·p.5
“management system once within two years after the completion of construction and every”
Water-quality treatment
Swales with ditch blocksTechnical Staff Report·19 May 2005·p.1
“Swales with Ditch blocks”
Receiving water body
Soldier's Creek (Class III)Technical Staff Report·19 May 2005·p.1
“Soldier’s Creek”
Qualifying rule
Qualifies under criteria for paving of an existing public dirt road by a public entity pursuant to 40C-42.024(2)(d), F.A.C. (no new development served, no additional lanes, no significant traffic increase, drainage system not significantly altered)Technical Staff Report·19 May 2005·p.2
“public entity pursuant to 40C-42.024(2)(d), F.A.C. as follows:”
Wetland impacts
Project will not involve dredging or filling in wetlands or other surface watersTechnical Staff Report·19 May 2005·p.2
“The project will not involve dredging or filling in wetlands or other surface”
Om inspection interval
O&M entity (City of Lake Mary) must inspect the system once within two years after completion of construction and every two years thereafterTechnical Staff Report·19 May 2005·p.2
“water management system once within two years after the completion of”

3 failed page verification — quarantined in Part 09.

Part 06

Stormwater infrastructure register

Ponds, swales, control structures, weirs, orifices, and outfalls documented in the permit record for this study area.

CNBS - Lake Mary 103055-19 governing-sequence
Washington Estates 108660-20 governing-sequence · 7 file history
Lineage: every attributable document here is from seq 1 (documents dated 2006–2008) — none from governing seq 2 (“Washington Estates”, 2014). Entries below are file history, not the governing record.
CR 15 from Ranoul Lane to CR 46A 110309-113 governing-sequence
Central Florida Commuter Rail - Lake Mary Station 114454-140 governing-sequence · 22 file history
Lineage: every attributable document here is from seq 1 (“Central Florida Commuter Rail Transit - Phase 1”, 2008) — none from governing seq 14 (“Central Florida Commuter Rail - Lake Mary Station”, 2013). Entries below are file history, not the governing record.
  • SwalesSwales and swales with blocks constructed to retain and infiltrate the 1-inch treatment volume of runoff from the project area seq 1Technical Staff Report·14 Oct 2008·p.9
  • Cross drain culverts11 cross drain culverts to be extended within the proposed double-track segments to maintain offsite flow patterns seq 1Technical Staff Report·14 Oct 2008·p.9
  • BridgeReplacement of the northern 114 feet of the existing 565-foot long wooden trestle bridge over the St. Johns River with a concrete trestle bridge seq 1Technical Staff Report·14 Oct 2008·p.7
  • Rail side ditchesExisting drainage ditches (other surface waters) along the railroad, constructed in uplands and through wetlands; work authorized in 7.44 acres of them seq 1Technical Staff Report·14 Oct 2008·p.7
  • Conveyance swalesOpen swales located parallel to the railroad embankment, added where right-of-way width allows, providing storage volume for the slight runoff increase from the second track and conveying runoff to cross drains or existing outfalls seq 1Drainage calculations·12 Dec 2007·p.12
  • Cross drain culvertsEleven culverts extended in the double-tracking areas; pipe sizes include 36" RCP, 24" RCP, 84" RCP, 98"x63" RCP, 18" RCP, and 6.25'x3.5' box; mitered end sections on nine, endwalls on two seq 1Drainage calculations·12 Dec 2007·p.12
  • Rail bridgeNorthernmost 114-foot span of the St. John's River rail bridge modified: wooden piles replaced by concrete piles and bridge deck replaced with concrete double box beams seq 1Drainage calculations·12 Dec 2007·p.13
  • Conveyance swalesExisting and proposed swales parallel to the tracks sized to accommodate the runoff difference between pre- and post-development conditions; swale volume tabulated per basin (ac-ft) seq 1Drainage calculations·12 Dec 2007·p.2
  • Floodplain encroachment areasTen floodplain encroachment/compensation reaches identified by milepost/station across St. Johns River Monroe, Soldier Creek, Cranes Roost Outlet, and Lake Seminary basins seq 1Drainage calculations·12 Dec 2007·p.2
  • Cross drain culvertsEleven extended cross drains modeled in CulvertMaster: 36" RCP, 24" RCP (x3), 84" RCP, 98"x63" RCP, 36" RCP, 18" RCP (x3), and 6.25'x3.5' box; each analyzed for 25-year headwater impact seq 1Drainage calculations·12 Dec 2007·p.2
  • CulvertSta 40241+20 cross drain: single 36-inch circular RCP, length 45.10 ft, upstream invert 15.35 ft, downstream invert 15.20 ft, slope 0.003326 ft/ft seq 1Drainage calculations·12 Dec 2007·p.3
  • Conveyance ditchLeft-side and right-side conveyance ditches/swales along the railroad with tabulated flowline elevations and slopes; segments labeled Existing Ditch, Typical Ditch, Special Ditch, and Special Ditch/Cross Drain (daylighting points) seq 1Drainage calculations·12 Dec 2007·p.2
  • Rail bridgeSt. Johns River rail bridge (RS 80 in the HEC-RAS model) with new prestressed concrete double box beams on new pier caps; Pier types A and B supported by piles; existing timber piles cut to stream bed level after new construction; M.P. 763.1 seq 1Drainage calculations·12 Dec 2007·p.2
  • Existing bridgeExisting U.S. 17-92 bridge modeled at RS 98; no changes proposed to the 17-92 bridge seq 1Drainage calculations·12 Dec 2007·p.7
  • DitchOther surface waters (OSW 3, 5, 5A, 7, 10, 13, 17, 19A, 32, 49, 56) - drainage ditches within the railroad right-of-way, FLUCFCS 510, totaling 1.369 acres of temporary impact seq 1Drainage calculations·12 Dec 2007·p.9
  • Surface water management systemSurface water management system constructed for the 203.66-acre Central Florida Commuter Rail Transit - Phase 1 project seq 1Permit·20 Oct 2008·p.3
  • Discharge structuresAs-built certification requires verifying dimensions and elevations of all discharge structures including weirs, slots, gates, pumps, pipes, and oil and grease skimmers seq 1Permit·20 Oct 2008·p.5
  • Rail side ditchesRail-side ditches (wetlands/other surface waters) in which 7.44 acres of work is authorized seq 1Permit·20 Oct 2008·p.3
  • Retention detention storageAll retention and detention storage areas must be excavated to rough grade prior to building construction; accumulated sediment removed prior to final grading seq 1Permit·20 Oct 2008·p.6
  • SwalesSwales and swales with blocks to retain and infiltrate the 1-inch treatment volume; compensating treatment of existing-track runoff where right-of-way is lacking seq 1Technical Staff Report·20 Oct 2008·p.4
  • BridgeReplacement of the northern 114 feet of the existing 565-foot long wooden trestle bridge over the St. Johns River with a concrete trestle bridge (single-track configuration) seq 1Technical Staff Report·20 Oct 2008·p.2
  • Drainage ditchesOther surface waters consisting of drainage ditches constructed in uplands and through wetlands during construction/maintenance of the existing railroad; 33 other surface waters present seq 1Technical Staff Report·20 Oct 2008·p.2
Carli Professional Office Building 123954-19 governing-sequence
Lake Mary Pediatric Medical Office 141317-112 governing-sequence
South Country Club Drainage Improvements 214983-12 governing-sequence
Lake Mary Boulevard , Phase II: pedestrian overpass (Ltr Mod) 21945-190 governing-sequence · 17 file history
Lineage: every attributable document here is from seq 1 (documents dated 2007–2008) — none from governing seq 19 (“Lake Mary Boulevard , Phase II: pedestrian overpass (Ltr Mod)”, 2005). Entries below are file history, not the governing record.
  • Retention detention pondFive retention/detention ponds receiving conveyed runoff seq 1Permit·p.3
  • Retention detention ditch swaleTwo retention/detention ditch swales seq 1Permit·p.3
  • Roadside swales and culvertsSheet flow to sodded roadside swales and culverts that convey runoff to the ponds seq 1Permit·p.3
  • Retention pond existingExisting shallow retention pond in the study area, seasonally dry, less than 0.5 acres (noted as the only other 'wetland' feature) seq 1Drainage calculations·17 Sep 2007·p.7
  • Retention detention pondFive retention/detention ponds and two retention/detention ditch swales; system divided into seven sections along the extension seq 1Technical Staff Report·p.2
  • Outfall structureAll retention/detention basins equipped with outfall structures and skimmers seq 1Technical Staff Report·p.2
  • Roadside swales and culvertsSheet flow to sodded roadside swales with (equalizer) culverts conveying runoff to the basins seq 1Technical Staff Report·p.2
  • Pond storagePonds provide storage to elevation 51.0 ft; 100-yr (24-hr) design stage 50.0 ft seq 1Technical Staff Report·p.8
  • Retention detention pondBasin 3: one-acre retention/detention pond constructed on the TASHJIAH parcel upstream of designated wetlands (2.3+ acres usable), serving 44.55-acre Basin 3 seq 1As-built·17 Sep 2007·p.25
  • Retention detention pondBasin 4: retention/detention pond at the southeast corner of Lake Mary Blvd and Longwood/Lake Mary Rd; pond discharge is via a pipe to the Basin 3 stormwater system seq 1As-built·17 Sep 2007·p.25
  • PondBasin 5: two existing ponds (2.4 acres) with no existing positive outfall; shorelines reshaped and material excavated to maintain overall storage capacity after roadway widening seq 1As-built·17 Sep 2007·p.25
  • Outfall pipeBasin 5 safety-feature outfall pipe to the east connecting to an existing storm drain into Big Lake Mary seq 1As-built·17 Sep 2007·p.25
  • Outfall culvertOutfall culvert from Lake Mary Boulevard to proposed WRA No. 3 (revised storm sewer tabulation sheet 8 of 11) seq 1As-built·17 Sep 2007·p.23
  • Water retention areaWRA No. 3 relocated and a muck blanket added for WRA No. 5 per 1988 permit modification submittal to SJRWMD seq 1As-built·17 Sep 2007·p.23
  • Outfall pipe54-inch RCP conveying peak storm flow through a pond control structure (handwritten Mizo, Hill & Glass calc sheet; page is a poor scan and surrounding values are not reliably legible) seq 1As-built·17 Sep 2007·p.81
  • Side drain filterSide-drain filter (underdrain) analyzed for drawdown using Darcy's law on a handwritten Mizo, Hill & Glass calc sheet dated 2-1-88; weir and stage values on the sheet are not reliably legible in the scan seq 1As-built·17 Sep 2007·p.88
  • Pond section detailHandwritten pond/WRA section sketch showing an apparent top elevation of 44.30 (OCR of handwriting reads "yoP=44.30", likely "TOP=44.30"; poor scan, value unverified) seq 1As-built·17 Sep 2007·p.80
Woodbridge Lk Phase 2C 22463-20 governing-sequence · 22 file history
Lineage: every attributable document here is from seq 1 (documents dated 2007–2008) — none from governing seq 2 (“Woodbridge Lk Phase 2C”, 1999). Entries below are file history, not the governing record.
  • Pond systemSeven dry-bottom ponds and one wet detention pond (Tract II) comprising the Woodbridge stormwater management system seq 1Drainage calculations·20 Mar 2007·p.106
  • Control structureDitch bottom control structures within the ponds, discharging to the on-site water bodies and Lake Dawson seq 1Drainage calculations·20 Mar 2007·p.106
  • Outfall structureTract II discharge structure to Lake Dawson (adICPR reach TRACTH to DAWSON): drop structure with one 15-in circular culvert, 160 ft long, D/S invert 40.0, with rectangular riser slots including weir crest EL 45.500 (crest length 10 ft) and a 2-in x 2-in slot at EL 41.000 (page is a degraded scan; values from adICPR input text layer) seq 1Drainage calculations·20 Mar 2007·p.23
  • Treatment pondRinehart Road Pond 3 on the purchased 3.40-acre Woodbridge commercial lot used as a water quality treatment pond; overflow discharges to Lake 1 in Woodbridge (text layer OCR reads Woodbndge) seq 1Drainage calculations·20 Mar 2007·p.3
  • Control structurePond 3 control structure set slightly above the treatment volume stage; treatment recovery via natural percolation seq 1Drainage calculations·20 Mar 2007·p.5
  • Detention pondStorage unit detention pond with control structure set at elevation 46.0 ft; a portion of Strang basin also discharges into this pond seq 1Drainage calculations·20 Mar 2007·p.5
  • Offsite overflowOffwest offsite basin discharges to Lake 1 when it stages to elevation 49.0 ft seq 1Drainage calculations·20 Mar 2007·p.5
  • Underdrain systemRetention Tract A2 underdrain system: 6-in drains, treatment volume 37,026 cf, 3-day recovery design (Universal Engineering PONDS v2.24 calcs) seq 1Drainage calculations·20 Mar 2007·p.219
  • Broad crested weirRinehart Road embankment functions as a broad-crested weir for offsite area west of the road staging to the lake seq 1Drainage calculations·20 Mar 2007·p.3
  • Retention pondsPer geotechnical report: 7 retention tracts including 10 retention ponds and 3 swales along the existing on-site lakes (text layer OCR reads swates) seq 1Drainage calculations·20 Mar 2007·p.147
  • Bypass inletProposed stormwater bypass system: type C inlet within Lake 1 with control elevation 46.0, discharging Lake 1 to Lake 3 (Rinehart Road widening coordination) seq 1As-built·20 Mar 2007·p.104
  • Retention pondRinehart Road widening retention pond adjacent to the Woodbridge Lakes Subdivision, ultimately outfalling to the Woodbridge Lakes stormwater management system seq 1As-built·20 Mar 2007·p.100
  • LakesFour major lakes: three isolated lakes (Lakes 1-3) and Lake Dawson, which contain the stormwater runoff per City of Lake Mary and SJRWMD criteria seq 1As-built·20 Mar 2007·p.100
  • Pond outfall pipePhase 2 pond outfall pipe relocated by field modification (easement area D) to avoid a stand of old oak trees; pipe easement moved over one lot seq 1As-built·20 Mar 2007·p.89
  • Dry retention pondSeven dry retention ponds serving the subdivision seq 1Permit·p.3
  • Detention pondOne dry detention pond, one wet detention pond, and three on-site lakes (text layer OCR reads LAMES for LAKES) seq 1Permit·p.3
  • Exfiltration systemExfiltration system required to be constructed per permitted plans under P.E. observation (Condition 17) seq 1Permit·p.6
  • Dry retention pondSeven dry-bottom retention ponds seq 1Technical Staff Report·p.4
  • Dry detention pondOne dry-detention pond with underdrain seq 1Technical Staff Report·p.4
  • Control structureDischarge controlled by structures within the ponds, discharging to on-site water bodies and Lake Dawson seq 1Technical Staff Report·p.4
  • Wet detention pondWet-detention pond discharging to Lake Dawson seq 1Technical Staff Report·p.5
  • On site lakesThree on-site lakes through which post-development runoff is routed after treatment in the eight dry-bottom ponds or wet-detention pond seq 1Technical Staff Report·p.5
Crystal Lake Condos 237414-19 governing-sequence
  • Underground stormwater chamber systemUnderground stormwater chamber (exfiltration) system in the south half of the property; receives impervious runoff via two pipe connections on the east and west and discharges southeast via a control structure. Stage-storage tabulated on the post-development basin map. Drainage calculations·12 Jun 2025·p.14
  • Chamber storageStormwater chamber stage-storage: cumulative storage 0.563 Ac-Ft at elevation 55.10 ft (top of stage-storage table). Drainage calculations·12 Jun 2025·p.14
  • Chamber bottom stageICPR node Chambers-1 initial (bottom) stage 51.600 ft; warning stage 54.600 ft. Drainage calculations·12 Jun 2025·p.15
  • Control structure weirWeir CS from node Chambers-1 to Post-E: vertical rectangular weir, span 48.00 in, rise 9.48 in, invert 54.400 ft, weir discharge coef 3.200, orifice discharge coef 0.600. Drainage calculations·12 Jun 2025·p.17
  • Control structure weir opening riseRectangular weir opening rise of 9.48 in on control structure CS. Drainage calculations·12 Jun 2025·p.17
  • Exfiltration (percolation) linkICPR percolation link PERC from Chambers-1 to groundwater node GW: horizontal conductivity 19.500 ft/day, vertical conductivity 13.000 ft/day, water table elevation 50.000 ft, aquifer base elevation 49.500 ft, effective porosity 0.250. Drainage calculations·12 Jun 2025·p.17
  • Dry-bottom retention pond (2022 concept)Stormwater to be collected and treated on site via a dry-bottom retention pond proposed along the west side of the site (2022 concept plan; the permitted 2024-2025 design ultimately used an underground chamber system). Drainage calculations·12 Jun 2025·p.13
  • Underground exfiltration vaultStormwater management system consists of an underground exfiltration vault and associated drainage infrastructure providing treatment and attenuation of development runoff. Technical Staff Report·29 Dec 2025·p.2
  • OutfallSystem discharges east to existing stormwater infrastructure with ultimate receiving waters of Crystal Lake. Technical Staff Report·29 Dec 2025·p.2
Rainbow Child Care Center 49830-30 governing-sequence · 11 file history
Lineage: every attributable document here is from seq 1 (“ZANCA OFFICE SITE”, 1998) — none from governing seq 3 (“Rainbow Child Care Center”, 2018). Entries below are file history, not the governing record.
  • Wet detention pondWet detention pond: empty (bottom) EL 49.00 ft, full (top of bank) EL 53.00 ft, full volume 1.290 ac-ft; stage-storage 0.290 ac-ft @ EL 50.00, 0.600 @ EL 51.00, 0.930 @ EL 52.00. seq 1Drainage calculations·30 Jan 2006·p.19
  • Control elevationPond control / water-quality elevation 49.66 ft (0.19 ac-ft W.Q. volume between control elevation and EL 50.00; stage-storage table dated 2/25/98). seq 1Drainage calculations·30 Jan 2006·p.13
  • Outfall weirRectangular overflow weir in outfall structure: crest EL 52.00 ft, length 3.083 ft, width 2.000 ft, weir C 3.2 (Path 001, POND to OUTFALL STRUCTURE). seq 1Drainage calculations·30 Jan 2006·p.22
  • Bleed down orificeWater-quality bleed-down orifice sized 1.17 inches diameter (invert EL 49.00 ft) to recover one-half the treatment volume in 48 hours per Sec. 29.0 of SJRWMD Handbook; modeled as 0.096 ft circular vertical gate at crest EL 49.00. seq 1Drainage calculations·30 Jan 2006·p.14
  • Outfall pipeOutfall pipe from outfall structure to existing inlet S-81: 751.0 ft long, 1.250 ft (15-in) rise and span, inlet/outlet inverts EL 49.00 ft, Manning n = 0.012. seq 1Drainage calculations·30 Jan 2006·p.23
  • Discharge pointSystem discharges from the outfall structure to existing inlet S-81 of the Lake Mary Blvd storm system. seq 1Drainage calculations·30 Jan 2006·p.23
  • Storm collection systemOn-site collection per site plan: Type C inlets (grate EL 52.00 and 53.00) and Type P7 storm manholes (inv EL 49.00) connected by 15-in RCP. seq 1Drainage calculations·30 Jan 2006·p.72
  • Wet detention pondWet detention checked as type of treatment for the new stormwater system. seq 1Technical Staff Report·p.2
  • SwalesSwales checked as type of treatment for the new stormwater system. seq 1Technical Staff Report·p.2
  • Stormwater systemNew stormwater system with stormwater treatment by wet detention, authorized for construction and operation. seq 1Permit·p.2
  • SwalesSwales are part of the authorized stormwater treatment train serving the Zanca Office Site. seq 1Permit·p.2
JR Academy of Lake Mary 69432-111 governing-sequence
  • Dry retention pondOne shallow dry retention pond in the eastern portion of the site; soil boring B-3 performed at the pond area Drainage calculations·22 Sep 2006·p.13
  • Dry retention pondPond stage-storage: elev 58 = 1,752 sq ft; elev 59 = 2,482 sq ft (cum 0.0486 ac-ft); elev 60 = 3,338 sq ft (cum 0.115 ac-ft); elev 61 = 4,319 sq ft (cum 0.203 ac-ft) Drainage calculations·22 Sep 2006·p.38
  • Dry retention pondICPR pond node stage-area rating: 58.000 ft = 0.040 ac, 59.000 ft = 0.057 ac, 60.000 ft = 0.077 ac, 61.000 ft = 0.099 ac; initial stage 58.000 ft Drainage calculations·22 Sep 2006·p.40
  • Control structure orificeSingle circular weir/gate/orifice control structure (reach OUT) from pond to outfall, invert elevation 59.610 ft, span 3.000 in by rise 3.000 in, weir coef 3.000, gate coef 0.600, 1 element Drainage calculations·22 Sep 2006·p.42
  • Control structure orificeOrifice invert elevation and size as modeled Drainage calculations·22 Sep 2006·p.42
  • OutfallOutfall node modeled as a time-stage boundary, initial stage 53.860 ft, rising to a maximum of 56.50 ft at 12.00 hr Drainage calculations·22 Sep 2006·p.41
  • Storm sewer conveyancePreschool building and associated infrastructure (parking and conveyance) draining to the pond; no pipe sizes given in this report Drainage calculations·22 Sep 2006·p.38
  • Retention systemNew stormwater system providing stormwater treatment by retention; permit gives no pond count, geometry or elevations Permit·p.2
  • Retention and detention storageRetention and detention storage referenced as part of the permitted system; must be excavated to rough grade before offsite discharge. No dimensions or elevations stated in the permit. Permit·p.4
  • Dry retention pondOne dry retention pond serving the site; no geometry or elevations given in the TSR Technical Staff Report·26 Jan 2001·p.1
  • Storm sewer conveyance systemStorm sewer conveyance system serving a 6,118 square foot preschool building and parking area Technical Staff Report·26 Jan 2001·p.1
Regency Pointe Commercial/Professional Center 71294-110 governing-sequence
  • Retention systemNew stormwater management system with stormwater treatment by retention serving the 3.90-acre Regency Pointe site, per plans received by the District July 31, 2001. Permit·p.2
  • Dry retention pondDry retention pond, 0.98 acres (25.13% of the 3.90-acre site), providing water quality treatment and peak attenuation; stage/storage tabulated from 48.50 to 55.00 ft-msl. Drainage calculations·22 Sep 2006·p.91
  • Pond bottomPond bottom elevation 47.50 ft (PONDS recovery analysis input); equivalent pond dimensions 81.00 ft x 75.00 ft. Drainage calculations·22 Sep 2006·p.158
  • WeirRectangular weir in drop structure DROP: 12 in span x 4 in rise, invert/control elevation 52.75 ft, weir discharge coefficient 3.2, orifice discharge coefficient 0.6; required weir elevation computed as 51.17 (51.20 ft-msl at 0.409 ac-ft) but set at 52.75 ft-msl for constructability. Drainage calculations·22 Sep 2006·p.122
  • Control structureDrop structure DROP from node POND to node OUTFALL (count 1); control structure equipped with a skimming device to prevent floating oils and debris from leaving the site. Drainage calculations·22 Sep 2006·p.86
  • Outfall culvertCircular outfall culvert on drop structure DROP from POND to OUTFALL: 15 in span/rise, 63 ft long, upstream invert 51.0 ft, downstream invert 48.5 ft, circular concrete with square edge headwall. Drainage calculations·22 Sep 2006·p.121
  • OutfallPond discharges into an existing curb inlet on Lake Mary Boulevard at the northeast corner of the site; final destination of site runoff is Big Lake Mary, less than 1/2 mile east. Drainage calculations·22 Sep 2006·p.86
  • Retention systemNew stormwater management system with stormwater treatment by retention serving the 3.90-acre Regency Pointe project (permit copy transmitted within this compliance submittal). As-built·22 Sep 2006·p.4
  • Storm sewerStorm sewers serving the commercial/professional office center and parking facilities. Technical Staff Report·17 Sep 2001·p.1
  • Stormwater treatment systemNew stormwater system with treatment by retention serving the 3.90-acre project. Technical Staff Report·17 Sep 2001·p.2
Cold Mix Paving of City's dirt streets - all phases 76767-30 governing-sequence · 2 file history
Lineage: every attributable document here is from seq 1 (documents dated 2006) — none from governing seq 3 (“Cold Mix Paving of City's dirt streets - all phases”, 2006). Entries below are file history, not the governing record.
  • Swales with ditch blocksSwales with ditch blocks used as Best Management Practices treatment for the 26.62-acre street pavement project; a modification to an existing stormwater system seq 1Permit·p.2
  • Swales with ditch blocksSwales with ditch blocks checked as the type of treatment (8) for the 26.62-acre roadway project; type of system is a modification to an existing system (4) seq 1Technical Staff Report·p.2
City of Lake Mary Police Station Retention Pond 76781-30 governing-sequence · 8 file history
Lineage: every attributable document here is from seq 1 (“NEW POLICE STATION”, 1999) — none from governing seq 3 (“City of Lake Mary Police Station Retention Pond”, 2013). Entries below are file history, not the governing record.
  • Dry retention pondPond A, dry retention pond in the southern portion of the site receiving all site runoff; bottom elevation 56.0 ft, top elevation 60.0 ft; oversized for build-out impervious area of 1.69 ac seq 1Drainage calculations·27 Dec 2007·p.4
  • Pond stage-storagePond A stage-storage: at top elevation 60 ft, surface area 25,640 sf (0.589 ac) and cumulative storage 73,477 cf (1.687 ac-ft) seq 1Drainage calculations·27 Dec 2007·p.29
  • Drop structure / outfall pipeDrop structure DROPA from node PONDA to LVINLET: 24-in circular concrete pipe, 50 ft long, upstream invert 52.41 ft, downstream invert 52.8 ft, Manning's n 0.013 seq 1Drainage calculations·27 Dec 2007·p.25
  • WeirWeir 1 of 2 in drop structure DROPA: horizontal rectangular weir, 36-in span x 28-in rise, invert and control elevation 59.0 ft (weir discharge coef 3.2) seq 1Drainage calculations·27 Dec 2007·p.25
  • WeirWeir 2 of 2 in drop structure DROPA: rectangular weir, 36-in span x 9-in rise, invert and control elevation 58.25 ft seq 1Drainage calculations·27 Dec 2007·p.25
  • Outfall swaleExisting swale along the railroad tracks' right-of-way at the southern site corner; right-of-way has positive outfall to Lake Mary, then a stream, Lake Jessup, St. Johns River seq 1Drainage calculations·27 Dec 2007·p.4
  • Retention systemNew stormwater system with stormwater treatment by retention serving the City of Lake Mary New Police Station, per plans received by the District on April 21, 1999 seq 1Permit·p.2
  • SwaleDry roadside swale system serving the new police station site (per TSR comments; treatment type box checked on the form is Retention) seq 1Technical Staff Report·p.2
Medlin Professional Office 85947-111 governing-sequence
  • Dry retention pondOne new dry-retention pond serving the new building and parking area; the permit document states no pond dimensions, elevations, or volumes Permit·p.2
  • Dry retention pondNew Medlin pond (proposed), stage-area table: bottom elevation 48 ft MSL at 4,187 sq ft rising to 6,801 sq ft at elevation 51; accumulated effective volume 13,794 cu ft at elevation 50.61 and 16,442 cu ft at elevation 51 Drainage calculations·9 Feb 2007·p.14
  • Retention pond geometryPONDS model geometry for the expanded on-line detention pond: equivalent pond length 109.9 ft, equivalent width 48.1 ft; stage-area 48.00 ft = 4,187 sq ft, 50.61 ft = 6,431 sq ft, 51.00 ft = 6,801 sq ft Drainage calculations·9 Feb 2007·p.18
  • Outfall8-inch CLDIP outfall, centerline elevation 50.61 ft datum, modeled as a rating curve: 0 cfs at stage 50.28, 0.3 cfs at 50.37, 0.6 cfs at 50.91, 0.8 cfs at 51.50, up to 1.6 cfs at 55.45 Drainage calculations·9 Feb 2007·p.19
  • Control structurePond control structure at the west side of the new pond, fed by 82 LF of 8-inch CLDIP with (2) 45-degree ells, invert elevation 50.17 Drainage calculations·9 Feb 2007·p.15
  • Curb inletNew Type C inlet, top elevation 51.25 with 12-inch RCP invert about 49; a second new Type C inlet at top 50.83 with 8-inch CLDIP invert 49.47 Drainage calculations·9 Feb 2007·p.15
  • Grated inletNew Type C inlet with iron grate and chain, 12 in by 18 in HERCP, invert 49.59 Drainage calculations·9 Feb 2007·p.15
  • Culvert92 LF of 15-inch HDPE storm pipe on the east side of the site; storm invert 48.34 Drainage calculations·9 Feb 2007·p.15
  • EndwallFDOT Index 261 U-type concrete endwall for 4:1 slope on the 15-inch pipe, invert elevation 48.00, discharging into the new pond Drainage calculations·9 Feb 2007·p.15
  • WeirPre-development condition only: broad crested earthen weir, crest elevation 50.90 ft datum, 4 ft long, weir coefficient 2.86, free discharge Drainage calculations·9 Feb 2007·p.7
  • Dry retention pondOne new dry-retention pond providing retention treatment for the 1.010-acre commercial redevelopment; the TSR gives no pond dimensions, elevations, or volumes Technical Staff Report·29 Oct 2002·p.2
Seminole Ave Pond Expansion 86365-100 governing-sequence · 5 file history
Lineage: every attributable document here is from seq 1 (documents dated 2002–2008) — none from governing seq 10 (“Seminole Ave Pond Expansion”, 2020). Entries below are file history, not the governing record.
  • Dry retention pondDry-retention pond serving the new office building and parking area of the 0.62-acre Shaw Construction project (no dimensions stated in permit document) seq 1Permit·p.2
  • Dry retention pondRetention pond modeled with equivalent pond length 96.0 ft and equivalent width 70.0 ft; groundwater mound expected to intersect pond bottom (water table el. 49.60 ft) seq 1Drainage calculations·7 Jan 2008·p.6
  • Pond stage-areaStage vs. area data: 362.0 sf at stage 52.00 ft (bottom) rising to 4,877.0 sf at stage 56.00 ft (top) seq 1Drainage calculations·7 Jan 2008·p.6
  • Drainage basinContributing basin of 0.752 acres, 82.0% DCIA, SCS curve number 89, time of concentration 10.0 minutes, SCS Type II Florida Modified distribution seq 1Drainage calculations·7 Jan 2008·p.7
  • Dry retention pondDry-retention pond designed to retain the entire post-development runoff volume from the 100-year/24-hour storm event; serves new office building and parking area seq 1Technical Staff Report·26 Nov 2002·p.2
GTE Federal Credit Union-Lake Mary 87951-13 governing-sequence
  • Stormwater management system (retention)Stormwater management system with treatment by retention serving the 2.63-acre GTE Federal Credit Union-Lake Mary project Permit·p.2
  • Dry retention pondDry retention pond on the northern portion of the site providing retention treatment for the 3,200 sf bank and parking areas Technical Staff Report·16 May 2003·p.2
  • Outfall / discharge pointSystem discharges to the existing roadway drainage system, matching the pre-development discharge route Technical Staff Report·16 May 2003·p.2
Cambridge Prep School - Lake Mary Blvd. 98061-113 governing-sequence
Watson Center at Lake Mary 98533-119 governing-sequence
Ruskin St, Johnson Ave, & S 4th St Paving & Drainage Improvements 98636-17 governing-sequence
  • Swale with ditch bottom inletsRoadside swales with ditch bottom inlets added along the paved roads to alleviate existing flooding; inlets set slightly above the swale bottom to retain runoff and promote infiltration Drainage calculations·25 Apr 2005·p.52
  • Storm sewer outfallProposed collection system outfalls into an existing storm sewer Drainage calculations·25 Apr 2005·p.52
  • Dry retention pondExisting dry retention pond along South 4th Street receiving the storm sewer discharge, with eventual discharge to a wetland contributory of Soldier's Creek Drainage calculations·25 Apr 2005·p.52
  • Storm sewer pipeProposed 18-inch RCP storm sewer reaches (R-2 through R-7) with locked flow-line elevations between 48.160 and 49.500 ft, per ASAD storm sewer reach details Drainage calculations·25 Apr 2005·p.46
  • Swales with ditch blocksPermitted stormwater treatment system: swales with ditch blocks serving the Ruskin St, Johnson Ave, and S 4th St roadway improvements Permit·19 May 2005·p.1
  • Swales with ditch blocksSwales with ditch blocks providing stormwater treatment for the roadway project Technical Staff Report·19 May 2005·p.1
  • Ditch bottom inletDitch bottom inlets set above the swale grades serving as blocks to retain runoff and promote infiltration into the soils Technical Staff Report·19 May 2005·p.2

1 failed page verification — quarantined in Part 09.

Part 07

Permit summaries

CNBS - Lake Mary 103055-1

ApplicantCNBS Properties LLC
Rule typeERP Stormwater Standard General (40C)
Decided2006-03-23
Expires2011-03-23 · construction term (see Method)
Receiving waterCrystal Lake,Lake Jesup
Documents28
File lineage28 docs: 24 from this sequence, 4 unstated

Environmental Resource Permit submittal package (drainage calculations, December 12, 2005) for a new +/-8,700 sf two-story bank/office facility with parking on a +/-0.93-acre commercial parcel at Lake Mary Blvd and S Fifth Street in Lake Mary, Seminole County; stormwater is handled by an on-site dry retention system, with site runoff historically flowing northeast through a small retention area into Crystal Lake. Drainage calculations·5 Sep 2008·p.4

Environmental Resource Permit submittal package (December 12, 2005, CPH Project C11602) for a new +/-8,700 sf two-story bank/office facility with parking on a +/-0.93-acre commercial parcel in Lake Mary, Seminole County; the entire site is served by an on-site dry retention stormwater system, with runoff historically flowing northeast through a small retention area into Crystal Lake. Drainage calculations·28 Dec 2005·p.3

SJRWMD stormwater permit 42-117-103055-1 (issued March 23, 2006 under Chapter 40C-42, F.A.C.) authorizing construction of a stormwater management system with treatment by retention for CNBS - Lake Mary, a 0.93-acre commercial project in Section 16, Township 20S, Range 30E, Seminole County. Permit·23 Mar 2006·p.1

Technical Staff Report (March 21, 2006) for standard general ERP stormwater permit application 42-117-103055-1, CNBS - Lake Mary: a two-story bank building with associated parking on a 0.9-acre commercial site (49.4% impervious excluding the pond), served by an online dry retention stormwater management system; receiving water body is Crystal Lake / Lake Jesup (Class III Fresh). Technical Staff Report·23 Mar 2006·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Washington Estates 108660-2

ApplicantWashington Estates Property Owners Association, Inc.
Rule typeERP Stormwater Standard General (40C)
Decided2014-03-28
Expires2112-03-27
Receiving waterSoldier Creek
Documents40
File lineage40 docs: 32 from seq 1 (2006–2008), 8 unstated

seq 1 Applicant's Section H (Information for Environmental Resource Stormwater Permits) summary for a retention-based stormwater treatment system stated to meet Subsection 40C-42.026(2) F.A.C.; the project is in the Soldier Creek Basin (not the Wekiva River Basin) and the treatment volume is retained in the proposed pond. Drainage calculations·21 Feb 2007·p.1

seq 1 Storm Drainage Report for Washington Estates, a five-lot residential subdivision (~3.14 ac) at 230 Washington Avenue, Lake Mary, FL, in the Soldiers Creek Drainage Basin; stormwater is collected by inlet structures and pipes and treated in an online dry retention pond discharging toward Washington Avenue right-of-way. Drainage calculations·21 Feb 2007·p.3

seq 1 SJRWMD stormwater permit 42-117-108660-1 (issued March 27, 2007) authorizing construction of a stormwater management system with stormwater treatment by retention for Washington Estates, a 3.15-acre residential project in Seminole County. Permit·27 Mar 2007·p.1

seq 1 Technical Staff Report for a standard general ERP stormwater permit for Washington Estates, a 3.145-acre, 5-lot single-family residential subdivision with an access road (0.75 ac impervious) in Lake Mary; treatment by dry retention, with the pond overflowing west to Soldier Creek (Class III Fresh), which ultimately discharges to Lake Jesup. Technical Staff Report·27 Mar 2007·p.2

Storm Drainage Report (duplicate copy of the August 22, 2006 Rockett & Associates report) for Washington Estates, a five-lot residential subdivision (~3.14 ac) at 230 Washington Avenue, Lake Mary, FL, in the Soldiers Creek Drainage Basin, with an online dry retention pond treating runoff collected by inlet structures and pipes. Drainage calculations·21 Nov 2006·p.3

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

CR 15 from Ranoul Lane to CR 46A 110309-1

ApplicantDepartment of Public Works Engineering Division
Rule typeERP Stormwater Standard General (40C)
Decided2007-08-07
Expires2012-08-07 · construction term (see Method)
Receiving waterCrystal Lake
Documents37
File lineage37 docs: 31 from this sequence, 6 unstated

Roadway and drainage improvement project on Country Club Road (CR 15) from Rantoul Lane to CR 46A in Seminole County, FL (approx. 7.46-acre corridor), consisting of curb and gutter replacement/installation, milling and resurfacing, new roadside storage swales for treatment, and sidewalk construction; runoff is conveyed by ditches and swales to a stormwater management pond adjacent to CR 46A and, at the south end, to Crystal Lake. Drainage calculations·15 Mar 2007·p.31

SJRWMD stormwater permit no. 42-117-110309-1 (Chapter 40C-42, F.A.C.), issued August 7, 2007, authorizing construction of a stormwater management system with treatment by best management practices for CR 15 from Rantoul Lane to CR 46A, a 7.46-acre roadway project of Seminole County Engineering Division. Permit·7 Aug 2007·p.1

Technical Staff Report for SJRWMD application 42-117-110309-1: roadway and drainage improvements along Country Club Road (CR 15) between Rantoul Lane and CR 46A in Seminole County (7.46 acres), with stormwater treatment by best management practices including a baffle box; receiving water body is Crystal Lake (Class III Fresh). Technical Staff Report·7 Aug 2007·p.2

Re-scanned bound report of the SJRWMD ERP application for the Country Club Road (CR 15) roadway and drainage improvement project from Rantoul Lane to CR 46A, Seminole County, FL (7.46-acre corridor): curb and gutter replacement/installation, milling and resurfacing, roadside treatment/storage swales, and sidewalk; runoff conveyed via ditches and swales to a stormwater management pond adjacent to CR 46A and, at the south end, to Crystal Lake. Drainage calculations·26 Apr 2010·p.34

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Central Florida Commuter Rail - Lake Mary Station 114454-14

ApplicantFlorida Department of Transportation - District 5
Rule typeERP Standard General (40C)
Decided2013-12-17
Expires2015-12-17 · construction term (see Method)
Receiving waterLake Mary
Documents188
File lineage188 docs: 170 from seq 1 (2007–2008), 18 unstated

seq 1 Individual ERP and State Lands TSR (Oct 10, 2008) recommending approval of a surface water management system for the Central Florida Commuter Rail Transit - Phase 1, a 203.66-acre, 31.77-mile rail corridor project (FDOT District 5) discharging to multiple receiving waters including Lake Mary, Lake Monroe, Soldier Creek, and the St. Johns River (OFW). Technical Staff Report·14 Oct 2008·p.7

seq 1 Stormwater management report (VHB) supporting the Individual ERP for the Central Florida Commuter Rail Transit (CFCRT) project - addition of a second track for approximately 20.8 miles (203.66 acres of double tracking) from Ft. Florida Rd. (Volusia County) to Sand Lake Rd. (Orange County); stormwater runoff from the railroad embankment flows to open swales parallel to the railroad, discharging to multiple basins/outfalls. Drainage calculations·12 Dec 2007·p.5

seq 1 Appendix B (Curve Number Calculations) of the CFCRT stormwater report - pre- and post-development runoff curve numbers and 25-year storm runoff volumes by basin for the Commuter Rail double-track project (VHB Project 9220.01, FDOT Project 412994-1-22-01), with swale volumes provided to accommodate the runoff increase. Drainage calculations·12 Dec 2007·p.2

seq 1 Appendix C (Floodplain Calculations) of the CFCRT stormwater report - summary of areas with floodplain, floodplain encroachment and compensation calculations, floodplain maps, and cross-section encroachment for the Commuter Rail double-track project in Volusia, Seminole, and Orange Counties. Drainage calculations·12 Dec 2007·p.2

seq 1 Appendix D (Cross Drain Extension Calculations) of the CFCRT stormwater report - CulvertMaster analyses of the eleven cross drains extended in the double-tracking areas, comparing pre- and post-development headwater elevations against maximum allowable headwater for the Commuter Rail project in Seminole/Orange Counties. Drainage calculations·12 Dec 2007·p.2

seq 1 Appendix E (Conveyance Ditch Profile) of the CFCRT stormwater report - flowline elevations and slopes of the conveyance swales/ditches (left and right side of the track) added along the railroad embankment for the Commuter Rail project in Seminole/Orange Counties. Drainage calculations·12 Dec 2007·p.2

seq 1 Appendix F (St. John's River Rail Bridge Hydraulic Analysis) of the CFCRT stormwater report - preliminary bridge structural sheets plus proposed/existing HEC-RAS and existing WSPRO model computations comparing water surface elevations for the 10-, 50-, 100-, and 500-year floods at the rail bridge (M.P. 763.1) and the U.S. 17-92 bridge over the St. Johns River. Drainage calculations·12 Dec 2007·p.7

seq 1 UMAM (Uniform Mitigation Assessment Method) wetland/surface-water functional assessment for the Central Florida Commuter Rail Transit - Phase 1 project, quantifying temporary impacts to forested wetlands, herbaceous wetland, and other surface waters (ditches) along the railroad corridor draining to the St. Johns River and Soldier Creek within the Wekiva River Aquatic Preserve (OFW). Drainage calculations·12 Dec 2007·p.1

seq 1 Standard Manatee Conditions for In-Water Work (July 2005) attachment to the permit, imposing manatee-protection requirements the permittee must follow during in-water construction (e.g., St. Johns River bridge work). Permit·12 Dec 2007·p.1

seq 1 Final Individual ERP (Permit No. 4-095-114454-1, issued October 14, 2008) authorizing construction of a surface water management system for the Central Florida Commuter Rail Transit - Phase 1, a 203.66-acre project in Orange, Seminole, and Volusia Counties, including work in/over 7.44 acres of wetlands or other surface waters (rail-side ditches). Permit·20 Oct 2008·p.3

seq 1 Individual ERP and State Lands Technical Staff Report (Oct 10, 2008) for construction of a surface water management system for the Central Florida Commuter Rail Transit - Phase 1, a 203.66-acre, 31.77-mile rail corridor (Orange, Seminole, Volusia Counties) discharging to receiving waters including Lake Mary, Lake Monroe, Soldier Creek, and the St. Johns River (OFW). Technical Staff Report·20 Oct 2008·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Carli Professional Office Building 123954-1

ApplicantD & B Carli LLC
Rule typeERP Stormwater Standard General (40C)
Decided2010-06-15
Expires2015-06-15 · construction term (see Method)
Receiving waterCrystal Lake
Documents22
File lineage22 docs: 22 unstated

Drainage report for the Carli Professional Office Building, a 0.463-acre commercial site at 2680 Lake Mary Boulevard, Lake Mary, FL, designed with a dry one-pond retention system; water quantity overflow passes a control-structure weir to right-of-way piping and an open swale that eventually drains into Crystal Lake. Drainage calculations·17 Mar 2010·p.2

SJRWMD Chapter 40C-42 stormwater permit No. 42-117-123954-1 (issued June 15, 2010) authorizing construction of a stormwater management system with treatment by retention for the Carli Professional Office Building, a 0.463-acre commercial project in Seminole County. Permit·15 Jun 2010·p.1

Technical staff report for a 0.463-acre commercial redevelopment at 2680 Lake Mary Boulevard (Seminole County): demolition of two homes and construction of a 3,680 sq ft office building with parking, served by one stormwater retention pond that treats runoff before discharge to the street drainage system and ultimately Crystal Lake (Class III fresh). Technical Staff Report·9 Jun 2010·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Lake Mary Pediatric Medical Office 141317-1

ApplicantUrgent Care Developers of West Lake Mary, LLC
Rule typeERP Individual (<40 ac no WL <12 IMP)
Decided2015-04-10
Expires2020-04-10 · construction term (see Method)
Receiving waterLake Mary
Documents30
File lineage30 docs: 30 unstated

ERP application drainage calculation report for the Lake Mary Pediatric Medical Office, a 1.04-acre redevelopment constructing a medical office building, walks, and asphalt parking served by an on-site dry retention pond; the site discharges east via overland flow toward Lake Mary (Zone AE el. 43 ft NAVD 88). Drainage calculations·18 Mar 2015·p.4

SJRWMD Technical Staff Report recommending approval of a stormwater management system with treatment by dry retention for the Lake Mary Pediatric Medical Office, a 1.04-acre commercial redevelopment in Seminole County discharging toward Lake Mary (Class III Fresh). Technical Staff Report·10 Apr 2015·p.1

SJRWMD individual permit 141317-1 issued April 10, 2015 authorizing construction of a stormwater management system with stormwater treatment by retention for the Lake Mary Pediatric Medical Office, a 1.04-acre project in Seminole County. Permit·10 Apr 2015·p.3

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

City of Lake Mary Downtown Redevelopment Stormwater Park 191235-3

ApplicantCity of Lake Mary
Rule typeERP Individual
Decided2023-03-03
Expires2028-03-03
Receiving waterCrystal Lake
Documents0

The district’s index returned no documents for this permit as of the query date. It still governs; nothing to extract until the district publishes the file.

Not in the record Permit, Technical Staff Report, Drainage calculations

South Country Club Drainage Improvements 214983-1

ApplicantSeminole County - Chief Design Engineers
Rule typeERP General
Decided2024-03-07
Expires2029-03-07
Receiving waterLake Mary
Documents14
File lineage14 docs: 14 unstated

Small stormwater retrofit drainage improvement project (0.03 acres) by Seminole County: construction of 128 linear feet of 30-inch French drain within an existing stormwater swale on the west side of South Country Club Road in Lake Mary, as FEMA drainage improvements post Hurricane Ian; the receiving water body is Lake Mary (Class III Fresh). Technical Staff Report·7 Mar 2024·p.1

SJRWMD General Environmental Resource Permit 214983-1 (issued March 07, 2024) authorizing Seminole County to conduct stormwater retrofit activities for the South Country Club Drainage Improvements project, constructed per plans received by the District on February 8, 2024; the receiving water body is Lake Mary (Class III Fresh), Seminole County. Permit·7 Mar 2024·p.3

Design documents on file Permit, Technical Staff Report, Construction plans

Not in the record Drainage calculations

Lake Mary Boulevard , Phase II: pedestrian overpass (Ltr Mod) 21945-19

ApplicantSeminole County Board of County Commissioners
Rule typeMSSW Individual
Decided2005-12-30
Expires2007-12-30 · construction term (see Method)
Receiving water
Documents12
File lineage12 docs: 11 from seq 1 (2007–2008), 1 unstated

seq 1 SJRWMD permit (No. 4-117-0151G, issued April 6, 1987) authorizing construction of a stormwater management and treatment facility serving the Lake Mary Blvd extension (Station 2+00 to 90+05; SR 17-92 to SR 427) in Seminole County: sheet flow to sodded roadside swales and culverts conveying runoff to five retention/detention ponds and two retention/detention ditch swales. Permit·p.3

seq 1 Lake Mary Boulevard Alignment Preliminary Environmental Study (Breedlove, Dennis & Associates, Aug 1986 / rev. Sept 1986) inventorying the natural features of the proposed roadway corridor in Seminole County: wetlands, Outstanding Florida Waters, and threatened/endangered species. (Bound in the permit file as the environmental support document; not a drainage-calculation report.) Drainage calculations·17 Sep 2007·p.2

seq 1 Technical staff report (dated 3/18/1987) recommending APPROVAL of application 4-117-0151AG: a stormwater management and treatment facility for the Lake Mary Blvd extension (Sta 2+00 to 90+05; SR 17-92 to SR 427), Seminole County (project acreage 30.44 ac). Sheet flow to sodded roadside swales and culverts conveys runoff to five retention/detention ponds and two ditch swales (all basins equipped with outfall structures and skimmers); receiving water is a Six Mile Creek tributary, then Lake Jessup. Technical Staff Report·p.2

seq 1 Historical compliance file for the master surface water management system serving the Lake Mary Boulevard Roadway Widening (Markham Woods Road to Country Club Drive, Seminole County) under SJRWMD Permit 4-117-0151 (master permit referenced by 4-117-21945-1): roadway and adjacent-parcel runoff is treated and attenuated in basin-by-basin retention/detention ponds (water retention areas), with the Basin 5 outfall connecting to an existing storm drain into Big Lake Mary. As-built·17 Sep 2007·p.23

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Woodbridge Lk Phase 2C 22463-2

ApplicantOlympia Homes Inc
Rule typeERP Individual (40C)
Decided1999-09-07
Expires2004-09-07 · construction term (see Method)
Receiving water
Documents12
File lineage12 docs: 10 from seq 1 (2007–2008), 2 unstated

seq 1 Bound stormwater calculation reports for the Woodbridge PD surface water management system (107.79-acre single-family planned development with a limited commercial tract adjacent to Lake Dawson, City of Lake Mary): the Donald W. McIntosh Woodbridge calculations for seven dry-bottom ponds and one wet detention pond discharging through ditch bottom structures to three on-site lakes and Lake Dawson, plus Glace & Radcliffe Rinehart Road Basin 3/Pond 3 calculations whose Pond 3 discharges to the Woodbridge lake system. Drainage calculations·20 Mar 2007·p.106

seq 1 Compliance-submittal file for the Woodbridge Lakes surface water management system (SJRWMD Permits 4-117-0422 and 12-117-0131) documenting conversion to the operation phase and transfer to the Woodbridge Lakes Homeowners Association, the grant and partial release of the conservation easement, and coordination of the Rinehart Road widening stormwater bypass into the Woodbridge lake system; the subdivision includes 3 isolated lakes (Lakes 1-3) plus Lake Dawson. As-built·20 Mar 2007·p.100

seq 1 SJRWMD MSSW Individual Permit 4-117-0422, issued September 12, 1995 to Olympia Lake Mary Associates, Ltd., authorizing a surface water management system for the Woodbridge single-family subdivision and out-parcel commercial site in Seminole County, consisting of seven dry retention ponds, one dry detention pond, one wet detention pond, and three on-site lakes; the receiving waterbody is Lake Dawson. Permit·p.3

seq 1 Technical Staff Report (August 17, 1995) recommending approval of MSSW application 4-117-0422A for Woodbridge, a 107.79-acre single-family subdivision with a commercial out-parcel (~65% impervious) north of Lake Mary Boulevard and east of Rinehart Road in the City of Lake Mary, Seminole County; treatment is by seven dry-bottom retention ponds, one dry detention pond with underdrain and one wet-detention system routed through three on-site lakes, with Lake Dawson (Class III) the receiving waterbody. Technical Staff Report·p.4

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Crystal Lake Condos 237414-1

ApplicantACC Trust
Rule typeERP Individual
Decided2025-12-29
Expires2030-12-29
Receiving waterCrystal Lake
Documents41
File lineage41 docs: 41 unstated

Signed and sealed drainage report (Aug 2024) for Crystal Lake Condominiums, an 18-unit multi-family redevelopment of a 1.05-acre property off West Wilbur Avenue in Lake Mary, FL; stormwater is collected in an underground stormwater chamber (exfiltration) system that outfalls to the southeast. Drainage calculations·12 Jun 2025·p.3

Geotechnical investigation (MTE, Inc., Sept 2022) for the proposed West Wilbur Condominiums (the Crystal Lake Condos site) at West Wilbur Avenue and North Fourth Street, Lake Mary, FL - two 2-story condominium buildings with paving, with a stormwater retention pond then planned along the west side of the site. Drainage calculations·12 Jun 2025·p.2

SJRWMD acknowledgment that it received a request for certification for the Crystal Lake Condos project (permit 237414-1) at W Wilbur Ave & N 4th St, and agrees to act on the request within a reasonable period of time. Certification of completion·29 Dec 2025·p.1

SJRWMD individual ERP Technical Staff Report (12/29/2025) recommending approval of construction and operation of a stormwater management system for the 1.05-acre Crystal Lake Condos multi-family development (four condominium buildings) in Lake Mary, Seminole County, FL; an underground exfiltration vault system with ultimate receiving waters of Crystal Lake (Class III Fresh). Technical Staff Report·29 Dec 2025·p.1

SJRWMD individual ERP permit 237414-1, issued December 29, 2025, authorizing construction and operation of a stormwater management system for the 1.05-acre Crystal Lake Condos multi-family development in Seminole County, FL, per plans received November 19, 2025; receiving water body Crystal Lake (Class III Fresh). Permit·29 Dec 2025·p.3

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Lake Mary Elementary School 48694-7

ApplicantSeminole County Public Schools
Rule typeERP Individual
Decided2026-03-05
Expires2031-03-05
Receiving waterExisting Permit 21945 Pond: 'WRA #5',Lake Mary
Documents4
File lineage4 docs: 4 from seq 1 (2006–2008)

Summary pending extraction. 4 documents retrieved and indexed.

Not in the record Permit, Technical Staff Report, Drainage calculations

Rainbow Child Care Center 49830-3

ApplicantEIG14T RCCC 200 FL - Lake Mary LLC
Rule typeERP Individual (<40 ac no WL <12 IMP)
Decided2018-04-13
Expires2023-04-13 · construction term (see Method)
Receiving waterLake Mary
Documents8
File lineage8 docs: 8 from seq 1 (2006)

seq 1 Stormwater calculations (Professional Design Associates, Jan 19, 1998, revised Mar 3, 1998) for the Zanca Office Site: two 8,004 sf office buildings and vehicular use area on a 1.74-acre parcel in Lake Mary, Seminole County, served by a wet-detention pond; existing runoff flows east across the adjacent school playground to the existing retention pond serving Lake Mary Blvd. Drainage calculations·30 Jan 2006·p.3

seq 1 SJRWMD Technical Staff Report for a Chapter 40C-42 F.A.C. general stormwater permit application (42-117-1231AN-ERP) for the Zanca Office Site, a 1.74-acre commercial project with a new stormwater system treated by wet detention and swales, discharging to Lake Mary (Class III). Technical Staff Report·p.2

seq 1 SJRWMD stormwater permit 42-117-1231N-ERP (issued April 13, 1998, under Chapter 40C-42 F.A.C.) authorizing a new stormwater system with treatment by wet detention and swales to serve the Zanca Office Site, a 1.74-acre project in Seminole County (Section 16, Township 20, Range 30 East). Permit·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

JR Academy of Lake Mary 69432-1

ApplicantJR Academy of Lake Mary
Rule typeERP Stormwater Standard General (40C)
Decided2001-01-26
Expires2006-01-26 · construction term (see Method)
Receiving waterCrystal Lake
Documents7

Bound supporting report for JR Academy of Lake Mary combining a Universal Engineering Sciences geotechnical exploration (Report No. 146066, December 5, 2000) recommending retention pond design parameters, foundations and pavement, and Mellich Blenden Engineering stormwater calculations (December 20, 2000) sizing a dry retention pond for a 6,118 square foot preschool on a 0.88-acre site. Drainage calculations·22 Sep 2006·p.38

SJRWMD Stormwater Permit No. 42-117-69432-1, issued January 26, 2001 under Chapter 40C-42, F.A.C., authorizing construction and operation of a new stormwater system with stormwater treatment by retention to serve JR Academy of Lake Mary, a 0.88-acre project in Section 9, Township 20S, Range 30E, Seminole County, Florida. Permit·p.2

Technical Staff Report dated January 26, 2001 for Standard General ERP Stormwater application 42-117-69432-1, recommending a new stormwater system with treatment by retention for JR Academy of Lake Mary, a 0.88-acre governmental/institutional preschool project in Seminole County discharging to Crystal Lake. Technical Staff Report·26 Jan 2001·p.1

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Regency Pointe Commercial/Professional Center 71294-1

ApplicantDelro Properties, Inc.
Rule typeERP Stormwater Standard General (40C)
Decided2001-09-17
Expires2006-09-17 · construction term (see Method)
Receiving waterLake Jesup
Documents10

SJRWMD stormwater permit 42-117-71294-1 (issued September 17, 2001 under Chapter 40C-42 F.A.C.) authorizing a new stormwater system with treatment by retention to serve Regency Pointe Commercial/Professional Center, a 3.90-acre commercial project in Seminole County. Permit·p.2

Bound drainage calculation report for Regency Pointe, a 3.90-acre commercial/professional office center on Lake Mary Boulevard (Lake Mary, Seminole County): a dry retention pond provides water quality treatment and 25yr/24hr peak attenuation, discharging through a drop structure to an existing curb inlet on Lake Mary Boulevard, with final destination Big Lake Mary. Drainage calculations·22 Sep 2006·p.86

Compliance submittal correspondence file for permit 42-117-71294-1 (Regency Pointe Commercial/Professional Center, Seminole County): routing sheet, transmittal of the permit copy authorizing a new stormwater system with retention treatment for the 3.90-acre project, and O&M entity documents (Articles of Incorporation and Declaration of Condominium). No as-built drawings or numeric as-built data are included. As-built·22 Sep 2006·p.4

Technical Staff Report for a 3.90-acre commercial/professional office center (Regency Pointe) with storm sewers, parking facilities, and a new stormwater system using retention treatment; receiving water body is Lake Jesup (Class III Fresh) in the Lake Jessup planning unit, Seminole County. Technical Staff Report·17 Sep 2001·p.1

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Cold Mix Paving of City's dirt streets - all phases 76767-3

ApplicantCity of Lake Mary
Rule typeERP Stormwater Standard General (40C)
Decided2006-07-24
Expires2011-07-24 · construction term (see Method)
Receiving waterBig Lake Mary,Lake Emma
Documents7
File lineage7 docs: 7 from seq 1 (2006)

seq 1 Modification of an existing stormwater management system for the City of Lake Mary's Street Pavement Program Phases 2 and 3, a 26.62-acre roadway paving project in Seminole County, utilizing Best Management Practices including swales with ditch blocks (SJRWMD Permit 42-117-1316NG-ERP under Chapter 40C-42, F.A.C., issued May 13, 1999). Permit·p.2

seq 1 Technical Staff Report for a Chapter 40C-42, F.A.C. general permit (application 42-117-1316ANG-ERP): a modification to an existing system for the Street Pavement Program Phases 2 and 3, a 26.62-acre roadway project treated by swales with ditch blocks, discharging to Lake Mary, Crystal Lake, and unnamed wetlands to the south (Class III waters). Technical Staff Report·p.2

seq 1 Administrative compliance submittal, not an engineering as-built: SJRWMD Permit Data Services change order request forms (largely handwritten) plus a typed renumbering sheet showing the stormwater application renumbered from 40-117-0577AG-ERP to 42-117-1316ANG-ERP on 5/6/99. No stormwater system design, discharge criteria, or infrastructure facts are stated. As-built·24 Jul 2006·p.4

Design documents on file Permit, Technical Staff Report

Not in the record Drainage calculations

City of Lake Mary Police Station Retention Pond 76781-3

ApplicantCity of Lake Mary
Rule typeERP Stormwater Standard General (40C)
Decided2013-05-22
Expires2018-05-22 · construction term (see Method)
Receiving waterCrystal Lake,Lake Mary
Documents8
File lineage8 docs: 8 from seq 1 (2007)

seq 1 Stormwater design calculations (CPH Engineers, revised April 20, 1999) for the City of Lake Mary Police Department, a 3.969-acre police station site in Lake Mary, Seminole County, FL, served by a dry retention pond (Pond A) whose pre-development outfall path is a swale along the railroad right-of-way with positive outfall to Lake Mary, then a stream, Lake Jessup, and the St. Johns River. Drainage calculations·27 Dec 2007·p.4

seq 1 SJRWMD permit 42-117-1336NG-ERP (issued May 18, 1999, under Chapter 40C-42 F.A.C.) authorizing a new stormwater system with treatment by retention to serve the City of Lake Mary New Police Station, a 3.97-acre project in Section 9, Township 20, Range 30 East, Seminole County. Permit·p.2

seq 1 SJRWMD Technical Staff Report for the Chapter 40C-42 F.A.C. general permit application (42-117-1336ANG-ERP) for the City of Lake Mary New Police Station: construction of a new police station with a dry roadside swale system, discharging to Lake Mary (Class III receiving water body). Technical Staff Report·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Medlin Professional Office 85947-1

ApplicantEEMJ/SM Family Trust
Rule typeERP Stormwater Standard General (40C)
Decided2002-10-29
Expires2007-10-29 · construction term (see Method)
Receiving waterCrystal Lake
Documents6

SJRWMD Standard General ERP Stormwater permit 42-117-85947-1, issued October 29, 2002 under Chapter 40C-42, F.A.C., authorizing construction and operation of the stormwater management system known as Medlin Professional Offices in Seminole County (Section 8, Township 20S, Range 30E). The authorized work is demolition of two buildings, filling the existing well, removal of two septic tanks, and construction of a new building, parking area, and a dry-retention pond. Permit·p.2

Bound drainage analysis by Roberts Engineering Inc. (Larry A. Roberts, P.E.) supporting the ERP application for Medlin Professional Offices at 2692 West Lake Mary Blvd., Seminole County. It contains PONDS 3.2 retention-pond recovery modeling of the proposed on-line retention/detention pond with an 8-inch outfall, comparing pre- and post-development runoff for the mean annual, 25-year/96-hour and 100-year/24-hour storms, plus pond stage-area tables, outlet control calculations, and a Universal Engineering Sciences geotechnical exploration report. Drainage calculations·9 Feb 2007·p.2

Technical Staff Report dated October 29, 2002 for application 42-117-85947-1, recommending a Standard General ERP Stormwater permit for construction and operation of the stormwater management system known as Medlin Professional Offices: demolition of two buildings, filling the existing well, removal of two septic tanks, and a new building, parking area, and dry-retention pond on a 1.010-acre commercial site in Seminole County discharging to Crystal Lake. Technical Staff Report·29 Oct 2002·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Seminole Ave Pond Expansion 86365-10

ApplicantCity of Lake Mary
Rule typeERP Individual
Decided2020-09-17
Expires2025-09-17 · construction term (see Method)
Receiving waterCrystal Lake
Documents12
File lineage12 docs: 12 from seq 1 (2002–2008)

seq 1 SJRWMD Chapter 40C-42 stormwater permit (No. 42-117-86365-1, issued November 26, 2002) authorizing construction and operation of the Shaw Construction stormwater management system in Lake Mary, Seminole County - a 0.62-acre commercial project consisting of a new office building, parking area, and a dry-retention pond. Permit·p.2

seq 1 Bound drainage calculation report (PONDS v3.2 'Retention Pond Recovery - Refined Method', by Ronald H. Wilson, P.E., dated 10-18-2002) for the Shaw Construction project, City of Lake Mary, Seminole County - a dry retention pond serving a 0.752-acre basin, modeled to fully retain both the 100yr/24hr and 25yr/96hr design storms with no surface discharge. Drainage calculations·7 Jan 2008·p.6

seq 1 SJRWMD Technical Staff Report (November 22, 2002) for standard general ERP stormwater permit application 42-117-86365-1: Shaw Construction, a 0.615-acre commercial project (new office building, parking area, dry-retention pond) on the east side of Lake Mary Boulevard south of I-4, Seminole County, in the Lake Monroe planning unit, using retention treatment and discharging to Dawson Lake (Class III Fresh). Technical Staff Report·26 Nov 2002·p.1

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

GTE Federal Credit Union-Lake Mary 87951-1

ApplicantGTE Federal Credit Union
Rule typeERP Stormwater Standard General (40C)
Decided2003-05-19
Expires2008-05-19 · construction term (see Method)
Receiving waterLake Mary
Documents8

Construction of a stormwater management system with stormwater treatment by retention for GTE Federal Credit Union-Lake Mary, a 2.63-acre commercial project in Seminole County, permitted under Chapter 40C-42, F.A.C. (SJRWMD permit 42-117-87951-1, issued May 19, 2003). Permit·p.2

Commercial development of a 3,200 sf bank with parking areas on a 2.63-acre site on Lake Mary Boulevard east of Longwood Lake Mary Road (Seminole County), served by a dry retention pond stormwater system; receiving water body is Lake Mary (Class III Fresh). Technical Staff Report·16 May 2003·p.1

Design documents on file Permit, Technical Staff Report, Construction plans

Not in the record Drainage calculations

Cambridge Prep School - Lake Mary Blvd. 98061-1

ApplicantLake Mary Cambridge LLC
Rule typeERP Stormwater Standard General (40C)
Decided2005-06-03
Expires2010-06-03 · construction term (see Method)
Receiving waterCrystal Lake
Documents16

Geotechnical subsurface exploration and analysis report supporting the proposed Cambridge Prep School childcare facility (approx. 2,300 sq ft) with associated parking and a stormwater retention pond on West Lake Mary Boulevard at 6th Street in Lake Mary, Florida. Drainage calculations·6 May 2005·p.2

Stormwater management report for development of a 7,400 SF child care facility and 11,191 SF of pavement on 1.01 acres on the north side of Lake Mary Blvd. in Lake Mary, Florida, served by a dry retention pond with a connected exfiltration system; pond overflow discharges to the Sixth Street right-of-way and ultimately to Crystal Lake. Drainage calculations·21 Mar 2005·p.6

SJRWMD stormwater permit no. 42-117-98061-1 (issued June 3, 2005, under Chapter 40C-42, F.A.C.) authorizing construction of a stormwater management system with stormwater treatment by exfiltration trench and retention for Cambridge Prep School - Lake Mary Blvd., a 1.01 acre project in Seminole County. Permit·3 Jun 2005·p.1

Technical staff report for a standard general ERP stormwater permit authorizing a stormwater management system with treatment by exfiltration trench and retention for Cambridge Prep School - Lake Mary Blvd., a 1.01-acre commercial child care project in Seminole County; site discharge is conveyed via a ditch to Crystal Lake (Class III Fresh). Technical Staff Report·3 Jun 2005·p.1

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Watson Center at Lake Mary 98533-1

ApplicantWatson Realty Corp
Rule typeERP Stormwater Standard General (40C)
Decided2006-07-03
Expires2011-07-03 · construction term (see Method)
Receiving waterCrystal Lake
Documents23
File lineage23 docs: 20 from this sequence, 3 unstated

Storm Drainage Report (Rockett & Associates, March 10, 2005) supporting the Watson Center at Lake Mary permit application: drainage design for a 15,532 sq. ft. office building on a 5.0784-acre parcel on Lake Mary Boulevard, Seminole County, using an off-line collection system that routes runoff to on-site stormwater ponds (Pond A and Pond B), documented with ICPR routing and PONDS retention-recovery modeling. Drainage calculations·31 May 2006·p.2

SJRWMD Chapter 40C-42 stormwater permit No. 42-117-98533-1 (issued July 3, 2006) to Watson Realty Corp authorizing construction and operation of a stormwater management system with treatment by an off-line retention pond for Watson Center at Lake Mary, a 5.08-acre commercial site in Section 16, Township 20S, Range 30E, Seminole County. Construction must follow plans received May 31, 2006 and revised sheets ENG-8 and ENG-10 received June 30, 2006. Permit·3 Jul 2006·p.1

Technical Staff Report (July 3, 2006) recommending issuance of Standard General Environmental Resource Stormwater Permit 42-117-98533-1 for construction of a stormwater management system with treatment by an off-line retention pond serving Watson Center at Lake Mary, a 5.078-acre new commercial development in Seminole County discharging to Crystal Lake. Technical Staff Report·3 Jul 2006·p.2

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Ruskin St, Johnson Ave, & S 4th St Paving & Drainage Improvements 98636-1

ApplicantCity of Lake Mary
Rule typeERP Stormwater Standard General (40C)
Decided2005-05-19
Expires2010-05-19 · construction term (see Method)
Receiving waterSoldier's Creek
Documents11

Cover/transmittal letter from HNTB Corporation submitting the SJRWMD permit application package (construction plans, permit application, and drainage calculations) for the Ruskin Street, Johnson Avenue and South 4th Street Paving and Drainage Improvements project in the City of Lake Mary, Florida. Drainage calculations·25 Apr 2005·p.1

ERP application and drainage calculation package for paving three existing dirt roads (Ruskin Street, Johnson Avenue, South 4th Street) in the City of Lake Mary to alleviate existing flooding; roadside swales with ditch bottom inlets collect runoff, outfalling through an existing storm sewer to an existing dry retention pond along South 4th Street with eventual discharge to a wetland contributory of Soldier's Creek. Drainage calculations·25 Apr 2005·p.51

SJRWMD Permit No. 42-117-98636-1 (Chapter 40C-42, F.A.C., issued May 19, 2005) authorizing modification and operation of a stormwater management system with treatment by swales with ditch blocks for the Ruskin St, Johnson Ave, & S 4th St Paving & Drainage Improvements, a 1.64-acre roadway project in the City of Lake Mary, Seminole County. Permit·19 May 2005·p.1

Technical Staff Report for SJRWMD application 42-117-98636-1: the City of Lake Mary proposes to pave three dirt roadways (Ruskin Street, Johnson Avenue, South 4th Street) totaling approximately 1,524 linear feet, a 1.64-acre roadway project with stormwater treatment by swales with ditch blocks, discharging to Soldier's Creek (Class III). Technical Staff Report·19 May 2005·p.1

Design documents on file Permit, Technical Staff Report, Drainage calculations, Construction plans

Part 08

Document index

Every file in the permit record, by permit — each one openable. Document opens the copy delivered with this report; district opens the same file on the district’s own site, which is the copy that governs. Any file we could not retrieve is listed and marked, never omitted.

103055-1CNBS - Lake Mary28 docs · 4 priority · 182 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 23 Mar 2006 8 district↗
Technical Staff Report Technical Staff Report 23 Mar 2006 3 district↗
Drainage calculations Drainage calculations 5 Sep 2008 48 district↗
Drainage calculations Drainage calculations 28 Dec 2005 42 district↗
Construction plans Construction plans 5 Jun 2008 11 district↗
Request for additional info Request for additional information 25 Jan 2006 4 district↗
Request for additional info Request for additional information 23 Feb 2006 19 district↗
Application Application 28 Dec 2005 4 district↗
Application Application 13 Jul 2009 2 district↗
Application Application 2 Sep 2009 3 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 26 Jan 2006 1 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 11 Jan 2006 2 district↗
Correspondence Correspondence 28 Dec 2005 2 district↗
Correspondence Correspondence 9 Jun 2009 4 district↗
Correspondence Correspondence 13 Jul 2009 4 district↗
Application Other 28 Dec 2005 1 district↗
Application Other 28 Dec 2005 2 district↗
Application Other 28 Dec 2005 2 district↗
108660-2Washington Estates40 docs · 5 priority · 473 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 27 Mar 2007 9 district↗
Technical Staff Report Technical Staff Report 27 Mar 2007 2 district↗
Drainage calculations Drainage calculations 21 Feb 2007 9 district↗
Drainage calculations Drainage calculations 21 Feb 2007 51 district↗
Drainage calculations Drainage calculations 21 Nov 2006 51 district↗
Construction plans Construction plans 21 Nov 2006 11 district↗
Construction plans Construction plans 27 Feb 2007 11 district↗
Construction plans Construction plans 18 Oct 2007 1 district↗
Construction plans Construction plans 22 Jan 2007 11 district↗
Construction plans Construction plans 12 May 2010 23 district↗
Construction plans Construction plans 27 Feb 2007 6 district↗
Request for additional info Request for additional information 19 Dec 2006 4 district↗
Request for additional info Request for additional information 16 Feb 2007 4 district↗
Request for additional info Request for additional information 27 Feb 2007 96 district↗
Request for additional info Request for additional information 22 Jan 2007 57 district↗
Request for additional info Request for additional information 22 Jan 2007 2 district↗
Request for additional info Request for additional information 22 Jan 2007 15 district↗
Request for additional info Request for additional information 22 Jan 2007 12 district↗
Application Application 21 Nov 2006 4 district↗
Application Application 21 Nov 2006 17 district↗
Correspondence Correspondence 8 Oct 2008 4 district↗
Correspondence Correspondence 8 Oct 2008 37 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Sep 2008 2 district↗
Correspondence Correspondence 23 Feb 2007 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 5 Dec 2006 2 district↗
Correspondence Correspondence 8 Jan 2007 2 district↗
Correspondence Correspondence 21 Nov 2006 3 district↗
Application Other 21 Nov 2006 1 district↗
Application Other 21 Nov 2006 2 district↗
110309-1CR 15 from Ranoul Lane to CR 46A37 docs · 5 priority · 528 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 7 Aug 2007 9 district↗
Technical Staff Report Technical Staff Report 7 Aug 2007 2 district↗
Drainage calculations Drainage calculations 15 Mar 2007 59 district↗
Drainage calculations Drainage calculations 26 Apr 2010 63 district↗
Drainage calculations Drainage calculations 12 May 2010 63 district↗
Construction plans Construction plans 8 Oct 2008 125 district↗
Construction plans Construction plans 15 Mar 2007 124 district↗
Construction plans Construction plans 26 Apr 2010 8 district↗
Construction plans Construction plans 12 May 2010 8 district↗
Request for additional info Request for additional information 11 Apr 2007 4 district↗
Request for additional info Request for additional information 3 Aug 2007 3 district↗
Request for additional info Request for additional information 10 May 2007 12 district↗
Application Application 15 Mar 2007 4 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 13 Apr 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 30 Mar 2007 1 district↗
Correspondence Correspondence 4 Jun 2007 3 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 8 Oct 2008 2 district↗
Correspondence Correspondence 23 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 23 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 27 Mar 2007 2 district↗
Correspondence Correspondence 15 Mar 2007 2 district↗
Correspondence Correspondence 26 Apr 2010 3 district↗
Correspondence Correspondence 12 May 2010 3 district↗
Review Documents Other 26 Mar 2007 district↗
Review Documents Other 26 Mar 2007 district↗
Application Other 15 Mar 2007 1 district↗
Application Other 15 Mar 2007 1 district↗
114454-14Central Florida Commuter Rail - Lake Mary…188 docs · 13 priority · 1662 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 12 Dec 2007 3 district↗
Permit Permit 20 Oct 2008 9 district↗
Technical Staff Report Technical Staff Report 14 Oct 2008 17 district↗
Technical Staff Report Technical Staff Report 20 Oct 2008 12 district↗
Drainage calculations Drainage calculations 12 Dec 2007 14 district↗
Drainage calculations Drainage calculations 12 Dec 2007 10 district↗
Drainage calculations Drainage calculations 12 Dec 2007 46 district↗
Drainage calculations Drainage calculations 12 Dec 2007 46 district↗
Drainage calculations Drainage calculations 12 Dec 2007 2 district↗
Drainage calculations Drainage calculations 12 Dec 2007 132 district↗
Drainage calculations Drainage calculations 12 Dec 2007 7 district↗
Drainage calculations Drainage calculations 12 Dec 2007 12 district↗
Drainage calculations Drainage calculations 12 Dec 2007 50 district↗
Construction plans Construction plans 12 Dec 2007 10 district↗
Construction plans Construction plans 27 Mar 2008 3 district↗
Construction plans Construction plans 12 Dec 2007 8 district↗
Construction plans Construction plans 12 Dec 2007 6 district↗
Construction plans Construction plans 12 Dec 2007 12 district↗
Construction plans Construction plans 12 Dec 2007 1 district↗
Construction plans Construction plans 12 Dec 2007 20 district↗
Construction plans Construction plans 12 Dec 2007 5 district↗
Construction plans Construction plans 12 Dec 2007 7 district↗
Construction plans Construction plans 12 Dec 2007 121 district↗
Construction plans Construction plans 12 Dec 2007 77 district↗
Construction plans Construction plans 12 Dec 2007 103 district↗
Construction plans Construction plans 12 Dec 2007 35 district↗
Request for additional info Request for additional information 15 Aug 2008 54 district↗
Request for additional info Request for additional information 26 Mar 2008 1 district↗
Request for additional info Request for additional information 9 Jan 2008 4 district↗
Request for additional info Request for additional information 26 Mar 2008 1 district↗
Request for additional info Request for additional information 26 Mar 2008 4 district↗
Request for additional info Request for additional information 26 Mar 2008 6 district↗
Request for additional info Request for additional information 15 Aug 2008 12 district↗
Request for additional info Request for additional information 15 Aug 2008 6 district↗
Request for additional info Request for additional information 15 Aug 2008 8 district↗
Request for additional info Request for additional information 23 Apr 2008 8 district↗
Request for additional info Request for additional information 26 Mar 2008 4 district↗
Request for additional info Request for additional information 26 Mar 2008 2 district↗
Application Application 12 Dec 2007 28 district↗
Application Application 12 Dec 2007 4 district↗
Application Application 13 Dec 2007 4 district↗
Correspondence Correspondence 22 Jan 2008 1 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 2 Apr 2008 1 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 26 Sep 2008 16 district↗
Correspondence Correspondence 30 Sep 2008 6 district↗
Correspondence Correspondence 30 Sep 2008 1 district↗
Correspondence Correspondence 2 Oct 2008 1 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Mar 2008 20 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 5 Mar 2008 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Mar 2008 7 district↗
Correspondence Correspondence 2 Apr 2008 4 district↗
Correspondence Correspondence 2 Jan 2008 1 district↗
Correspondence Correspondence 7 Jan 2008 1 district↗
Correspondence Correspondence 17 Dec 2007 2 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 3 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 10 Sep 2008 7 district↗
Correspondence Correspondence 13 Oct 2008 5 district↗
Correspondence Correspondence 11 Jan 2008 2 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 8 Oct 2008 1 district↗
Correspondence Correspondence 2 Jan 2008 1 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 14 Dec 2007 3 district↗
Correspondence Correspondence 30 Sep 2008 5 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 3 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 12 Dec 2007 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 13 Dec 2007 2 district↗
Correspondence Correspondence 27 Mar 2008 4 district↗
Correspondence Correspondence 24 Sep 2008 2 district↗
Correspondence Correspondence 17 Dec 2007 2 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 3 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 14 Dec 2007 3 district↗
Correspondence Correspondence 23 Sep 2008 2 district↗
Correspondence Correspondence 26 Sep 2008 1 district↗
Correspondence Correspondence 6 Oct 2008 1 district↗
Correspondence Correspondence 17 Dec 2007 2 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 24 Sep 2008 6 district↗
Correspondence Correspondence 28 Dec 2007 1 district↗
Correspondence Correspondence 12 Dec 2007 1 district↗
Correspondence Correspondence 13 Dec 2007 13 district↗
Correspondence Correspondence 16 Oct 2008 1 district↗
Correspondence Correspondence 14 Jun 2010 1 district↗
Correspondence Correspondence 14 Jun 2010 1 district↗
Correspondence Correspondence 14 Jun 2010 5 district↗
Correspondence Correspondence 6 Apr 2011 1 district↗
Correspondence Correspondence 6 Apr 2011 1 district↗
Correspondence Correspondence 6 Apr 2011 5 district↗
Correspondence Correspondence 6 Sep 2011 71 district↗
Correspondence Correspondence 6 Jul 2011 1 district↗
Correspondence Correspondence 6 Jul 2011 5 district↗
Correspondence Correspondence 6 Jul 2011 1 district↗
Correspondence Correspondence 6 Jul 2011 21 district↗
Correspondence Correspondence 21 Feb 2012 1 district↗
Correspondence Correspondence 21 Feb 2012 1 district↗
Correspondence Correspondence 22 Feb 2012 1 district↗
Correspondence Correspondence 22 Feb 2012 1 district↗
Correspondence Correspondence 22 Feb 2012 1 district↗
Correspondence Correspondence 6 Mar 2012 1 district↗
Review Documents Other 13 Dec 2007 district↗
Review Documents Other 13 Dec 2007 district↗
Review Documents Other 1 Oct 2008 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 11 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 11 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 13 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 9 district↗
Application Other 12 Dec 2007 14 district↗
Application Other 12 Dec 2007 2 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 6 district↗
Application Other 12 Dec 2007 6 district↗
Application Other 12 Dec 2007 6 district↗
Application Other 12 Dec 2007 27 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 40 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 20 district↗
Application Other 12 Dec 2007 14 district↗
Application Other 12 Dec 2007 13 district↗
Application Other 12 Dec 2007 13 district↗
Application Other 12 Dec 2007 86 district↗
Application Other 12 Dec 2007 7 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 12 Dec 2007 9 district↗
Application Other 12 Dec 2007 1 district↗
Application Other 13 Dec 2007 1 district↗
123954-1Carli Professional Office Building22 docs · 3 priority · 140 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 15 Jun 2010 8 district↗
Technical Staff Report Technical Staff Report 9 Jun 2010 5 district↗
Drainage calculations Drainage calculations 17 Mar 2010 77 district↗
Construction plans Construction plans 17 Mar 2010 7 district↗
Request for additional info Request for additional information 13 Apr 2010 3 district↗
Request for additional info Request for additional information 20 May 2010 1 district↗
Request for additional info Request for additional information 20 May 2010 2 district↗
Request for additional info Request for additional information 20 May 2010 3 district↗
Request for additional info Request for additional information 20 May 2010 1 district↗
Request for additional info Request for additional information 20 May 2010 8 district↗
Application Application 17 Mar 2010 4 district↗
Correspondence Correspondence 17 Mar 2010 3 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Correspondence Correspondence 31 Mar 2010 2 district↗
Application Other 17 Mar 2010 1 district↗
Application Other 17 Mar 2010 1 district↗
141317-1Lake Mary Pediatric Medical Office30 docs · 4 priority · 256 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 10 Apr 2015 13 district↗
Permit Permit 10 Apr 2015 district↗
Technical Staff Report Technical Staff Report 10 Apr 2015 7 district↗
Drainage calculations Drainage calculations 18 Mar 2015 65 district↗
Construction plans Construction plans 18 Mar 2015 3 district↗
Construction plans Construction plans 18 Mar 2015 1 district↗
Application Application 18 Mar 2015 9 district↗
Correspondence Correspondence 18 Mar 2015 2 district↗
Correspondence Correspondence 18 Mar 2015 2 district↗
Correspondence Correspondence 18 Mar 2015 2 district↗
Correspondence Correspondence 18 Mar 2015 2 district↗
Correspondence Correspondence 18 Mar 2015 2 district↗
Correspondence Correspondence 20 Mar 2015 2 district↗
Correspondence Correspondence 20 Mar 2015 1 district↗
Correspondence Correspondence 26 Mar 2015 1 district↗
Correspondence Correspondence 9 Apr 2015 18 district↗
Correspondence Correspondence 9 Apr 2015 18 district↗
Correspondence Correspondence 10 Apr 2015 4 district↗
Correspondence Correspondence 10 Apr 2015 4 district↗
Correspondence Correspondence 10 Apr 2015 4 district↗
Correspondence Correspondence 20 May 2015 1 district↗
Correspondence Correspondence 15 Jan 2016 3 district↗
Correspondence Correspondence 22 Jan 2016 3 district↗
Application Other 18 Mar 2015 1 district↗
Application Other 18 Mar 2015 2 district↗
Application Other 18 Mar 2015 1 district↗
Application Other 18 Mar 2015 1 district↗
Application Other 18 Mar 2015 82 district↗
Review Documents Other 18 Mar 2015 1 district↗
Review Documents Other 7 Apr 2015 1 district↗
214983-1South Country Club Drainage Improvements14 docs · 3 priority · 61 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 7 Mar 2024 12 district↗
Permit Permit 7 Mar 2024 district↗
Technical Staff Report Technical Staff Report 7 Mar 2024 5 district↗
Construction plans Construction plans 8 Feb 2024 9 district↗
Application Application 8 Feb 2024 6 district↗
Correspondence Correspondence 4 Mar 2024 1 district↗
Correspondence Correspondence 4 Mar 2024 1 district↗
Correspondence Correspondence 4 Mar 2024 1 district↗
Application Other 8 Feb 2024 6 district↗
Application Other 8 Feb 2024 2 district↗
Application Other 8 Feb 2024 6 district↗
Application Other 8 Feb 2024 district↗
Application Other 8 Feb 2024 6 district↗
Application Other 8 Feb 2024 6 district↗
21945-19Lake Mary Boulevard , Phase II: pedestrian…12 docs · 4 priority · 330 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 5 district↗
Technical Staff Report Technical Staff Report 8 district↗
Drainage calculations Drainage calculations 17 Sep 2007 42 district↗
Construction plans Construction plans 17 Sep 2007 48 district↗
Construction plans Construction plans 17 Sep 2007 25 district↗
Construction plans Construction plans 5 Aug 2008 6 district↗
As-built As-built 17 Sep 2007 89 district↗
Application Application 17 Sep 2007 8 district↗
Correspondence Correspondence 17 Sep 2007 26 district↗
Correspondence Correspondence 43 district↗
Correspondence Correspondence 5 Aug 2008 28 district↗
Correspondence Correspondence 17 Sep 2007 2 district↗
22463-2Woodbridge Lk Phase 2C12 docs · 4 priority · 877 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 10 district↗
Technical Staff Report Technical Staff Report 20 district↗
Drainage calculations Drainage calculations 20 Mar 2007 450 district↗
Construction plans Construction plans 20 Mar 2007 25 district↗
As-built As-built 20 Mar 2007 107 district↗
Application Application 20 Mar 2007 34 district↗
Correspondence Correspondence 20 Mar 2007 3 district↗
Correspondence Correspondence 135 district↗
Correspondence Correspondence 20 Mar 2007 37 district↗
Correspondence Correspondence 22 Jul 2008 7 district↗
Correspondence Correspondence 31 Mar 2004 49 district↗
Review Documents Other 19 Jun 2025 district↗
237414-1Crystal Lake Condos41 docs · 6 priority · 313 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 29 Dec 2025 12 district↗
Permit Permit 29 Dec 2025 district↗
Technical Staff Report Technical Staff Report 29 Dec 2025 7 district↗
Drainage calculations Drainage calculations 12 Jun 2025 39 district↗
Drainage calculations Drainage calculations 12 Jun 2025 17 district↗
Construction plans Construction plans 12 Jun 2025 10 district↗
Request for additional info Request for additional information 10 Jul 2025 4 district↗
Request for additional info Request for additional information 10 Jul 2025 district↗
Request for additional info Request for additional information 10 Jul 2025 district↗
Request for additional info Request for additional information 14 Aug 2025 19 district↗
Request for additional info Request for additional information 14 Aug 2025 4 district↗
Request for additional info Request for additional information 14 Aug 2025 40 district↗
Request for additional info Request for additional information 14 Aug 2025 2 district↗
Request for additional info Request for additional information 14 Aug 2025 4 district↗
Request for additional info Request for additional information 14 Aug 2025 1 district↗
Request for additional info Request for additional information 22 Sep 2025 18 district↗
Request for additional info Request for additional information 22 Sep 2025 2 district↗
Request for additional info Request for additional information 24 Oct 2025 13 district↗
Request for additional info Request for additional information 24 Oct 2025 19 district↗
Request for additional info Request for additional information 24 Oct 2025 2 district↗
Request for additional info Request for additional information 24 Oct 2025 40 district↗
Request for additional info Request for additional information 24 Oct 2025 4 district↗
Request for additional info Request for additional information 1 Dec 2025 9 district↗
Certification of completion Certification of completion 29 Dec 2025 1 district↗
Application Application 12 Jun 2025 9 district↗
Correspondence Correspondence 24 Jul 2025 1 district↗
Correspondence Correspondence 24 Jul 2025 1 district↗
Correspondence Correspondence 22 Sep 2025 district↗
Correspondence Correspondence 22 Sep 2025 district↗
Correspondence Correspondence 15 Oct 2025 2 district↗
Correspondence Correspondence 15 Oct 2025 4 district↗
Correspondence Correspondence 11 Sep 2025 3 district↗
Correspondence Correspondence 19 Nov 2025 13 district↗
Correspondence Correspondence 21 Nov 2025 1 district↗
Correspondence Correspondence 1 Dec 2025 2 district↗
Correspondence Correspondence 30 Jan 2026 3 district↗
Correspondence Correspondence 4 Feb 2026 3 district↗
Application Other 12 Jun 2025 district↗
Application Other 12 Jun 2025 1 district↗
Application Other 12 Jun 2025 2 district↗
Application Other 12 Jun 2025 1 district↗
48694-7Lake Mary Elementary School4 docs · 0 priority · 80 pp · governing
DocumentClassified asDatePagesSource
Correspondence Correspondence 8 Oct 2008 2 district↗
Correspondence Correspondence 6 Aug 2008 3 district↗
Correspondence Correspondence 21 Apr 2006 73 district↗
Correspondence Correspondence 8 Oct 2008 2 district↗
49830-3Rainbow Child Care Center8 docs · 3 priority · 208 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 8 district↗
Technical Staff Report Technical Staff Report 2 district↗
Drainage calculations Drainage calculations 30 Jan 2006 72 district↗
Construction plans Construction plans 30 Jan 2006 15 district↗
Application Application 30 Jan 2006 10 district↗
Correspondence Correspondence 30 Jan 2006 16 district↗
Correspondence Correspondence 30 Jan 2006 3 district↗
Correspondence Correspondence 82 district↗
69432-1JR Academy of Lake Mary7 docs · 3 priority · 181 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 10 district↗
Technical Staff Report Technical Staff Report 26 Jan 2001 2 district↗
Drainage calculations Drainage calculations 22 Sep 2006 44 district↗
Construction plans Construction plans 22 Sep 2006 5 district↗
Application Application 22 Sep 2006 11 district↗
Correspondence Correspondence 22 Sep 2006 11 district↗
Correspondence Correspondence 98 district↗
71294-1Regency Pointe Commercial/Professional…10 docs · 4 priority · 537 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 10 district↗
Technical Staff Report Technical Staff Report 17 Sep 2001 2 district↗
Drainage calculations Drainage calculations 22 Sep 2006 313 district↗
Construction plans Construction plans 25 Sep 2006 12 district↗
Request for additional info Request for additional information 5 Jun 2001 district↗
Request for additional info Request for additional information 13 Aug 2001 district↗
As-built As-built 22 Sep 2006 12 district↗
Application Application 22 Sep 2006 14 district↗
Correspondence Correspondence 22 Sep 2006 75 district↗
Correspondence Correspondence 99 district↗
76767-3Cold Mix Paving of City's dirt streets…7 docs · 3 priority · 205 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 8 district↗
Technical Staff Report Technical Staff Report 3 district↗
As-built As-built 24 Jul 2006 4 district↗
Application Application 24 Jul 2006 19 district↗
Correspondence Correspondence 24 Jul 2006 5 district↗
Correspondence Correspondence 96 district↗
Correspondence Correspondence 24 Jul 2006 70 district↗
76781-3City of Lake Mary Police Station Retention…8 docs · 3 priority · 242 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 8 district↗
Technical Staff Report Technical Staff Report 2 district↗
Drainage calculations Drainage calculations 27 Dec 2007 102 district↗
Construction plans Construction plans 27 Dec 2007 9 district↗
Application Application 27 Dec 2007 12 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 89 district↗
Correspondence Correspondence 27 Dec 2007 18 district↗
85947-1Medlin Professional Office6 docs · 3 priority · 193 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 9 district↗
Technical Staff Report Technical Staff Report 29 Oct 2002 3 district↗
Drainage calculations Drainage calculations 9 Feb 2007 63 district↗
Construction plans Construction plans 12 Feb 2007 8 district↗
Application Application 9 Feb 2007 21 district↗
Correspondence Correspondence 89 district↗
86365-10Seminole Ave Pond Expansion12 docs · 3 priority · 287 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 9 district↗
Technical Staff Report Technical Staff Report 26 Nov 2002 3 district↗
Drainage calculations Drainage calculations 7 Jan 2008 104 district↗
Construction plans Construction plans 7 Jan 2008 6 district↗
Construction plans Construction plans 9 Apr 2008 6 district↗
Construction plans Construction plans 15 Apr 2008 6 district↗
Application Application 7 Jan 2008 18 district↗
Correspondence Correspondence 7 Jan 2008 20 district↗
Correspondence Correspondence 28 Jun 2006 6 district↗
Correspondence Correspondence 8 Oct 2008 20 district↗
Correspondence Correspondence 87 district↗
Correspondence Correspondence 7 Jan 2008 2 district↗
87951-1GTE Federal Credit Union-Lake Mary8 docs · 2 priority · 193 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 9 district↗
Technical Staff Report Technical Staff Report 16 May 2003 2 district↗
Construction plans Construction plans 27 Dec 2007 9 district↗
Request for additional info Request for additional information 9 Apr 2003 district↗
Application Application 27 Dec 2007 87 district↗
Correspondence Correspondence 27 Dec 2007 2 district↗
Correspondence Correspondence 27 Dec 2007 73 district↗
Correspondence Correspondence 11 district↗
98061-1Cambridge Prep School - Lake Mary Blvd.16 docs · 4 priority · 138 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 3 Jun 2005 8 district↗
Technical Staff Report Technical Staff Report 3 Jun 2005 2 district↗
Drainage calculations Drainage calculations 6 May 2005 23 district↗
Drainage calculations Drainage calculations 21 Mar 2005 33 district↗
Construction plans Construction plans 2 May 2008 17 district↗
Request for additional info Request for additional information 6 May 2005 37 district↗
Request for additional info Request for additional information 13 Apr 2005 2 district↗
Application Application 21 Mar 2005 4 district↗
Correspondence Correspondence 8 Oct 2008 2 district↗
Correspondence Correspondence 20 Apr 2005 2 district↗
Correspondence Correspondence 11 Apr 2005 1 district↗
Correspondence Correspondence 3 Jun 2005 1 district↗
Correspondence Correspondence 21 Mar 2005 2 district↗
Application Other 3 Jun 2005 1 district↗
Application Other 21 Mar 2005 2 district↗
Application Other 21 Mar 2005 1 district↗
98533-1Watson Center at Lake Mary23 docs · 3 priority · 231 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 3 Jul 2006 8 district↗
Technical Staff Report Technical Staff Report 3 Jul 2006 3 district↗
Drainage calculations Drainage calculations 31 May 2006 51 district↗
Construction plans Construction plans 2 May 2008 17 district↗
Construction plans Construction plans 30 Jun 2006 9 district↗
Request for additional info Request for additional information 18 May 2005 4 district↗
Request for additional info Request for additional information 31 May 2006 100 district↗
Application Application 31 May 2006 15 district↗
Correspondence Correspondence 9 May 2005 1 district↗
Correspondence Correspondence 27 Apr 2005 4 district↗
Correspondence Correspondence 30 Jun 2006 1 district↗
Correspondence Correspondence 13 May 2005 1 district↗
Correspondence Correspondence 31 May 2006 1 district↗
Correspondence Correspondence 12 May 2005 1 district↗
Correspondence Correspondence 31 May 2006 3 district↗
Correspondence Correspondence 9 Jun 2009 2 district↗
Correspondence Correspondence 12 May 2005 4 district↗
Correspondence Correspondence 18 May 2005 1 district↗
Review Documents Other 26 Apr 2005 district↗
Review Documents Other 26 Apr 2005 district↗
Application Other 18 Apr 2005 1 district↗
Application Other 18 Apr 2005 2 district↗
Application Other 31 May 2006 2 district↗
98636-1Ruskin St, Johnson Ave, & S 4th St…11 docs · 4 priority · 104 pp · governing
DocumentClassified asDatePagesSource
Permit Permit 19 May 2005 8 district↗
Technical Staff Report Technical Staff Report 19 May 2005 2 district↗
Drainage calculations Drainage calculations 25 Apr 2005 1 district↗
Drainage calculations Drainage calculations 25 Apr 2005 53 district↗
Construction plans Construction plans 25 Apr 2005 20 district↗
Application Application 25 Apr 2005 10 district↗
Correspondence Correspondence 7 Sep 2006 2 district↗
Correspondence Correspondence 25 Apr 2005 3 district↗
Application Other 25 Apr 2005 1 district↗
Application Other 25 Apr 2005 2 district↗
Application Other 25 Apr 2005 2 district↗

Part 09

Failed verification — quarantined

6 entries failed the page-image check — the cited page does not support the value as extracted. Counted in the statistics, excluded from every register. Read the source before relying on anything here.

PermitFieldExtracted valueCitationWhy it failed
114454-14 Conveyance swales Proposed swales adjacent to the tracks intended to pick up any pollutants; District staff expressed concern about swales cut into wet… Drainage calculations·12 Dec 2007·p.2 visual tier-2 (agent): Page 2 is a bridge plan/elevation drawing with no swale or pollutant text anywhere on it; the claimed swale statement does not appear on…
114454-14 Project purpose Appendix G (Pre-Application Meeting Minutes) of the CFCRT stormwater report - minutes of two pre-application meetings (FDOT April 16, 2007… Drainage calculations·12 Dec 2007·p.2 visual tier-2 (agent): M.P. 763.1 ST. JOHN'S RIVER - PRELIM. / CENTRAL FLORIDA COMMUTER RAIL TRANSIT / FLORIDA DEPARTMENT OF TRANSPORTATION - Page 2 is an…
114454-14 Project purpose Appendix H (Environmental Considerations Attachments) of the CFCRT stormwater report - agency coordination materials including a Florida… Drainage calculations·12 Dec 2007·p.2 visual tier-2 (agent): Conveyance Ditch Profile | Project: Commuter Rail | Location: Seminole/Orange | Ditch Profile Left Side / Ditch Profile Right Side -…
114454-14 Water quality treatment determination For the tracks it was determined there would be no water quality or pre-post requirements based on existing/proposed pervious surfaces… Drainage calculations·12 Dec 2007·p.2 visual tier-2 (agent): Page 2 is a bridge drawing sheet (piers, spans, box beams) with no text about water quality, pre/post requirements, curve numbers, or…
114454-14 Parking site permitting Each proposed parking/station site requires a General Stormwater Permit as specified in the St. Johns MSSW Handbook Drainage calculations·12 Dec 2007·p.2 visual tier-2 (agent): Page 2 is a bridge drawing sheet containing no mention of a General Stormwater Permit or the St. Johns MSSW Handbook; the closest…
114454-14 Listed species records FWC database indicates listed species occurrence data are located within or adjacent to the project area (Volusia County); maps of listed… Drainage calculations·12 Dec 2007·p.2 visual tier-2 (agent): Conveyance Ditch Profile | Project: Commuter Rail | Location: Seminole/Orange | table rows e.g. '40790+00 56.7 2.06 Special…

Part 10

Method & limits

Source
Permits and documents were retrieved from the St. Johns River Water Management District public ERP record, filter UPPER(RULE_TYPE_DESC) NOT LIKE '%CONSUMPTIVE%'. Only issued permits are reported.
Study-area geometry
The boundary in Part 01 is the geometry actually queried — fingerprint SHA-256 ef7112e961c7b315… over its GeoJSON coordinates, serialised without whitespace. Re-submitting the same coordinates against the same index layer reproduces this sweep. The intersection test is the district service’s own spatial query against its published permit geometry; that geometry is the district’s record of the permit’s extent, not a cadastral survey.
Supersession
Permit records are grouped by official permit number and ordered by sequence. The highest sequence is reported as governing; earlier sequences are listed as superseded. Supersession orders the record — it does not by itself resolve which conditions of an earlier sequence were carried forward, modified, or extinguished; where that distinction matters, read the governing sequence’s own authorization at the cited source.
Sequence lineage
The district’s document listing returns a permit’s complete file — every sequence, not only the governing one. Filenames carry their sequence of origin; every extracted entry in this report is attributed to its source sequence and labelled when it belongs to an earlier one. Where a governing sequence has no retrieved documents of its own, the report says so on the card rather than presenting older material as current. A filename that states no sequence is reported as unattributed, never guessed.
Document classification
Documents are sorted into engineer priority categories using the District’s own document typing and the document title, falling back to first-page text where the typing is ambiguous.
Depth measurement
The depth threshold in Part 03 is not a fixed number. It is the page count of the longest permit letter or technical staff report in this study area — 20 pages — so a citation past it is past the end of every summary document in the record. Depth is measured from the citation page recorded at extraction, against the page count of the retrieved file.
Citation verification (page-location)
Every extracted value carries the document and page it was read from, and is checked in two tiers. Tier 1 matches the supporting quotation against the text of that page: verified means the quotation was located on the cited page. Where tier 1 fails — nearly always a scanned or handwritten page with no reliable text layer — tier 2 renders the page as an image and verifies the value visually: page image means the fact was confirmed on the page image; needs review means the page does not support the value. unchecked marks a value not yet checked at tier 2 — read it at the source before relying on it. What this metric is: page-location verification establishes that the supporting text or value exists where the citation says it does. It is a check on citation integrity, not a review of the engineering interpretation built on it — a value can sit verified on its page and still be read wrongly in context. That review is what the cited sources, delivered with this report, are for. Values that FAIL the page-image check are quarantined in Part 09 rather than rendered beside relied-upon findings.
Vertical datum
Elevations are reported exactly as stated in their source documents. Of 82 elevation-class values in this report, 2 state a vertical datum on the cited page; the rest do not, and none is assumed — Central Florida ERP records of this era may reference either NGVD29 or NAVD88, and the difference is roughly a foot. Where a datum matters to a design decision, confirm it at the cited source.
Expiration dates
The “Expires” date on a permit card is the construction-authorization term as recorded by the district. Operation-and-maintenance obligations under an environmental resource permit generally continue beyond the construction term, so an expired date does not read as “no longer governs” — the governing label reflects the district’s current-sequence record as of the query date, and cards whose construction term has passed say so.
Coverage limits
Documents above the retrieval size limit are indexed but not read inline; they are listed in Part 08 and delivered with the source set. Construction plan sets are indexed, not parsed.
Standing
This is a research deliverable. It does not constitute engineering design or a regulatory determination, and it is not sealed. Where a value matters to a design decision, read it at the source document cited.
Remedy
If a governing permit inside this study area is missing from this report, tell us which one and the study area is refunded in full and re-run at no charge. Every value here is cited to its document and page so that claim can be checked rather than trusted.

Sounding Research · Report 20260724-105810 · 10 August 2026 · 544 documents, 104 pages indexed for this study area. Set in Source Serif 4 and IBM Plex (SIL Open Font License 1.1).